Question

In: Accounting

Villegas Corporation has been using normal costing based on direct labor cost. In an attempt to...

Villegas Corporation has been using normal costing based on direct labor cost. In an attempt to better understand their costs, they conducted an activity study and identified the following overhead costs and drives for the coming year:

            Overhead Item         Cost Driver           Budgeted Cost            Budgeted Activity Level
            Machine Setup           Number of Setups      $ 20,000                        200
            Inspection              Number of Inspections   $ 130,000                      6,500
            Material Handling     Number of Material Moves $ 80,000                       8,000
            Engineering                     Engineering Hours      $ 50,000                       1,000
            Total                                                                    $ 280,000

The following information was collected on three jobs taht were completed during the year:
                                               Job 101                 Job 102                 Job 103
Direct Materials                    $ 5,000    $ 12,000 $ 8,000
Direct Labor                         $ 2,000                  $ 2,000                    $ 4,000
Units Completed                    100                         50                            200
Number of Setups                    1                           2                               4
Number of Inspections           20                         10                             30
Number of Material Moves     30                         10                             50
Engineering Hours                  10                         50                             10

Budgeted direct labor cost was $100,000 and budgeted direct material cost was $300,000

1) Using normal costing, the cost of Job 103 would be...

2) Using activity based costing, the cost of Job 103 would be...

3) Frank Aquilino, president of Villegas Corporation is concerned that his current system may not have been given them useful cost information and has head that Job 103 was miscosted. He asks "what the heck is going on here?"
With respoect to Job 103, was the job overcosted or undercosted under their current normal costing procedure?
Frank also needs an explanation as to why this is occuring. Specificially, for Job 103, WHY was this inaccurately costed? Explain to Frank what is going on that is causing this?

Show all work.

Solutions

Expert Solution

1) . Cost of job 103 using normal costing method is as follows :-

Particulars amount
Direct material 8000
Direct labour 4000
Overhead cost (2.80x4000) [wn i] 11200
Total cost 23200

Working note :-

i . Overhead is to be absorbed in the basis of labour cost. Thus, overhead rate per dollar of direct labour cost = 280000/100000= 2.80 per dollar of labour cost.

2) . Cost of job 103 using activity based costing will be as follows :-

Particulars amount
Direct material 8000
Direct labour 4000
Overheads :
Set up cost (100 [WN ii] ) x4 400
Inspection cost (20 [wn ii] x30) 600
Material handling cost (10 [wn ii] x50) 500
Engineering cost (50 [wn ii ] x10) 500
Total cost 14000

ii Calculation of cost per unit of cost driver

Overhead item cost driver budgeted cost Budgeted activity level cost per unit of driver
Machine setup no of setup 20000 200 100
Inspection no of inspection 130000 6500 20
Material handling no of material movement 80000 8000 10
Engineering cost engineering hours 50000 1000 50

3) . As per the ongoing method of charging overhead cost in relation to direct labour cost, cost of job 3 is coming out to be $23200 whereas as per activity based costing total cost of job 3 is coming out to be $14000. Therefore , clearly we can see that cost of job 3 calculated based on ongoing system is overcosted compared to the activity based costing

Now coming to the reason why this is happening, it is because in the ongoing system we are charging all the overhead cost on the basis of a single blanket rate based on direct labour cost irrespective of efforts involved in each overhead cost item we are only considering extent of labour cost involved in the present case total budgeted labour cost is $100000, and labour cost on job 3 is $4000, which is 4% of total labour cost thus 4% of total overhead cost will be charged on job 3 as per Current method. But overhead consider of different heads of exp all requiring different level of efforts . For instance total no. Of setups are 200, whereas no of setup on job 3 is only 4 i.e. 2% of total therefore 2% of overhead concerning setup cost will only attributable to job 3, total inspection is 6500, whereas inspection involved in job 3 is 30 only i.e. only 0?4% of total inspections this only 0.4% of total inspection is attributable to job 3. Material movements is 8000, and that for job 3 is 50 which is 0.625% of total and engineering hours are 1000 and those for job 3 is only 10 thus only 1% of total.

We can see above that proprtion of efforts in job 3 is quite low, whereas it's proportion of total labour cost was more that's why more cost get charged on job 3 as per ongoing method which was wrong.

So, it would be better to apply activity costing method considering the whole discussion .


Related Solutions

a large hotel​ chain, has been using​ activity-based costing to determine the cost of a​ night's...
a large hotel​ chain, has been using​ activity-based costing to determine the cost of a​ night's stay at their hotels. One of the​ activities, "Inspection," occurs after a customer has checked out of a hotel room. Fitzgerald inspects every 10th room and has been using​ "number of rooms​ inspected" as the cost driver for inspection costs. A significant component of inspection costs is the cost of the supplies used in each inspection. Dawn McAdams​, the chief​ inspector, is wondering whether...
Wuhan Company’s costing system has two direct-cost categories: Direct Materials and Direct Labor. Management evaluates the...
Wuhan Company’s costing system has two direct-cost categories: Direct Materials and Direct Labor. Management evaluates the Direct Materials Department by keeping purchases separate from production for variance analysis purposes. Manufacturing overhead (both variable and fixed) is allocated on the basis of Direct Labor-hours. Budget (standard) amounts for the current period are as follows: Budget (Standard) Amount / Input Direct Materials 2 lbs. at $7.50 per lb. Direct Labor 1.30 hrs. at $25 per hr. Variable Mfg. Overhead $ 105,300 Fixed...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor....
The Brown Manufacturing​ Company's costing system has two​ direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead​ (both variable and​ fixed) is allocated to products on the basis of standard direct manufacturing labor hours​ (DLH). At the beginning of 2014 Brown adopted the following standards for its manufacturing​ costs:  Direct materials 3 lbs. at $4 per lb. $12.00 Direct manufacturing labor 4 hrs. at $20 per hr. 80.00 Manufacturing overhead: Variable $6 per DLH 24.00 Fixed $7 per DLH...
The manufacturing overhead budget at Franklyn Corporation is based on budgeted direct labor-hours. The direct labor...
The manufacturing overhead budget at Franklyn Corporation is based on budgeted direct labor-hours. The direct labor budget indicates that 2,600 direct labor-hours will be required in January. The variable overhead rate is $7 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $43,100 per month, which includes depreciation of $3,660. All other fixed manufacturing overhead costs represent current cash flows. The January cash disbursements for manufacturing overhead on the manufacturing overhead budget should be: Multiple Choice $61,300 $18,200 $57,640...
Tiger Corporation uses a standard cost system and applies overhead based on direct labor hours. If...
Tiger Corporation uses a standard cost system and applies overhead based on direct labor hours. If the actual quantity of direct labor hours exceeds the standard hours allowed: an favorable variable overhead rate variance will exist an unfavorable variable overhead efficiency variance will exist a favorable variable overhead efficiency variance will exist a favorable labor rate variance will exist
Hakara Company has been using direct labor costs as the basis for assigning overhead to its...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its many products. Under this allocation system product A has been assigned overhead of $24.08 per unit while product B has been assigned $11.37 per unit. Management feels that an ABC system will provide a more accurate allocation of the overhead costs and has collected the following cost pool and cost driver information:   Cost Pools Activity Costs Cost Driver Driver Consumption   Machine setup $ 396,000...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its many products. Under this allocation system product A has been assigned overhead of $31.58 per unit while product B has been assigned $8.69 per unit. Management feels that an ABC system will provide a more accurate allocation of the overhead costs and has collected the following cost pool and cost driver information:   Cost Pools Activity Costs Cost Driver Driver Consumption   Machine setup $ 198,000...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its many products. Under this allocation system product A has been assigned overhead of $24.82 per unit while product B has been assigned $13.58 per unit. Management feels that an ABC system will provide a more accurate allocation of the overhead costs and has collected the following cost pool and cost driver information: Cost Pools Activity Costs Cost Driver Driver Consumption Machine setup 158,000 Setup...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its...
Hakara Company has been using direct labor costs as the basis for assigning overhead to its many products. Under this allocation system, product A has been assigned overhead of $26.98 per unit, while product B has been assigned $15.22 per unit. Management feels that an ABC system will provide a more accurate allocation of the overhead costs and has collected the following cost pool and cost driver information: Cost Pools Activity Costs Cost Drivers Activity Driver Consumption Machine setup $...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT