Question

In: Economics

Economic Evaluation problem: The following information has been gathered on the costs and effectiveness of the...

Economic Evaluation problem:

  1. The following information has been gathered on the costs and effectiveness of the two treatments, A and B. In this problem, costs and consequences are not discounted.

Treatment A

Treatment B

Mortality rate

2%

5%

Life expectancy for survivors

20 years

10 years

Initial treatment cost

$10,000

$3,000

Follow up costs, year 1

$5,000

$1,000

Annual follow up costs, all subsequent years

$1,000

$500

  1. What is the total cost for the survivors receiving treatment A?
  2. What is the total cost for survivors receiving treatment B?
  3. What is the expected cost for those patients receiving treatment A?
  4. The expected cost of Treatment B?
  5. Calculate the incremental cost and incremental benefit of the treatment alternatives.
  6. What is the ICER?
  7. How does cost-benefit analysis differ from cost-effectiveness analysis?

Solutions

Expert Solution

Answer

a) The total cost for a survivor taking treatment A is computed as the sum of the following:-

(1) Initial treatment costs in Year 0;

(2) Follow-up costs in Year 1; and

(3) Total costs of follow up from Year 2 till Year 20

Now, basis the information provided in the Table given in the question, it follows that (1) Initial treatment cost in Year 0 = $10,000; (2) Follow-up costs in Year 1 = $ 5,000 and (3) Total follow-up costs from Year 2 till Year 20 = $ 19,000 which is computed by multiplying the Annual follow up cost of $1,000 incurred each year by 19 which is the number of years from Year 2 till Year 20

Thus, the total cost for a survivor taking treatment A = $10,000 + $ 5,000 + $ 19,000 =$34,000

Hence, the answer to Question 1. i.e. the total cost for survivors receiving treatment A is $34,000.

However, for those patients who cannot survive i.e. those 2% of the patients who die early, the total cost is equivalent to the initial treatment cost of treatment A which is $10,000.

b)Answer

The total cost for a survivor taking treatment B is computed as the sum of the following:-

(1) Initial treatment costs in Year 0;

(2) Follow-up costs in Year 1; and  

(3) Total costs of follow up from Year 2 till Year 10

Now, basis the information provided in the Table given in the question, it follows that (1) Initial treatment cost in Year 0 = $3,000; (2) Follow-up costs in Year 1 = $ 1,000 and (3) Total follow-up costs from Year 2 till Year 20 = $ 4,500 which is computed by multiplying the Annual follow up cost of $500 incurred each year by 9 which is the number of years from Year 2 till Year 10

Thus, the total cost for a survivor taking treatment B = $3,000 + $ 1,000 + $ 4,500 =$8,500

Hence, the answer to Question 2. i.e. the total cost for survivors receiving treatment B is $8,500.

However, for those patients receiving treatment B who cannot survive i.e. those 5% of the patients who die early, the total cost is equivalent to the initial treatment cost of Treament B which is $3,000.

c)Answer

The mortality rate of the patients receiving treatment A is 2% whereas the mortality rate of the patients receiving treatment B is 5%.

This implies that the 98% of the patients receiving treatment A survive. Similarly, 95% of the patients receiving treatment B survive,

The expected cost for those patients receiving treatment A = (Mortality rate)* (Total Cost of treatment A for patients who don't survive i.e. who die early) + (% of survivors receiving treatment A) *(Total Cost of treatment A for survivors receiving treatment A).

Now, basis the information provided in the Table given in the question, it follows that Mortality rate for patient receiving Treatment A is 2%. The total cost of treatment A for patients who don't survive i.e. who die early as computed in Answer to Question 1 above is $10,000. Furthermore, the total cost for the survivors receiving treatment A as computed in Answer to Question No.1 above is $ 34,000.

Thus, the expected cost for the patients receiving treatment A = (2%* $10,000) + (98%*$34,000) = $33,520

Similarly, the expected cost for those patients receiving treatment B= (Mortality rate)* (Total cost of treatment B for patients who don't survive i.e. who die early) + (% of survivors receiving treatment B) *(Total cost of treatment B for survivors receiving treatment B).

Now, basis the information provided in the Table given in the question, it follows that Mortality rate for patient receiving Treatment B is 5%. The total cost of treatment B for patients who don't survive i.e. who die early as computed in Answer to Question 2 above is $3,000. Furthermore, the total cost for the survivors receiving treatment B as computed in Answer to Question No.2 above is $ 8,500.

Thus, the expected cost for the patients receiving treatment B = (5%* $3,000) + (95%*$8,500) = $8,225

Hence, the answer to this Question 3 i.e. the expected cost for those patients receiving treatment A is $33,520 and the expected cost for those patients receiving treatment B is $8,225.

e)Answer

The incremental cost of the treatment alternatives is computed as difference between the expected cost for those patients receiving treatment A and the expected cost for those patients receiving treatment B i.e. $33,520 - $8,225 = $25,295

The benefit of treatment A is computed by multiplying the life expectancy of the survivors receiving treatment A and % of survivors receiving treatment A . Similarly, the benefit of treatment B is computed by multiplying the life expectancy of the survivors receiving treatment B and % of survivors receiving treatment B.

Basis the information provided in the table given in the Question, the Life expectancy of the survivors receiving treatment A is 20 years. The % of survivors receiving treatment A is 98%. Thus, the benefit of treatment A = 20* 0.98 which comes out to 19.6

SImilarly, basis the information provided in the table given in the Question, the Life expectancy of the survivors receiving treatment B is 10 years. The % of survivors receiving treatment A is 95%. Thus, the benefit of treatment A = 10* 0.95 which comes out to 9.5.

The incremental benefit of the treatment alternatives is computed as difference between the benefit of receiving treatment A and the benefit of receiving treatment B i.e. 19.6- 9.5 which comes out to be 10.1.

Hence, the answer to this Question 4 i.e. the incremental cost and incremental benefit of the treatment alternatives are $25,295 and 10.1.

f)Answer

The ICER is computed as the ratio of incremental costs and incremental benefits of the treatment alternatives i,e, ICER is computed by the dividing the incremental costs and incremental benefits of the treatment alternatives as computed above i.e. ICER = 25295/10.1 which comes out to be 2,504 (rounded figure).

Hence, the answer to this Question 5 i.e. the ICER is 2,504.

g)Answer

In the cost-benefit analysis, the value of the benefits are expressed in monetary terms i.e. there is a quantification of the benefits and costs in monetary terms. In the Cost effectiveness analysis, the benefits are not measured in monetary terms but they are measured in terms of the effectiveness of the outcomes.


Related Solutions

For Questions 14-19 The following information has been gathered on the costs and effectiveness of the...
For Questions 14-19 The following information has been gathered on the costs and effectiveness of the two treatments, A and B. Treatment A Treatment B Mortality rate 2% 5% Life expectancy for survivors 10 years 6 years Initial treatment cost $8,000 $4,000 Annual follow up costs $1,000 $800 14. What is the total cost for the survivors receiving treatment A? A. $8,000 B. $10,000 C. $18,000 D. $20,000 1 points    QUESTION 15 What is the total cost for decedents...
The following information has been gathered for a project to install a new machine lathe at...
The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc. Activity Activity Time (wks) Immediate Predecessor(s) A 4 — B 7 A C 9 B D 3 B E 14 D F 10 C, D G 11 F, E Draw the network diagram. Calculate the slack for each activity and determine the critical path. How long will the project take?
Overton Company has gathered the following information.
Overton Company has gathered the following information.Units in beginning work in process21,100Units started into production184,900Units in ending work in process24,700Percent complete in ending work in process:    Conversion costs60%    Materials100%Costs incurred:    Direct materials$103,000    Direct labor$263,576    Overhead$187,500Compute equivalent units of production for materials and for conversion costs.MaterialsConversion CostsThe equivalent units of production  Determine the unit costs of production. (Round unit costs to 2 decimal places, e.g. 2.25.)MaterialsConversion CostsUnit costs$$  Show the assignment of costs to units transferred out and in process.Transferred out$Ending work in process$
Gulf Company has gathered the following information on quality costs for the year 2017: Quality engineering...
Gulf Company has gathered the following information on quality costs for the year 2017: Quality engineering of products $20,000 Quality training of employees $2,000 Net cost of scrap $30,000 Rework labor $4,500 Warranty repairs $100,000 Product recalls $200,000 Liability arising from defective products $1,000,000 Maintenance of test equipment $44,000 Quality improvement projects $55,000 Setups for testing $3,000 Supplies used in testing $5,500 Downtime caused by defects $70,000 Disposal of defective products $80,000 Assume that year sales totaled $5,000,000 Required: a....
The following information has been gathered for Highgate Security for the month ended September 30, 2021:...
The following information has been gathered for Highgate Security for the month ended September 30, 2021: 1) The bank statement indicates a balance of $6,417. 2) The general ledger cash account indicates a balance of $5,422 on September 30, 2021. 3) There was an EFT deposit of $1,700 on the bank statement for the monthly rent from a tenant. 4) The bookkeeper had erroneously recorded a $100 cheque as $1,000. The cheque was to settle the account payable of Janex...
Marigold Corp. has gathered the following information concerning one model of shoe: Variable manufacturing costs $36000...
Marigold Corp. has gathered the following information concerning one model of shoe: Variable manufacturing costs $36000 Variable selling and administrative costs $10000 Fixed manufacturing costs $160000 Fixed selling and administrative costs $120000 Investment $1700000 ROI 30% Planned production and sales 4000 pairs What is the target selling price per pair of shoes? $177 $209 $139 $198
Moresan Co. gathered the following information on power costs and factory machine usage for the last...
Moresan Co. gathered the following information on power costs and factory machine usage for the last six months: Month Power Cost Factory Machine Hours January $24,400 13,900 February 30,400 17,600 March 29,000 16,800 April 22,340 13,200 May 19,900 11,600 June 16,900 8,600 Using the high-low method of analyzing costs, answer the following questions. What is the estimated variable portion of power costs per factory machine hour? (Round answer to 2 decimal places, e.g. 15.25.) Variable power costs $ per factory...
Fernicus Company gathered the following information on power costs and factory machine usage for the last...
Fernicus Company gathered the following information on power costs and factory machine usage for the last five months. Month Power Cost Factory Machine Hours January P48,000 19,000 February 35,000 15,500 March 50,000 18,500 April 41,000 17,000 May 40,000 15,000 Instructions: Use the high-low method of analyzing costs to answer the following questions. 1. How much is the estimated variable portion of power costs per factory machine hour? 2. How much is the estimated fixed power cost each month? 3. If...
(Ignore income taxes in this problem.) Overland Corporation has gathered the following data on a proposed...
(Ignore income taxes in this problem.) Overland Corporation has gathered the following data on a proposed investment project: Click here to view Exhibit 8B-1 and Exhibit 8B-2 to determine the appropriate discount factor(s) using tables. Investment required in equipment $ 410,000 Annual cash inflows $ 60,000 Salvage value of equipment $ 0 Life of the investment 16 years Discount rate 9 % The company uses straight-line depreciation on all equipment. Assume cash flows occur uniformly throughout a year except for...
(Ignore income taxes in this problem.) Overland Corporation has gathered the following data on a proposed...
(Ignore income taxes in this problem.) Overland Corporation has gathered the following data on a proposed investment project: Click here to view Exhibit 8B-1 and Exhibit 8B-2 to determine the appropriate discount factor(s) using tables. Investment required in equipment $ 560,000 Annual cash inflows $ 82,000 Salvage value of equipment $ 0 Life of the investment 16 years Discount rate 9 % The company uses straight-line depreciation on all equipment. Assume cash flows occur uniformly throughout a year except for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT