In: Accounting
What is a job-order costing system? What do you know about Activity-Based-Costing (ABC) system? What are the differences between an ABC system and a traditional costing system? Use an example to show how we calculate and allocate overhead costs in an ABC system and a traditional system.
Job order costing system is a system of costing that is used to assign and accumulate costs od an individual unit of cost. This system s used in a case when items produced are sufficiently different from each other and everyone have a significant cost.The job cost record reports direct materials and direct labor and assigned amount of manufacturing overhead of each item that were used.
An activity based costing system is an method that is used to find the total cost of activities that is necessary for making a product. Under ABC costing each activity is assigned cost( that goes into production).It is generally used as a tool for understanding product cost and profit that is based on production.
Difference between an ABC system and a traditional costing system are:
ABC system | Traditional system |
It is a complex system | It is a simple system |
In this the cost id dependent upon the activities that is used by the cost objects | Under this cost object and used up resources are required for cost evaluation. |
This is more preferred than Traditional system | This is less preferred than ABC system. |
This uses multiple overhead pools | This uses a single overhead pool |
This system focus on activities. | This focus on structure. |
This is largely in use since 1981. | This is almost obsolete. |
For example:
A company makes 2 types of ball one with hollow center and one with solid center. The equipment used is same During the year company expects to make 1,000,000 hollow center ball and 2,000,000 solid center ball. The overhead cost allocated to the activity pool are as:
Materials purchased | $200,000 |
Set up of machines | 350,280 |
Packaging | 300,000 |
Testing | 270,000 |
Cleaning and maintenance | 288,540 |
Total overhead cost | $1,408,820 |
The cost driver estimated and cost calculated are:
Activity | cost driver | total expected unit | total cost | unit cost per cost driver |
purchasing of material | purchase order | 100 | $200,000 | $2,000 |
Set up of machines | set up | 252 | $350,280 | $1,390 |
packaging | containers filled | 2,500,000 | 300,000 | 0.12 |
testing | test | 3,000 | 270,000 | 90 |
cleaning and maintenance | of runs | 252 | 288,540 | 1,145 |
The activity by product is as follows:
Activity | Cost driver | unit cost (3) | Expected use hollow Centre (4) | expected use solid Centre (5) | ABC cost assigned Hollow Centre (6) | ABC cost assigned solid Centre (7) |
Purchasing purchase orders | $2,000 | 50 | 50 | $100,000 | $100,000 | |
set up | set ups | 1,390 | 126 | 126 | 175,140 | 175,140 |
Packaging | containers filled | 0.12 | 500,000 | 2,000,000 | 60,000 | 240,000 |
Testing | tests | 90 | 1,000 | 2,000 | 90,000 | 180,000 |
Cleaning and maintenance | runs | 1,145 | 84 | 168 | 96,180 | 192,360 |
Total | $521,320 | $887,500 |
Per unit overhead cost in ABC costing :
Hollow Centre ball = $521,320/1,000,000 = $0.521
Soft center ball = $887,500 / 2,000,000 = $0.444
Under traditional method based on direct labor . Estimated direct labor cost for the year = $1,512,000( hollow = $378,000 and soft = $1,134,000)
Per unit direct labor cost:
Hollow center = $378,000 / 1,000,000 = $0.38
Soft center = $1,134,000 / 2,000,000 = $0.57
Per unit cost of ball are :
Overhead per direct labor = $1,408,820 / $1,512,000 = $0.932
Allocation of overhead:
Hollow center = $0.932* $0.378 = $0.352 overhead per unit
Soft center = $0.932* $0.528 = $0.528 overhead per unit
Company overhead per unit :
ABC | Traditional | |
Hollow center | $0.52 | $0.35 |
Solid center | $0.44 | $0.53 |