Question

In: Finance

22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would...

22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would the company be indifferent between the two projects? Year /Cash Flow A /Cash Flow B 0 /-$10,000.00 /-$5,000.00 1/ $142,200.00/ $52,600.00 2/ $34,600.00/ $139,400.00 3/ $38,700.00/ $35,500.00 A) 22.41 percent B) 19.16 percent C) 29.11 percent D) -15.14 percent E) -19.49percent

Solutions

Expert Solution

after pressing the enter we get the below result

so the correct answer is option a 22.41%

please Like ? the answer, Please comment if any query…………………………………………………………………………………….

Related Solutions

Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 –$ 259,000 –$ 259,000 1 114,100 90,400 2 104,800 99,900 3 88,800 101,900 4 77,800 108,900 At what interest rate would the company be indifferent between the two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)    Interest rate             % Which project is better if the required return is above this interest...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 –$ 256,000 –$ 256,000 1 114,400 88,600 2 104,200 99,600 3 88,200 101,600 4 77,200 108,600 At what interest rate would the company be indifferent between the two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)    Interest rate             % Which project is better if the required return is above this interest...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0...
Hodgkiss Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 -269,000 -269,000 1 113,100 96,400 2 106,800 100,900 3 90,800 102,900 4 79,800 109,900 At what interest rate would the company be indifferent between the two projects? Which project is better if the required return is above this interest rate?
Two projects A and B with the following cash flows with a fix interest rate of...
Two projects A and B with the following cash flows with a fix interest rate of 12%. A. Use the present worth to select which project is better? Table 1 Project A 0 1 2 3 -9000 3000 3000 6000 Table 2 Project B 0 1 2 3 -12000 4000 3000 8000 B. Repeat the question in part A using AW analysis C. Repeat the question in part A using FW analysis
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows: Year Project A Project B Project C 0 ? $ 180,000 ? $ 330,000 ? $ 180,000 1 116,000 212,000 126,000 2 116,000 212,000 96,000 Suppose the relevant discount rate is 9 percent per year. a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 200,000 −$ 365,000 −$ 200,000 1 129,000 226,000 139,000 2 129,000 226,000 109,000    Suppose the relevant discount rate is 8 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows: Year Project A Project B Project C 0 − $ 215,000 − $ 380,000 − $ 215,000 1 138,000 232,000 152,000 2 138,000 232,000 118,000    Suppose the relevant discount rate is 9 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places,...
The treasurer of Amaro Canned Fruits, INC., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, INC., has projected the cash flows of projects A, B, and C as follows Year Project A Project B Project C 1 -100,000 -200,000 -150,000 2 60,000 130,000 110,000 3 60,000 130,000 110,000 Suppose the cost of capital is 10 percent and Amaro’s budget for these projects is $ 300,000. The projects are not divisible. Which project(s) should Amaro accept?
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 205,000 −$ 370,000 −$ 205,000 1 132,000 228,000 142,000 2 132,000 228,000 112,000    Suppose the relevant discount rate is 7 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
Harris Corporation is considering the following two mutually exclusive projects with their projected cash flows:                        &nb
Harris Corporation is considering the following two mutually exclusive projects with their projected cash flows:                                     Year                 Project A          Project B                                     0                    ($10,000)         ($10,000)                                     1                         4,500                      0                                     2                         4,500                      0                                        3                         4,500              15,000 If the required return on these projects is 10 percent, which would be chosen and why? Group of answer choices Project A because of higher IRR Project B because of higher NPV Project B because of higher IRR Project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT