In: Finance
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows:
Year | Project A | Project B | Project C | ||||||
0 | − | $ | 200,000 | − | $ | 365,000 | − | $ | 200,000 |
1 | 129,000 | 226,000 | 139,000 | ||||||
2 | 129,000 | 226,000 | 109,000 | ||||||
Suppose the relevant discount rate is 8 percent per year.
a. Compute the profitability index for each of the
three projects. (Do not round intermediate calculations.
Round your answers to 2 decimal places, e.g., 32.16.)
Profitability index | |
Project A | |
Project B | |
Project C | |
b. Compute the NPV for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)
NPV | ||
Project A | $ | |
Project B | $ | |
Project C | $ | |
c. Suppose these three projects are
independent. Which project(s) should Amaro accept based on the
profitability index rule?
Project A | |
Project B | |
Project C | |
Project A, Project B, Project C | |
Project A, Project B | |
Project A, Project C | |
Project B, Project C |
d. Suppose these three projects are mutually
exclusive. Which project(s) should Amaro accept based on the
profitability index rule?
Project B | |
Project A | |
Project C | |
Project A, Project B | |
Project A, Project B, Project C | |
Project A, Project C | |
Project B, Project C |
e. Suppose Amaro’s budget for these projects is
$565,000. The projects are not divisible. Which project(s) should
Amaro accept?
Project A | |
Project B | |
Project C | |
Project A, Project B, Project C | |
Project B, Project C | |
Project B, Project A | |
Project A, Project C |
a. Profitability index is computed by using the below formula:
= Present value of future cash flows / Initial investment
PI of project A
= ( $ 129,000 / 1.081 + $ 129,000 / 1.082 ) / $ 200,000
= 1.15 Approximately
PI of project B
= ( $ 226,000 / 1.081 + $ 226,000 / 1.082 ) / $ 365,000
= 1.10 Approximately
PI of project C
= ( $ 139,000 / 1.081 + $ 109,000 / 1.082 ) / $ 200,000
= 1.11 Approximately
b. The NPV of the projects is computed as shown below:
NPV of project A is shown below:
= - $ 200,000 + $ 129,000 / 1.081 + $ 129,000 / 1.082
= $ 30,041.15 Approximately
NPV of project B is shown below:
= - $ 365,000 + $ 226,000 / 1.081 + $ 226,000 / 1.082
= $ 38,017.83 Approximately
NPV of project C is shown below:
= - $ 200,000 + $ 139,000 / 1.081 + $ 109,000 / 1.082
= $ 22,153.64 Approximately
c. Since all of the projects PI is greater than 1, hence all the project shall be accepted. So the correct answer is option of Project A, Project B, Project C.
d. Since the PI of project A is the highest among all the three projects, hence project A shall be accepted. So the correct answer is option of Project A.
e. Project A and B shall be executed if the budget is $ 565,000, since they will result in the highest NPV of
= $ 30,041.15 + $ 38,017.83
= $ 68,058.98
So the correct answer is option of Project B, Project A.
Feel free to ask in case of any query relating to this question