In: Accounting
solution:
Based on the decision variables defined in the question,
Total Cost = 37*FM + 10.5*SM + 5.5*TM + 50*FP + 14*SP + 6.5*TP
We have to minimize this cost
Subject to constraints
3.5*FM + 1.3*SM + 0.8*TM <= 350 hours * 60 minutes i.e. 21000..........Constraint for availability of minutes of Cutting time
2.2*FM + 1.7*SM + 0*TM <= 420 * 60 = 25,200 .....................................Constraint for availability of minutes of Milling time
3.1*FM + 2.6*SM + 1.7*TM <= 680*60 = 40,800.....................................Constraint for availability of minutes of Shaping time
Total Demand of final product = 4500 units
FM + FP >= 4500..........Constraint for demand of Frames
SM + SP >= 9000........Constraint for demand of Support (2 supports per 1 Liftmaster)
TM + TP >= 4500..........Constraint for demand of Strap
Hence, we get formulation as
Minimize Total Cost C = 37*FM + 10.5*SM + 5.5*TM + 50*FP + 14*SP + 6.5*TP
Subject to Constraints:
3.5*FM + 1.3*SM + 0.8*TM <= 21000
2.2*FM + 1.7*SM + 0*TM <= 25,200
3.1*FM + 2.6*SM + 1.7*TM <= 40,800
FM + FP >= 4500
SM + SP >= 9000
TM + TP >= 4500
FM, SM, TM, FP, SP, TP >=0
We solve in Excel using Excel solver as shown below:
The above solution in the form of formulas along with Excel Solver extract is shown below for better understanding and reference:
As seen from the above solution, we get
b) Total cost = $307615.38
c) Cutting = 21000
Milling = 16765.38
Shaping = 24450
d) For part d and e, we generate a sensitivity report as shown below:
As seen from the above sensitivity report,
The shadow price for Shaping Department (Cell B15 in Constraints table) is 0. Hence, any increase in the number of hours in the shaping department will lead to a 0 decrease in total cost. Further, there is a slack of 40800 - 24450 = 16,350. Hence, Frandec should be willing to pay $0 because there is slack of 16,350 hours.
e) As seen from the above sensitivity report,
The Reduced cost for Frames to be purchased (Cell B5 in Variables table) is 3.58. In order to make the optimal solution such that Frames are purchased, the price of frames should be reduced by at least $3.58 i.e. 50 - 3.58 = $46.42. Since the supplier is supplier at $45 which is less than minimum reduced price, Frandec can improve by pursuing this opportunity. Hence, the reduced cost of 3.577 indicates the solution can be improved.
******
Please up vote....Its very usefull for us .....Thank you .....So
Much......If any qurries comment below....I will resolve
ASAP....Until u got.....