Question

In: Finance

The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B,...

The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows:

Year Project A Project B Project C
0 $ 200,000 $ 365,000 $ 200,000
1 129,000 226,000 139,000
2 129,000 226,000 109,000

  

Suppose the relevant discount rate is 8 percent per year.
  
a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)

  

Profitability index
Project A
Project B
Project C

  

b. Compute the NPV for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)

  

NPV
Project A $
Project B $
Project C $

  

c. Suppose these three projects are independent. Which project(s) should Amaro accept based on the profitability index rule?
  

Project A
Project B
Project C
Project A, Project B, Project C
Project A, Project B
Project A, Project C
Project B, Project C


  
d. Suppose these three projects are mutually exclusive. Which project(s) should Amaro accept based on the profitability index rule?
  

Project B
Project A
Project C
Project A, Project B
Project A, Project B, Project C
Project A, Project C
Project B, Project C


  
e. Suppose Amaro’s budget for these projects is $565,000. The projects are not divisible. Which project(s) should Amaro accept?
  

Project A
Project B
Project C
Project A, Project B, Project C
Project B, Project C
Project B, Project A
Project A, Project C

Solutions

Expert Solution

a. Profitability index is computed by using the below formula:

= Present value of future cash flows / Initial investment

PI of project A

= ( $ 129,000 / 1.081 + $ 129,000 / 1.082 ) / $ 200,000

= 1.15 Approximately

PI of project B

= ( $ 226,000 / 1.081 + $ 226,000 / 1.082 ) / $ 365,000

= 1.10 Approximately  

PI of project C

= ( $ 139,000 / 1.081 + $ 109,000 / 1.082 ) / $ 200,000

= 1.11 Approximately  

b. The NPV of the projects is computed as shown below:

NPV of project A is shown below:

= - $ 200,000 + $ 129,000 / 1.081 + $ 129,000 / 1.082

= $ 30,041.15 Approximately

NPV of project B is shown below:

= - $ 365,000 + $ 226,000 / 1.081 + $ 226,000 / 1.082

= $ 38,017.83 Approximately

NPV of project C is shown below:

= - $ 200,000 + $ 139,000 / 1.081 + $ 109,000 / 1.082

= $ 22,153.64 Approximately

c. Since all of the projects PI is greater than 1, hence all the project shall be accepted. So the correct answer is option of Project A, Project B, Project C.

d. Since the PI of project A is the highest among all the three projects, hence project A shall be accepted. So the correct answer is option of Project A.

e. Project A and B shall be executed if the budget is $ 565,000, since they will result in the highest NPV of

= $ 30,041.15  + $ 38,017.83

= $ 68,058.98

So the correct answer is option of Project B, Project A.

Feel free to ask in case of any query relating to this question


Related Solutions

The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows: Year Project A Project B Project C 0 ? $ 180,000 ? $ 330,000 ? $ 180,000 1 116,000 212,000 126,000 2 116,000 212,000 96,000 Suppose the relevant discount rate is 9 percent per year. a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 200,000 −$ 365,000 −$ 200,000 1 129,000 226,000 139,000 2 129,000 226,000 109,000    Suppose the relevant discount rate is 8 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of projects A, B, and C as follows: Year Project A Project B Project C 0 − $ 215,000 − $ 380,000 − $ 215,000 1 138,000 232,000 152,000 2 138,000 232,000 118,000    Suppose the relevant discount rate is 9 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places,...
The treasurer of Amaro Canned Fruits, INC., has projected the cash flows of projects A, B,...
The treasurer of Amaro Canned Fruits, INC., has projected the cash flows of projects A, B, and C as follows Year Project A Project B Project C 1 -100,000 -200,000 -150,000 2 60,000 130,000 110,000 3 60,000 130,000 110,000 Suppose the cost of capital is 10 percent and Amaro’s budget for these projects is $ 300,000. The projects are not divisible. Which project(s) should Amaro accept?
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 205,000 −$ 370,000 −$ 205,000 1 132,000 228,000 142,000 2 132,000 228,000 112,000    Suppose the relevant discount rate is 7 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 190,000 −$ 355,000 −$ 190,000 1 123,000 222,000 133,000 2 123,000 222,000 103,000    Suppose the relevant discount rate is 9 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B,...
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows:    Year Project A Project B Project C 0 −$ 155,000 −$ 305,000 −$ 155,000 1 111,000 202,000 121,000 2 111,000 202,000 91,000    Suppose the relevant discount rate is 9 percent per year.    a. Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.)...
Interstate Appliance Inc. is considering the following two mutually exclusive projects. Projected cash flows for these...
Interstate Appliance Inc. is considering the following two mutually exclusive projects. Projected cash flows for these ventures are as follows: Plan A IO CF1 CF2 CF3 CF4 CF5 3,600,000 0 0 0 0 7,000,000 Plan B IO CF1 CF2 CF3 CF4 CF5 3,500,000 1,000,000 0 2,000,000 2,000,000 1,000,000 If Interstate Appliance has a 12% cost of capital, what decision should be made regarding the projects above? a. Accept plan A. b. Accept plan B. c. Reject both plans A and...
University Hospital has four capital projects under consideration with the following investments and projected cash flows....
University Hospital has four capital projects under consideration with the following investments and projected cash flows. What is their optimal capital budget allocation if their corporate cost of capital is 12%? Year 0 1 2 3 4 5 Project A        (600,000)                                 50,000                    90,000        150,000        200,000        250,000 B        (400,000)                                 80,000                  100,000        100,000        100,000        100,000 C        (700,000)                              100,000                  220,000        250,000        250,000        250,000 D       ...
22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would...
22) Textiles Unlimited has gathered projected cash flows for two projects. At what interest rate would the company be indifferent between the two projects? Year /Cash Flow A /Cash Flow B 0 /-$10,000.00 /-$5,000.00 1/ $142,200.00/ $52,600.00 2/ $34,600.00/ $139,400.00 3/ $38,700.00/ $35,500.00 A) 22.41 percent B) 19.16 percent C) 29.11 percent D) -15.14 percent E) -19.49percent
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT