Question

In: Accounting

On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...

On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $5,000 $7,000 $1,500 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March, and Job 2 is finished but not sold by the end of March. Job 1 Job 2 Job 3 Direct labor used $9,000 $4,000 $3,000 1. Determine the amounts of direct materials, direct labor, and factory overhead applied that would be reported on job cost sheets for each of the three jobs for March.

2. Determine the total dollar amount of Work in Process Inventory at the end of March.

     

3.

Determine the total dollar amount of Finished Goods Inventory at the end of March. Assume the company has no beginning Work in Process or Finished Goods inventories.

     

Solutions

Expert Solution

  • All working forms part of the answer
  • Working for total cost:

Job 1

Job 2

Job 3

Beginning WIP

$                        -  

$                         -  

$                       -  

Direct Material Added

$           5,000.00

$             7,000.00

$          1,500.00

Direct Labor

$           9,000.00

$             4,000.00

$          3,000.00

Applied manufacturing Overhead [40% of above direct labor cost]

$           3,600.00

$             1,600.00

$          1,200.00

Total Cost

$         17,600.00

$           12,600.00

$          5,700.00

Status

Work in Process

Finished Inventory not sold

Work in Process

  • Answers

---Answer ‘2’: Total Dollar amount of WIP Inventory at the end of March = Total cost of Job 1 and 3 = $ 17,600 + $ 5,700 = $ 23,300

---Answer ‘3’: Total Dollar amount of Finished Goods Inventory = Cost of Job 2 = $ 12,600


Related Solutions

Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the...
Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the adjusting entries at year-end was unable to complete the adjustments due to illness. You have been given the following unadjusted trial balance along with some additional information for the December 31, 2020, year-end. Account Unadjusted Balance Account Unadjusted Balance Accounts receivable $ 72,000 Land $ 122,000 Accum. deprec., building 117,000 Merchandise inventory 70,000 Accum. deprec., equipment 333,000 Mortgage payable 218,809 Advance sales 217,000 Sarah...
Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the...
Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the adjusting entries at year-end was unable to complete the adjustments due to illness. You have been given the following unadjusted trial balance along with some additional information for the December 31, 2017, year-end. Account Unadjusted Balance   Accounts receivable $ 82,600   Accum. deprec., building 134,000   Accum. deprec., equipment 350,000   Advance sales 234,000   Allowance for doubtful accounts 600   Building 451,000   Cash 88,900   Equipment 655,000   Estimated warranty...
Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the...
Golden Wedding Dress Company designs custom wedding dresses for brides to be. The person preparing the adjusting entries at year-end was unable to complete the adjustments due to illness. You have been given the following unadjusted trial balance along with some additional information for the December 31, 2017, year-end. Account Unadjusted Balance   Accounts receivable $ 82,600   Accum. deprec., building 134,000   Accum. deprec., equipment 350,000   Advance sales 234,000   Allowance for doubtful accounts 600   Building 451,000   Cash 88,900   Equipment 655,000   Estimated warranty...
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $5,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,000 $6,400 direct labor .................. 5,000 3,900 4,000 Madtack applies overhead to jobs at a rate of 80% of direct materials used. During March,...
Daniel J Company uses a job-order costing system and started the month of March with three...
Daniel J Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Daniel J applies overhead to jobs based on a percentage of direct materials used. During...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Propane Company uses a job-order costing system and started the month of March with three jobs...
Propane Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Propane applies overhead to jobs based on a percentage of direct materials used. During March, Propane...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT