In: Operations Management
1. All the below are outputs of plan procurement except
A. change requests, SOW, and source selection criteria.
B. a make-or-buy decision, a procurement management plan, and a contract.
C. procurement documents, SOW, and document updates.
D. source selection criteria, a procurement management plan, and a make-or-buy decision.
2.The selection of a proper seller is critical to the success of a project. All of the below would be considered good selection criteria for a buyer to use to select a seller, except
A. the proprietary rights of the buyer, life cycle cost of product, and warrantee offered by the seller.
B. the past work done by the seller, intellectual property rights, and references associated with a given seller.
C. the technical capability of the seller, understanding of work by the seller, and business type of the seller.
D. the managerial approach of the seller, capacity of the seller to do the work, and buyer’s ability to create a WBS.
1. C. procurement documents, SOW, and document updates.
Document updates are not output of plan procurement.
2. D. the managerial approach of the seller, capacity of the seller to do the work, and buyer’s ability to create a WBS.
buyer's ability to create a WBS is not a supplier selection criterion.