Question

In: Operations Management

Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an...

Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office bu... Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office building for Fred. In preparation of his bid, Bill asked Sam, a tile manufacturer in Setauket, New York, for a quote on tile to Bill's specifications. On October 27, 2006, Sam returned a statement on his letterhead with a quote of $8,000.00 which stated that the quote was irrevocable. Although Bill did not tell Sam, Bill submitted a bid for the building on November 11, 2006, using Sam's quote as the basis for part of his bid. On January 8, 2007, after the price of tile had increased, Sam told Bill that he was revoking his offer. On January 9, 2007, Bill was awarded the contract to build the office building. Bill demanded that Sam deliver tile as per Sam's offer, but Sam refused. Bill thereupon purchased tile to his specifications from Ted, another tile manufacturer, for $9,000.00. Bill also needed doors for the office building. He contacted Steve, a door manufacturer in Syosset, New York, and placed an order for doors at a cost of $6,000.00, F.O.B. Syosset. Steve entered into a contract, which was reasonable, with a common carrier for the transportation of the doors from Syosset to Brentwood. While the doors were en route, the truck in which the doors were being transported was struck by lightning. The doors were completely destroyed. Bill refused Steve's demand for payment. Steve refused to supply Bill with replacement doors. Bill obtained replacement doors from Tom, another door manufacturer, for a cost of $7,000.00 which was then the current market value for doors meeting Bill's specifications. Bill and Susan, a window manufacturer in Stony Brook, New York, entered into a written contract whereby Susan agreed to provide windows to Bill's specifications no later than October 23, 2007, for a cost of $12,000.00. Susan's profit on the sale to Bill was $2,000.00. Susan has thousands of windows in stock, and can supply anyone with as many windows as he or she needs, at any time. On October 15, 2007, Susan delivered windows to Bill; however, the windows did not conform to Bill's specifications. Bill refused the windows and notified Susan in writing that day that he refused the windows. On October 16, 2007, Susan notified Bill that she would cure the non-conforming tender of goods. On October 18, 2007, Susan delivered new windows to Bill which conformed to Bill's specifications, but Bill had already purchased the windows he needed from Tina, another window supplier, for $11,500.00, on October 17, 2007, and Bill refused to accept Susan's second delivery of windows. Susan sold the windows to Frank, another buyer, for $12,000.00. Bill seeks damages from Sam, Steve and Susan. Steve and Susan seek damages from Bill.

Steve was discharged by impossibility when the doors were destroyed by lightning during transportation to Bill. True or False?

Bill is entitled to receive the full contract price of $6,000.00 from Steve. True or False?

Susan delivered defective windows to Bill on October 15, 2007. True or False ?

Susan is a lost volume seller since she had thousands of windows in stock and could supply anyone with as many windows as they need, at any time. True or False?

Susan is entitled to recover the full contract price of $12,000.00 from Bill. True or False?

Solutions

Expert Solution

Steve was discharged by impossibility when the doors were destroyed by lightning during transportation to Bill.

Answer:- False

Reason:- when the doors were destroyed by lightning during transportation to Bill, it can be replaced by the new door and thus the provision of discharged by impossibility will no be applicable.

Bill is entitled to receive the full contract price of $6,000.00 from Steve.

Answer:- False

Reason:- Bill can get the difference between the money paid for a new door and the contract price of the door with Steve

Susan delivered defective windows to Bill on October 15, 2007

Answer:- true

Reason:- The window delivered by Susan did not meet the specifications of Bill and thus it will be seen as a defective product

Susan is a lost volume seller since she had thousands of windows in stock and could supply anyone with as many windows as they need, at any time.

Answer:- True

Reason:- Susan will be a lost volume seller as Bill did not ask her to cancel the product or informed her that he is buying the product from somewhere else.

Susan is entitled to recover the full contract price of $12,000.00 from Bill.

Answer:- True

Reason:- In case of a lost volume seller, a seller can claim for the total amount which is sacrificed.


Related Solutions

Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an...
Question: Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office bu... Facts: Bill, a contractor in Brentwood, New York, prepared a bid for construction of an office building for Fred. In preparation of his bid, Bill asked Sam, a tile manufacturer in Setauket, New York, for a quote on tile to Bill's specifications. On October 27, 2006, Sam returned a statement on his letterhead with a quote of $8,000.00 which stated that the...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two...
Problem 12-18 (Algorithmic) A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $530,000 and $730,000 B Normal probability distribution with a mean bid of $630,000 and a standard deviation of $43,000 If required, round your answers to three...
package construction; public class Bid{ private String contractor; private float price; public Bid(String contractor, float price)...
package construction; public class Bid{ private String contractor; private float price; public Bid(String contractor, float price) { this.contractor = contractor; this.price = price; } public String getContractor() { return contractor; } public float getPrice() { return price; } } package construction; public class ContractorBids{ // assume proper variables and other methods are here public void winningBid(Bid[] bids, int numBids){ /**************************** * your code would go here * ****************************/ } } You are doing renovations on your building, and multiple contractors...
4. Express Warranties. FACTS: Ronald Anderson, Jr., a self?employed construction contractor, went to a Home Depot...
4. Express Warranties. FACTS: Ronald Anderson, Jr., a self?employed construction contractor, went to a Home Depot store to buy lumber for a construction project. It was raining, so Anderson bought a tarp to cover the bed of his pickup truck. To secure the tarp, Anderson bought a bag of cords made by Bungee International Manufacturing Corp. The printed material on the Bungee bag included the words “Made in the U.S.A.” and “Premium Quality.” To secure the tarp at the rear...
You are trying to decide whether to bid on a construction contract for a new bridge...
You are trying to decide whether to bid on a construction contract for a new bridge in South Carolina. You think that it will take 36 months to build and that construction costs will be $2 million per month. You expect tolls to be $10 million per year once the bridge opens, which will be offset by toll collection and maintenance costs of $2 million per year. Your (minimally acceptable rate of return) MARR is 15% per year. To bid...
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction...
On March 1, 2020, Reed hired a contractor to construct a new office building. The construction work commenced on April 1, 2020, and it is expected to continue through July 31, 2022, the estimated completion date. Reed made progress payments to the contractor in 2020 as follows: Date Amount April 1 $ 48,000 June 1 195,000 September 1 322,000 November 1 67,000 $632,000 As stated in A5 above, Reed took a 1-year, 9%, $225,000 construction loan to help fund the...
Cary Construction Inc. is preparing to bid on a job building a new dorm fo the...
Cary Construction Inc. is preparing to bid on a job building a new dorm fo the local college. Cary expects that the job will require $850,000 of direct materials, $500,000 of direct labor, and $425,000 of overhead costs. Administrative and other expenses for the job are expected to be $2,000. On average last year, Cary Construction earned about $250,000 profit on a job this size and would like to increase the profit by 5 percent on new contracts. Cary normally...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be...
Johnson Company is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from other contractors can be described by the following probability distributions: Contractor A: Uniform probability distribution between $500,000 and $1,000,000. Contractor B: Normal probability distribution with a mean bid of $700,000 and a standard deviation of $100,000. a. If Johnson Company submits a bid of $750,000, what is the probability Butler will...
Lobo, Inc., a construction contractor, has asked for your advice on the following: New City filed...
Lobo, Inc., a construction contractor, has asked for your advice on the following: New City filed suit against Lobo at the end of 2018 seeking $10 million in civil penalties and injunctive relief based upon violation of the New City construction code pertaining to green building standards.   New City alleged that Lobo had violated the code in various projects undertaken over the past two years. At the end of 2019, the parties had engaged in discovery and begun settlement negotiations....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT