Question

In: Finance

A manufacturer of the famous swimwear line needs help planning production for next year.

A manufacturer of the famous swimwear line needs help planning production for next year. Demand for swimwear follows a seasonal pattern, as shown below. Given the following costs and demand forecasts

 

Beginning workforce: 12 workers

Beginning inventory: 0

Subcontracting capacity: unlimited

Overtime capacity: 2000 units/month

Production rate per worker: 200 units/month

Regular wage rate : $10 per unit

Overtime wage rate: $20 per unit

Subcontracting cost: $25 per unit

Hiring cost: $150 per worker Firing cost: $250 per worker

Holding cost: $0.75 per unit/month

Backordering cost: $5 per unit/month

a. Level production with overtime and subcontracting, as needed.

b. Level production with backorders as needed.

c. 4000 units regular production from May through September and as much regular, over- time, and subcontracting production in the other months as needed to meet annual demand.

d. Which strategy would you recommend?

Solutions

Expert Solution

MONTH JAN FEB MARCH APRIL MAY JUNE JULY AUGUST SEP OCT NOV DEC
DEMAND 2000 1000 1000 1500 6000 8000 10000 6000 2000 1000 1000 4000

 

Opening workforce: 12 people
Production rate per worker: 200 units/month
No. of workers required each month = Demand each month/200 units (example for January= 2000/200=10 workers)

 

MONTH JAN FEB MARCH APRIL MAY JUNE JULY AUGUST SEP OCT NOV DEC
No. of workers 10 5 5 7.5 or 8 30 40 50 30 10 5 5 20

 

Note that extra number of workers are required only for months May, June, July, August and December. I will be addressing the following questions only for these months as for the rest of the months normal workers with normal wage rates will determine production.

 

a. Level production with overtime and subcontracting
Overtime capacity is 2000 units/ month
existing number of workforce* No. of units each can produce = 12*200= only 2400 units can be produced by existing workers in normal hours. If 4400 units > demand > 2400 units, overtime hours can be utilized.

 

For December, to produce 4000 units, labour cost for 12 workers would be = (2400*10)+(1600*20)= $56,000


Now, for the remaining months, i.e.. May to August, up to 4000 units, the labour cost would be the same ($56,000)

 

Calculations for excess production is as follows (subcontracting cost):
May: 6000-4000 units= 2000 units *25 per unit = $ 50,000
Total cost for May= $ 56,000+ $50,000 = $106,000

June: 8000- 4000 units = 4000*25 = $ 100,000
Total cost for June = $56,000 + $100,000= $ 156,000

July: 10,000-4000 units = 6000* 25 = $ 150,000
Total cost for July = $56,000+$150,000 = $206,000

August: 6000-4000 units = 2000*25 = $50,000
Total cost for August = $56,000 + $50,000 = $106,000

Total cost for these given months by using overtime/subcontracting = $106,000+$156,000+$206,000+$106,000+$56,000 = $630,000

 

b. level production with backorders

Now back orders are excess of demand over production. Pls note that this case arises again only when demand goes above 2400 units in any given month which is the case in months May to August and December. Backorder cost is $5 per unit /month. Let us calculate the backorder cost for these months:

May: Backlog cost = (6000-2400 units)*5 = $18,000
June: Backlog cost = (8000-2400units) *5= $28,000
July: Backlog cost = (10,000 - 2400 units)*5 = $38,000
August: Backlog cost = (6000-2400 units)*5 = $18,000
December: Backlog cost = (4000-2400 units)*5 = $8,000
Total excess cost = $110,000

 

c. If 4000 units produced from May to September

MONTH JAN FEB MARCH APRIL MAY JUNE JULY AUGUST SEP OCT NOV DEC
DEMAND 2000 1000 1000 1500 4000 4000 4000 4000 4000 1000 1000 4000

Annual demand according to original table is 43,500 units. In the table above only 31,500 units are being accounted for. Excess units that have to be adjusted in other months are 43,500 units - 31,500 units = 12,000. These 12,000 units can be adjusted in other months as follows: (note holding inventory per months is $0.75 per unit/month)
May to September demand = 32000 units, production = 20,000 units. Remaining 12000 units have to be produced in months Jan to April by producing extra that what is actually produced. extra 3000 units have to be produced in these months

Jan: demand = 2000, production= 2000+3000
Feb: demand = 1000, production = 1000+3000
March: demand = 1000, production = 1000+3000
April: demand = 1500, production = 1500+3000

Cost
Jan: (2400 units*10)+(2000*20)+(600*25) = $65,500 + holding excess inventory cost (2000*0.75*4)+(1000*0.75*5)= 9750
Total Jan cost = 75250
Feb: (2400 units*10)+(1600*20)+holding excess inventory cost (3000*0.75*4) = $65,000
March: (2400 units*10)+(1600*20)+holding excess inventory cost (3000*0.75*4) = $65,000
April: (2400 units*10)+(1600*20)+(500*25)+holding excess inventory cost (3000*0.75*3) = $75,250

Month Jan Feb March April May June July August Sep Oct Nov Dec Total
Strategy A 20,000 10,000 10,000 15,000 106,000 156,000 206,000 106,000 20,000 10,000 10,000 56,000 725,000
Strategy B 20,000 10,000 10,000 15,000 42,000 52,000 62,000 42,000 20,000 10,000 10,000 32,000 325,000
Strategy C 75250 65,000 65,000 75,250 40,000* 40,000 40,000 40,000 20,000 10,000 10,000 40,000 480,500

40,000* it is given in the question that 4000 units would be regular production from months May to September. So I have assumed regular wage rate of $10 per unit per month

 

d. which strategy to choose
As you can see, cost is lowest in Strategy B, $325,000. This is because backorder cost is only $5 per unit/month while overtime and subcontracting is more.


Related Solutions

A manufacturer of integrated circuits is planning production for the next four months. The forecast demand...
A manufacturer of integrated circuits is planning production for the next four months. The forecast demand for the circuits is shown in the following table. Circuit September October November December IC341 650 875 790 1100 IC256 900 350 1200 1300 At the beginning of September, the warehouse is expected to be completely empty. There is room for no more than 1,800 integrated circuits to be stored. Holding costs for both types is $0.05 per unit per month. Because workers are...
In the planning of the monthly production for the next four months, in each month a...
In the planning of the monthly production for the next four months, in each month a company must operate either a normal shift or an extended shift (but not both) if it produces. It may choose not to produce in a month. A normal shift costs $100,000 per month and can produce up to 5,000 units per month. An extended shift costs $140,000 per month and can produce up to 7,500 units per month. The cost of holding inventory is...
Question 1 John is the production manager of Kam Kee Limited, a famous soy sauce manufacturer...
Question 1 John is the production manager of Kam Kee Limited, a famous soy sauce manufacturer in Hong Kong. Currently, he is reviewing the possibility of replacing the old brewing system in order to boost production volume. The old brewing system was purchased eight years ago with a total cost of $6,600,000. It has a 12-year economic life with four years remaining and zero salvage value. If this system were to be sold today, it would be worth $2,200,000. The...
Question 1 John is the production manager of Kam Kee Limited, a famous soy sauce manufacturer...
Question 1 John is the production manager of Kam Kee Limited, a famous soy sauce manufacturer in Hong Kong. Currently, he is reviewing the possibility of replacing the old brewing system in order to boost production volume. The old brewing system was purchased eight years ago with a total cost of $6,600,000. It has a 12-year economic life with four years remaining and zero salvage value. If this system were to be sold today, it would be worth $2,200,000. The...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to meet sales demand in the coming year. He is also trying to determine how the company’s profits might be increased in the coming year. This problem asks you to use cost-volume-profit concepts to help Waterways understand contribution margins of some of its products and decide whether to mass-produce any of them. Waterways markets a simple water control and timer that it mass-produces. Last year,...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to meet sales demand in the coming year. He is also trying to determine how the company’s profits might be increased in the coming year. This problem asks you to use cost-volume-profit concepts to help Waterways understand contribution margins of some of its products and decide whether to mass-produce any of them. Waterways markets a simple water control and timer that it mass-produces. Last year,...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to meet sales demand in the coming year. He is also trying to determine how the company’s profits might be increased in the coming year. This problem asks you to use cost-volume-profit concepts to help Waterways understand contribution margins of some of its products and decide whether to mass-produce any of them. Waterways markets a simple water control and timer that it mass-produces. Last year,...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to meet sales demand in the coming year. He is also trying to determine how the company’s profits might be increased in the coming year. This problem asks you to use cost-volume-profit concepts to help Waterways understand contribution margins of some of its products and decide whether to mass-produce any of them. Waterways markets a simple water control and timer that it mass-produces. Last year,...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to...
The Vice President for Sales and Marketing at Waterways Corporation is planning for production needs to meet sales demand in the coming year. He is also trying to determine how the company’s profits might be increased in the coming year. This problem asks you to use cost-volume-profit concepts to help Waterways understand contribution margins of some of its products and decide whether to mass-produce any of them. Waterways markets a simple water control and timer that it mass-produces. Last year,...
A manufacturer who produces cereal wants to check the quality of their production line. If the...
A manufacturer who produces cereal wants to check the quality of their production line. If the cereal boxes are under filled, then customers may complain and the company’s image will suffer. If the cereal boxes are over filled, then the cost of production will go up which will negatively impact the profit made from sales. The company has set up production so that the boxes, on average, have 17 ounces of cereal. Assume that the weight of cereal in a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT