Recently,Asphal Corp. received a report from an external consulting a Quality Costs Report that totally costs...

  1. Recently,Asphal Corp. received a report from an external consulting a Quality Costs Report that totally costs is 21% of its sales. Raynaldo and Richiekun are directors of that company and try to improve the Quality Product and Services by determined A Quality Improvement Program(QIP) to reduced to 17% costs to total revenue. Vintachan as controller tr to reduce the Costs of Quality below:

    no

    Costs

    Before QIP

    After QIP

    1

    Warranty

    $ 1,200

    $900

    2

    Quality Planning

    2,800

    3,200

    3

    Product Acceptance

    2,300

    2,800

    4

    Disposal Costs

    700

    500

    5

    Scrap

    600

    400

    6

    Field Inspection

    1,100

    1,300

    7

    Complain adjustment

    1,000

    900

    8

    Downtime

    900

    600

    9

    Returned materials

    600

    400

    10

    Quality audits

    1,500

    1,800

    11

    Packaging inspection

    800

    900

    12

    Quality Circles

    2,600

    2,900

    13

    Product recalls

    700

    300

    14

    Machine downtime

    400

    300

    15

    New product review

    1800

    2,100


    Required: a) Cost of Quality report before and After QIP    b) is there any improvement, explain

Solutions

Expert Solution

a)


Related Solutions

Dividends received from a domestic corporation are totally sourced to the U.S. if: a.         the corporation earns...
Dividends received from a domestic corporation are totally sourced to the U.S. if: a.         the corporation earns at least 80% of its gross income over the immediately preceding three tax years from the active conduct of a U.S. trade or business. b.         the corporation earns at least 25% of its gross income over the immediately preceding three tax years from the active conduct of a U.S. trade or business. c.         the corporation earns no more than 80% of its gross income over the...
Alma and Associates, a new consulting service, recently received a bill for repairs on its.
BE  154 Alma and Associates, a new consulting service, recently received a bill for repairs on its computers totaling $2,280. Alma thinks it may have been overcharged and is trying to recreate the components of the bill. She knows the hourly rate is $75 and 15 hours of labor was charged. She also knows $700 of parts were replaced.   Instructions Compute the material loading charge percentage the repair service used. BE  155 Freberg Company, a division of Dudge Cars,...
Classify the following quality costs as prevention costs, appraisal costs, internal failure costs, or external failure...
Classify the following quality costs as prevention costs, appraisal costs, internal failure costs, or external failure costs: 1. Internal audit to ensure that quality guidelines and processes are being followed 2. Repairing products in the field 3. Providing engineering assistance to selected suppliers to improve their product quality 4. Correcting a design error discovered during product development 5. Settling a bodily injury law suit caused by a defective product 6. Customer complaint department 7. Quality control circles 8. Continuing supplier...
Which of the following is true about quality management systems? A. External failure costs are the...
Which of the following is true about quality management systems? A. External failure costs are the easiest quality costs to measure. B. Businesses should invest upfront in prevention and appraisal costs. C. Quality management systems only use financial measures to assess success or failure. D. Prevention, appraisal and internal costs are not considered in the cost of products.
Give examples of the COPQ (internal and external failure costs) and the cost of quality assurance...
Give examples of the COPQ (internal and external failure costs) and the cost of quality assurance (prevention and appraisal) costs, using relevant industry example(s) to illustrate your point(s). Compare and contrast the supply chains for McDonald’s and for Toyota. Be detailed and specific.
Write a report on the feedback received from the review process?
Write a report on the feedback received from the review process?
Management at Work William is a manager at Macy’s. He recently received a special motivation report,...
Management at Work William is a manager at Macy’s. He recently received a special motivation report, but he isn’t sure how to use the information it contains. Can you help? Knowing that you are studying expectancy theory, William wants you to read the motivation report and help him write an e-mail that will motivate his employee Abigail. Review what motivates employees at Macy’s by reading the “Motivation Report.” Motivation Report In general, motivation at Macy’s is high. However, different employees...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $66,000        $99,000            Vendor certification 121,500        182,250        Appraisal costs:     Product acceptance $90,000        $135,000            Process acceptance 87,000        102,500        Internal failure costs:     Retesting $100,000        $94,000            Rework 200,000        170,000        External failure costs:     Recalls $145,000        $116,000            Warranty 315,000        318,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $60,000        $90,000            Vendor certification 127,500        191,250        Appraisal costs:     Product acceptance $84,000        $126,000            Process acceptance 93,000        115,000        Internal failure costs:     Retesting $98,000        $86,000            Rework 204,000        185,000        External failure costs:     Recalls $152,500        $122,000            Warranty 305,000        302,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December...
Interim Quality Performance Report Davis, Inc., had the following quality costs for the years ended December 31, 20x4 and 20x5: 20x4 20x5 Prevention costs:     Quality audits $65,000        $97,500            Vendor certification 123,500        185,250        Appraisal costs:     Product acceptance $91,000        $136,500            Process acceptance 99,000        110,000        Internal failure costs:     Retesting $92,000        $96,000            Rework 204,000        173,000        External failure costs:     Recalls $140,000        $112,000            Warranty 325,000        294,000        At the end of 20x4, management decided to increase its investment in control costs by 50 percent for each category’s...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT