  1. Integrated Change Control includes all of the following tools and techniques except:

    A.

    Project management plan updates.

    B.

    Expert judgement.

    C.

    Meetings.

    D.

    A change control board to approve or reject changes.  

Solutions

Expert Solution

A- Project management plan updates.

In the above option project plan updates are output not the tools and techniques for Integrated Change Control. The other outputs are approved changes, change log etc.


Related Solutions

what are the tools in Plan Risk response inputs( Risk response tools & techniques )in project...
what are the tools in Plan Risk response inputs( Risk response tools & techniques )in project management that can be used to handle the risk involved in software development Systems on 500 medical records for an orthopedic health clinic?
Project Management for Engineers Course 1-All good project plans have a change control system as a...
Project Management for Engineers Course 1-All good project plans have a change control system as a component. Briefly explain the change control process. 2-What are the two primary purposes of control? 3-Why is control difficult? 4-What is earned value? 5-Define the terms monitoring and control. 6-What actions can you take to help avoid the common problems associated with meetings?
Describe various tools and techniques used in human resource management for a project. Use PMBOK as...
Describe various tools and techniques used in human resource management for a project. Use PMBOK as your main source of information List and describe some techniques for conflict management.
As a maintenance manager, your task is to apply project management tools and techniques towards planning...
As a maintenance manager, your task is to apply project management tools and techniques towards planning of your maintenance project. Think of your own project (for example, refurbishing of a boiler plant) and report on how you would go about planning such a project. Indicate all the equipment involved in your project, maintenance activities, allocation of human resources and all costs involved. Show the following in the process of planning your project: 1. Project definition 2. Work breakdown structure 3....
Discuss the tools and techniques best suited for resistance to change?
Discuss the tools and techniques best suited for resistance to change?
Cost of quality includes all of the following EXCEPT: Cost of the design and planning of...
Cost of quality includes all of the following EXCEPT: Cost of the design and planning of a quality control program. Cost of the direct appraisal and evaluation of quality in the plant and the field. Cost related to the failure of the product or service discovered by the performing organization while the item(s) is still within its control, or discovered by the customer Cost of operating computers required for the project.
9. The highest and best use of property includes all of the following EXCEPT:
Real Estate9. The highest and best use of property includes all of the following EXCEPT:(A) most productive use(B) economically viable.(C) possible within the physical limits of the property.(D) conformity to the surroundings.10. What is the amount of interest paid per year on a loan of $34,050 at an interest rate of 4.38%?(A) $1,491.39 (B) $1,284.33 (C) $1,309.21 (D) $1,118.4311) In order to complete the Due diligence for a rental property in NYC, you as the buyer may ask for the...
IT Project Management Tools Describe the tools and technology used to support IT project management. What...
IT Project Management Tools Describe the tools and technology used to support IT project management. What are the characteristics of future tools?
Are PERT and CPM both official tools of operations management? Also, each formalized project management plan...
Are PERT and CPM both official tools of operations management? Also, each formalized project management plan has a stakeholder management plan embedded in it. This is key (and confidential) as specifics to each person is needed in terms of engagement (how, when, frequency, etc.). Additionally, not all stakeholders are equal. Do operational plans require a stakeholder management plan as well?
comprehensively discuss the main financial management tools and techniques
comprehensively discuss the main financial management tools and techniques
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT