Question

In: Accounting

22. Fletcher Company collected the following data regarding production of one of its products. Compute the...

22. Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead cost variance.

Direct labor standard (2.0 hrs. @ $13.40/hr.) $ 26.80 per finished unit
Actual direct labor hours 92,500 hrs.
Budgeted units 47,500 units
Actual finished units produced 45,500 units
Standard variable OH rate (2 hrs. @ $15.20/hr.) $ 30.40 per finished unit
Standard fixed OH rate ($589,000/47,500 units) $ 12.40 per unit
Actual cost of variable overhead costs incurred $ 1,379,200
Actual cost of fixed overhead costs incurred $ 470,000

Multiple Choice

  • $20,750 unfavorable.

  • $4,000 favorable.

  • $21,100 unfavorable.

  • $17,100 favorable.

23. Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $17 per hour. During August, Hassock produced 14,000 units and used 28,160 hours of direct labor at a total cost of $476,020. What is Hassock’s labor rate variance for August?

Multiple Choice

  • $2,685 unfavorable.

  • $2,685 favorable.

  • $2,700 favorable.

  • $5,385 favorable.

  • $2,700 unfavorable.

  • $20,750 favorable.

24.

Fletcher Company collected the following data regarding production of one of its products. Compute the fixed overhead cost variance.

Direct labor standard (2 hrs. @ $13.40/hr.) $ 26.80 per finished unit
Actual direct labor hours 100,500 hrs.
Budgeted units 51,500 units
Actual finished units produced 49,500 units
Standard variable OH rate (2 hrs. @ $16.40/hr.) $ 32.80 per finished unit
Standard fixed OH rate ($588,000/60,000 units) $ 9.80 per unit
Actual cost of variable overhead costs incurred $ 1,618,600
Actual cost of fixed overhead costs incurred $ 590,000

Multiple Choice

  • $104,900 unfavorable.

  • $16,400 unfavorable.

  • $104,900 favorable.

  • $21,400 favorable.

  • $21,400 unfavorable.

25. Fletcher Company collected the following data regarding production of one of its products. Compute the standard quantity allowed for the actual output.

Direct materials standard (4 lbs. @ $2/lb.) $ 8 per finished unit
Actual direct materials used 155,000 lbs.
Actual finished units produced 38,000 units
Actual cost of direct materials used $ 308,000

Multiple Choice

  • 304,000 pounds.

  • 152,000 pounds.

  • 38,000 pounds.

  • 76,000 pounds.

  • 155,000 pounds.

Solutions

Expert Solution

22. Variable overhead cost variance = Standard variable overhead cost - Actual variable overhead cost

= ($30.40 × 45,500) - $1,379,200
= $1,383,200 - $1,379,200
$4000 favourable.
Since actual variable cost is less than standard variable cost, it is favourable variance.

23. Labour rate variance = (Actual rate - Standard rate) x Actual hours worked

Actual rate = Actual labour cost/ actual labour hours = $476,020/28,160

Standard rate = $17

Let's apply the equation,
Labour rate variance = [($476,020/28,160) × $17] × 28,160
= $2,700 unfavourable.
Since actual direct labour cost is less than standard labour cost, it is unfavourable variance.

24. Fixed overhead cost variance = Fixed overhead absorbed - actual fixed overhead incurred

Fixed overhead absorbed = 49,500 × $9.80

Fixed overhead cost variance = ($49,500 × $9.80) - $590,000 = $109,400 unfavourable.
Actual fixed overhead is more than absorbed overhead. Hence it is unfavourable.

25. Standard quantity allowed = *standard quantity × standard price
= (38,000 × 4) × $2
= 152,000 × $2
= 304,000 pounds

* To produce 1 unit of finished product, the standard pounds required is 4. Hence to produce 38,000 units, the standard pounds needed is 38,000 × 4.


Related Solutions

Fletcher Company collected the following data regarding production of one of its products. Compute the variable...
Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.60/hr.) $ 25.20 per finished unit Actual direct labor hours 101,500 hrs. Budgeted units 61,000 units Actual finished units produced 50,000 units Standard variable OH rate (2 hrs. @ $16.20/hr.) $ 32.40 per finished unit Standard fixed OH rate ($603,900/61,000 units) $ 9.90 per unit Actual cost of variable overhead costs incurred $ 1,614,000 Actual...
Parallel Enterprises has collected the following data on one of its products. During the period the...
Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. What is the direct materials price variance? Direct materials – standard (7 kg. @ $2.40/kg) $16.80 per finished unit Actual cost of materials purchased $402,500 Actual direct materials purchased and used 158,000 lbs
Parallel Enterprises has collected the following data on one of its products. During the period the...
Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. What is the direct materials price variance? Direct materials – standard (7 kg. @ $2.40/kg) $16.80 per finished unit Actual cost of materials purchased $402,500 Actual direct materials purchased and used 158,000 lbs a. $23,300 U b. $23,300 F c. $40,800 F d. $40,800 U e. $17,500 U Parallel Enterprises has collected the following data on one of its products....
1.) Georgia, Inc. has collected the following data on one of its products. The direct materials...
1.) Georgia, Inc. has collected the following data on one of its products. The direct materials price variance is: Direct materials standard (3 lbs @ $1/lb) $3 per finished unit Total direct materials cost variance—unfavorable $22,250 Actual direct materials used 100,000 lbs. Actual finished units produced 25,000 units 2.) Milltown Company specializes in selling used cars. During the month, the dealership sold 32 cars at an average price of $16,000 each. The budget for the month was to sell 30...
Variance Analysis Peter Enterprises has collected the following data on one of its products. During the...
Variance Analysis Peter Enterprises has collected the following data on one of its products. During the period the company produced生产了(件) 25,000 units. The direct materials quantity variance 直接原材料数量差异is: Direct materials standard (7 kg. @ $2.05/kg) $14.35 per finished unit Actual cost of materials purchased $332,150 Actual direct materials purchased and used 151,000 kg Multiple Choice $22,600 favorable. $26,600 unfavorable. $49,200 favorable. $49,200 unfavorable. $22,600 unfavorable.
Barbaro Production Company has developed the following standards for one of its products: STANDARD VARIABLE COST...
Barbaro Production Company has developed the following standards for one of its products: STANDARD VARIABLE COST CARD One Unit of Product Materials: 30 square feet × $5 per square foot $150.00 Direct labor: 16 hours × $7 per hour 112.00 Variable manufacturing overhead: 16 direct labor hours × $5 per hour 80.00 Total standard variable cost per unit $342.00 The company records materials price variances at the time of purchase. The following activity occurred during the month of April: Materials...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into...
Fletcher Fabrication, Inc., produces three products by a joint production process. Raw materials are put into production in Department X, and at the end of processing in this department, three products appear. Product A is sold at the split-off point with no further processing. Products B and C require further processing before they are sold. Product B is processed in Department Y, and product C is processed in Department Z. The company uses the estimated net realizable value method of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT