In: Economics
Two projects A and B with the following cash flows with a fix interest rate of 12%.
A. Use the present worth to select which project is better?
Table 1 Project A
0 | 1 | 2 | 3 |
-9000 | 3000 | 3000 | 6000 |
Table 2 Project B
0 | 1 | 2 | 3 |
-12000 | 4000 | 3000 | 8000 |
B. Repeat the question in part A using AW analysis
C. Repeat the question in part A using FW analysis
Answer and explanation below
Explanation:
a) Present worth = P / (1 + r)t
Project A
Year 0 = -9,000 / (1 + 0.12)0
=9,000 / 1 = -9,000
Year 1 = 3,000 / 1.121 = 2,678.5714
Year 2 = 3,000 / 1.22 = 2,391.5816
Year 3 = 6000 / 1.123 = 4,270.681
NPV = -9,000 + 2,678.5714 + 2,391.5816 + 4,270.681
= 340.834
Project B
Year 0 = -12,000
Year 1 = 4,000 / 1.12 = 3,571.4285
Year 2 = 3000/ 1,122 = 2,391.5816
Year 3 = 8000/ 1.123 = 5,694. 2419
NPV = -12,000 + 3571.4285 + 2,391.5816 + 5,694.2419
= -342.748
Project A is better since it has a positive present worth.
b) Annual Worth
AW = Future worth * Rate of interest / [ (1 + Rate of interest)Time - 1
Project A = 232.268 x 0.12/ [( 1 + 0.12)3 - 1]
= 232.268 x 0.12/ 0.4049
= 232.268 x 0.29634
= $68.832
Project B = -233.573 x 0.29634
= -$69.217
Select project A because it has a positive annual worth
c) Future worth = Present worth * ( 1 - interest rate)time
Project A = 340.834 * ( 1-0.12)3
= 340.834 x 0.681472
= $232.268
Project B = 342.748 x 0.681472
= -233.573
Project A is better because it has a positive future worth.