Question

In: Accounting

Cary Construction Inc. is preparing to bid on a job building a new dorm fo the...

Cary Construction Inc. is preparing to bid on a job building a new dorm fo the local college. Cary expects that the job will require $850,000 of direct materials, $500,000 of direct labor, and $425,000 of overhead costs. Administrative and other expenses for the job are expected to be $2,000. On average last year, Cary Construction earned about $250,000 profit on a job this size and would like to increase the profit by 5 percent on new contracts. Cary normally applies a markup on a cost of goods sold to arrive at an initial bid price and then adjusts. the price if necessary in order to meet competitors' prices. The college already has one bid from a national construction company to do the job for $2,000,000.

a.) calculate the markup percentage on the new job.

b.) what is Cary Construction's initial bid?

c.) In light of the competitor's price of $2,000,000, what would you recommend as a bid price for Cary Construction?

Solutions

Expert Solution

Answer:-

Cary Construction Inc. Bid Value
Particulars Amount
Direct Material $850,000
Add: Direct Labour $500,000
Add: Overhead $425,000
Prime Cost $1,775,000
Add: Administrative & other Expenses $2,000
Total Cost $1,777,000
Add: Profit ($250,000+5%) $262,500
Total Bid Value $2,039,500

a). Markup Percentage on the new Job

Markup = (Profit/Total Cost)*100

Markup = ($262,500/$1,777,000)*100

Markup = 14.77% (approx)

b). Carry Construction's Initial Bid value is $2,039,500 as stated above.

c) As compare to competitor's price of $2,000,000, Carry Construction's Bid value (i.e. $2,039,500) is higher. Therefore Carry Construction's have to reduce it's profit atleast by $39,500 to match the competitor's bid price.

In that case Markup (%) would be 12.55% which is as follows:-

Markup = (Profit/Total Cost)*100

Markup = ($223,000/$1,777,000)*100

Markup = 12.55% (approx)


Related Solutions

A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from other contractors can be described by the following probability distributions: Contractor A: Uniform probability distribution between $500,000 and $1,000,000. Contractor B: Normal probability distribution with a mean bid of $700,000 and a standard deviation of $100,000. a. If Johnson Company submits a bid of $750,000, what is the probability Butler will...
Service Provider will fund an investment in a new dorm building in the amount of Ten...
Service Provider will fund an investment in a new dorm building in the amount of Ten Million Dollars ($10,000,000). The investment will be amortized over a period of fifteen (15) years from the date of disbursement calculated at a rate equal to a straight-line basis. If the agreement is terminated prior to the full amortization of the investment, then the client is liable for and promises to pay Service Provider within thirty (30) days of the termination notice date the...
Thompson’s proposal for a building construction contract was for $125,500. After finding that his bid was...
Thompson’s proposal for a building construction contract was for $125,500. After finding that his bid was low, he checked his estimates and found that an item of $25,000 had been incorrectly recorded as $2,500 in making the summary of costs. Can he remove his bid? Is the contract likely to be valid? Why or why not? Explain your answer. To receive full credit, you should use the legal terms discussed in class.
You are trying to decide whether to bid on a construction contract for a new bridge...
You are trying to decide whether to bid on a construction contract for a new bridge in South Carolina. You think that it will take 36 months to build and that construction costs will be $2 million per month. You expect tolls to be $10 million per year once the bridge opens, which will be offset by toll collection and maintenance costs of $2 million per year. Your (minimally acceptable rate of return) MARR is 15% per year. To bid...
You are the project manager responsible for a new building construction in northern Virginia. The building...
You are the project manager responsible for a new building construction in northern Virginia. The building is worth $500,000 and will have five bedrooms, a kitchen, landscaping, and a two-car garage to be completed in two years. This was agreed upon in a firm fixed contract. During the execution (construction) of the building, you realize that the cost of materials have gone up by 10%, and your schedule is behind by 90 days due to delays from county inspections and...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Construction of a new building began on April 1 and was completed on October 29. Construction...
Construction of a new building began on April 1 and was completed on October 29. Construction expenditures were as follows: May 1 $3,300,000 July 30 2,200,000 September 1 1,740,000 October 1 2,640,000 MMI borrowed $5,000,000 at 6% on April 1 to help finance construction. This loan, plus interest, will be paid in 2022. The company also had a $6,650,000, 8% long-term note payable outstanding throughout 2021. Weighted Average Accumulated Expenditures were: [Round expenditure to nearest dollar] Date Expenditure Months financed...
Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an...
Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office bu... Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office building for Fred. In preparation of his bid, Bill asked Sam, a tile manufacturer in Setauket, New York, for a quote on tile to Bill's specifications. On October 27, 2006, Sam returned a statement on his letterhead with a quote of $8,000.00 which stated that the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT