In: Accounting
22. Fletcher Company collected the following data regarding
production of one of its products. Compute the variable overhead
cost variance.
Direct labor standard (2.0 hrs. @ $13.40/hr.) | $ | 26.80 | per finished unit | |
Actual direct labor hours | 92,500 | hrs. | ||
Budgeted units | 47,500 | units | ||
Actual finished units produced | 45,500 | units | ||
Standard variable OH rate (2 hrs. @ $15.20/hr.) | $ | 30.40 | per finished unit | |
Standard fixed OH rate ($589,000/47,500 units) | $ | 12.40 | per unit | |
Actual cost of variable overhead costs incurred | $ | 1,379,200 | ||
Actual cost of fixed overhead costs incurred | $ | 470,000 | ||
Multiple Choice
$20,750 unfavorable.
$4,000 favorable.
$21,100 unfavorable.
$17,100 favorable.
23. Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $17 per hour. During August, Hassock produced 14,000 units and used 28,160 hours of direct labor at a total cost of $476,020. What is Hassock’s labor rate variance for August?
Multiple Choice
$2,685 unfavorable.
$2,685 favorable.
$2,700 favorable.
$5,385 favorable.
$2,700 unfavorable.
$20,750 favorable.
24.
Fletcher Company collected the following data regarding
production of one of its products. Compute the fixed overhead cost
variance.
Direct labor standard (2 hrs. @ $13.40/hr.) | $ | 26.80 | per finished unit | |
Actual direct labor hours | 100,500 | hrs. | ||
Budgeted units | 51,500 | units | ||
Actual finished units produced | 49,500 | units | ||
Standard variable OH rate (2 hrs. @ $16.40/hr.) | $ | 32.80 | per finished unit | |
Standard fixed OH rate ($588,000/60,000 units) | $ | 9.80 | per unit | |
Actual cost of variable overhead costs incurred | $ | 1,618,600 | ||
Actual cost of fixed overhead costs incurred | $ | 590,000 | ||
Multiple Choice
$104,900 unfavorable.
$16,400 unfavorable.
$104,900 favorable.
$21,400 favorable.
$21,400 unfavorable.
25. Fletcher Company collected the following data regarding
production of one of its products. Compute the standard quantity
allowed for the actual output.
Direct materials standard (4 lbs. @ $2/lb.) | $ | 8 | per finished unit | |
Actual direct materials used | 155,000 | lbs. | ||
Actual finished units produced | 38,000 | units | ||
Actual cost of direct materials used | $ | 308,000 | ||
Multiple Choice
304,000 pounds.
152,000 pounds.
38,000 pounds.
76,000 pounds.
155,000 pounds.
22. Variable overhead cost variance = Standard variable overhead cost - Actual variable overhead cost
= ($30.40 × 45,500) - $1,379,200
= $1,383,200 - $1,379,200
$4000 favourable.
Since actual variable cost is less than standard variable cost, it
is favourable variance.
23. Labour rate variance = (Actual rate - Standard rate) x Actual hours worked
Actual rate = Actual labour cost/ actual labour hours = $476,020/28,160
Standard rate = $17
Let's apply the equation,
Labour rate variance = [($476,020/28,160) × $17] × 28,160
= $2,700 unfavourable.
Since actual direct labour cost is less than standard labour cost,
it is unfavourable variance.
24. Fixed overhead cost variance = Fixed overhead absorbed - actual fixed overhead incurred
Fixed overhead absorbed = 49,500 × $9.80
Fixed overhead cost variance = ($49,500 × $9.80) - $590,000 =
$109,400 unfavourable.
Actual fixed overhead is more than absorbed overhead. Hence it is
unfavourable.
25. Standard quantity allowed = *standard quantity × standard
price
= (38,000 × 4) × $2
= 152,000 × $2
= 304,000 pounds
* To produce 1 unit of finished product, the standard pounds required is 4. Hence to produce 38,000 units, the standard pounds needed is 38,000 × 4.