In: Accounting
Question 2: Toyota Motors has the following monthly
data regarding its engine
production:
● Materials purchased and used, 3,300 pounds
● Direct-labor costs incurred, 5,500 hours, $42,350
● Variable-overhead costs incurred, $4,620
● Finished units produced, 1,000
● Actual materials cost, $.97 per pound
● Standard variable-overhead rate, $.80 per direct-labor hour
● Standard direct-labor cost, $8 per hour
● Standard materials cost, $1 per pound
● Standard pounds of material in a finished unit, 3
● Standard direct-labor hours per finished unit, 5
Compute the following: (a) Materials price variance; (b) Materials
quantity
variance; (c) Labor rate variance; (d) Labor usage variance; (e)
Variable overhead
spending variance; (f) Variable overhead efficiency variance; and
(g) Overall
production variance for the engine division.
Computation of direct material variances
| 
 1. Standard quantity required per unit in pounds  | 
 3 pounds  | 
|
| 
 2. Standard quantity required in for actual production in pounds (1000units )  | 
 SQ  | 
 3000 pounds (1000 units * 3 pounds )  | 
| 
 3. Actual quantity required for actual production (1000 units )  | 
 AQ  | 
 3300 pounds  | 
| 
 4. Actual price per pound  | 
 AP  | 
 $ 0.97  | 
| 
 5. Standard price per pound  | 
 SP  | 
 $ 1  | 
| 
 A) Direct material cost variance  | 
 SQ* SP – AQ *AP 3000 pounds *$1- 3300*$ 0.97 $ 3000- $ 3201 $ 201U(Unfavorable)  | 
| 
 B) Direct material price variance  | 
 AQ*SP- AQ*AP 3300 pounds * $ 1 – 3300 pounds *$ 0.97 $ 3300- $ 3201 99F( Favorable )  | 
| 
 C) Direct Material Usage variance  | 
 SQ* SP- AQ* SP 3000 pounds * $1 – 3300 pounds $ 1 $ 300 U( unfavorable)  | 
Computation of labor variances:
| 
 1. Standard labor hours required per unit  | 
 5 hrs  | 
|
| 
 2. Standard hours required for actual production (1000units)  | 
 SH  | 
 5000 hrs (1000 units * 5 hrs )  | 
| 
 3. Actual labor Hours required for actual production  | 
 AH  | 
 5500 hrs  | 
| 
 4. Actual labor rate per hour  | 
 AR  | 
 $ 7.70  | 
| 
 5. Standard labor rate per hour  | 
 SR  | 
 $ 8.0  | 
Actual labor rate per hour = Actual cost incurred for labor hours / Actual hrs
= $ 42,350/ 5500 hrs
= $ 7.70
| 
 Labor cost variance  | 
 SH* SR– AH *AR 5000hrs *$ 8.00 – 5500 hrs *$ 7.70 $ 40,000 - $ 42,350 $ 2,350 U (unfavorable)  | 
| 
 Labor rate variance  | 
 AH*SR- AH*AR 5500 hrs * $ 8 – 5500 hrs *$ 7.70 $ 44,000 - $ 42,350 $ 1,650 F (Favorable)  | 
| 
 Labor usage variance  | 
 SH* SR- AH* SR 5000 hrs *$ 8.00- 5500hrs * $ 8.00 $ 40000- $ 44,000 $ 4000 U (unfavorable )  | 
Computation of variable overhead variances:
| 
 1. Standard variable overhead hours required per unit  | 
 5 hrs  | 
|
| 
 2. Standard hours required for actual production units (1000units )  | 
 SOH  | 
 1000 units * 5 hrs = 5000hrs Actual production * Standard hours per unit  | 
| 
 3. Actual variable overhead Hours required per unit  | 
 AOH  | 
 5500 hrs  | 
| 
 4. Actual overhead rate per unit  | 
 AR  | 
 $ 0.84  | 
| 
 5. Standard variable overhead per unit  | 
 SR  | 
 $ 1.00  | 
Actual variable overhead rate per hour = Actual variable overheads incurred / Actual hrs
= $ 4620/ 5000 hrs
= $ 0.84
| 
 Variable overhead cost variance  | 
 SOH* SR– AOH *AR 5000*$ 1.00 -5500*$ 0.84 $ 5000- $ 4620 $ 380 F (Favorable)  | 
| 
 Variable overhead spending variance  | 
 AOH*SR- AOH*AR 5500hrs $ 1.00- 5500 hrs * $ 0.84 $ 5500- $ 4620 $ 880 F (Favorable)  | 
| 
 Variable overhead efficiency variance  | 
 SOH* SR- AOH* SR 5000 hrs * $ 1.00- 5500 hrs *$ 1.00 $ 5000 -$ 5500 500 U (Unfavorable)  | 
Please do rate if my answer was found helpful. Thankyou !!!!!!