In: Accounting
The controller of Blossom Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs.
Total Electricity Costs |
Total Machine Hours |
|||||||
January | $2,660 | 230 | ||||||
February | 3,050 | 330 | ||||||
March | 3,520 | 460 | ||||||
April | 4,770 | 690 | ||||||
May | 3,190 | 420 | ||||||
June | 4,960 | 790 | ||||||
July | 4,030 | 650 | ||||||
August | 3,870 | 590 | ||||||
September | 5,040 | 670 | ||||||
October | 4,270 | 610 | ||||||
November | 3,260 | 330 | ||||||
December | 8,460 | 810 |
(a)
Determine the fixed- and variable-cost components using the
high-low method.
Fixed-costs | $ | |
Variable-costs | $ |
eTextbook and Media
(b)
What electricity cost does the cost equation estimate for a level
of activity of 460 machine hours?
Electricity costs | $ |
By what amount does this differ from March’s observed cost for 460
machine hours?
Amount differ | $ |
eTextbook and Media
(c)
What electricity cost does the cost equation estimate for a level
of activity of 790 machine hours?
Electricity costs | $ |
By what amount does this differ from June’s observed cost for 790
machine hours?
Amount differ | $ |
Answer -
(a) Answer -
Fixed costs = $360
Variable costs = $10 per machine hour
Calculation:
As per given information,
Highest activity cost = $8,460
Lowest activity cost = $2,660
Highest activity = 810 machine hours
Lowest activity = 230 machine hours
So,
Variable cost = (Highest activity cost - Lowest activity cost) / (Highest activity - Lowest activity)
= ($8,460 - $2,660) / (810 machine hours - 230 machine hours)
= $5,800 / 580 machine hours
= $10 per machine hour
Now,
Fixed cost = Highest activity cost - (Variable cost per machine hour * Highest activity)
= $8,460 - ($10 per machine hour * 810 machine hours)
= $360
(b) Answer -
Electricity costs = $4,960
Amount differ = $1,440
Calculation:
As per given information,
Observed electricity cost for level of activity of 460 machine hours is $3,520 (total electricity cost for March).
Now,
Electricity costs = Fixed costs + (Variable cost per machine hour * Level of activity)
= $360 + ($10 per machine hour * 460 machine hours)
= $4,960
Amount differ = Electricity costs - Observed electricity cost for level of activity of 460 machine hours
= $4,960 - $3,520
= $1,440
(c) Answer -
Electricity costs = $8,260
Amount differ = $3,300
Calculation:
As per given information,
Observed electricity cost for level of activity of 790 machine hours is $4,960 (total electricity cost for June).
Now,
Electricity costs = Fixed costs + (Variable cost per machine hour * Level of activity)
= $360 + ($10 per machine hour * 790 machine hours)
= $8,260
Amount differ = Electricity costs - Observed electricity cost for level of activity of 790 machine hours
= $8,260 - $4,960
= $3,300