Question

In: Statistics and Probability

A new industrial oven has just been installed at the Piatt Bakery. To develop experience regarding...

A new industrial oven has just been installed at the Piatt Bakery. To develop experience regarding
the oven temperature, an inspector reads the temperature at four di erent places inside the oven
each half hour.
Reading
Time 1 2 3 4
8:00 A.M. 340 350 355 339
8:30 A.M. 344 342 338 338
9:00 A.M. 341 345 347 343
9:30 A.M. 339 339 341 341
10:00 A.M. 337 342 346 341
10:30 A.M. 339 340 339 340
1. Determine the control limits for the mean temperature. Determine the grand mean. Plot the
experience on a chart.
2. Interpret the chart. Does there seem to be a time when the temperature is out of control?
3. Determine the control limits for the range. Plot the experience on a chart.
4. Does there seem to be a time when there is too much variation in the temperature?
5. Determine the CL, UCL, and LCL for the S-chart. Plot the chart and interpret the result.
6. Determine the CL, UCL, and LCL for the control charts of the median and the range. Plot
the charts and interpret the results.
7. If you have to decide which charts to use among the presented charts, which you prefer?
Justify.
8. Assume normality distribution for the oven temperature and use estimators of the mean and
standard deviation to determine the process capability by computing the necessary indexes.
The lower and upper speci cations limits are 333.1 and 350.42, respectively.
Interpret the results.

Solutions

Expert Solution

please rate my answer and comment for doubt.


Related Solutions

A new industrial oven has just been installed at Piatt Bakery. To develop experience regarding the...
A new industrial oven has just been installed at Piatt Bakery. To develop experience regarding the oven temperature, an inspector reads the temperature at four different places inside the oven each half hour starting at 8:00 a.m. The last reading was at 10:30 a.m., for a total of six samples. The first reading, taken at 8:00 a.m., was 337 degrees Fahrenheit. (Only the last two digits are given in the following table to make the computations easier.) Reading Time 1...
Amanda's Bakery plans to purchase a new oven for its store. The oven has an estimated...
Amanda's Bakery plans to purchase a new oven for its store. The oven has an estimated useful life of 4 years. The estimated pretax cash flows for the oven are as shown in the table that​ follows, with no anticipated change in working capital. Amanda's Bakery has a 14​% ​after-tax required rate of return and a 35​% income tax rate. Assume depreciation is calculated on a​ straight-line basis for tax purposes using the initial investment in the oven and its...
Bakery plans to purchase a new oven for its store. The oven has an estimated useful...
Bakery plans to purchase a new oven for its store. The oven has an estimated useful life of 4 years. The estimated pretax cash flows for the oven are as shown in the table that? follows, with no anticipated change in working capital. Bertha's Bakery has a 14?% ?after-tax required rate of return and a 33?% income tax rate. Assume depreciation is calculated on a? straight-line basis for tax purposes using the initial oven investment and estimated terminal disposal value...
You need a new oven for your bakery. Your current oven is worn out so you...
You need a new oven for your bakery. Your current oven is worn out so you are trying to decide which one of two ovens to buy as a replacement. Whichever oven you purchase will be replaced after its useful life. Oven A costs $25,000 and costs $3,000 a year to operate over an 8-year life. Oven B costs $20,000 and costs $4,500 a year to operate over a 6-year life. Given this information, which one of the following statements...
A new machine has just been installed to cut and rough-shape large slugs. The slugs are...
A new machine has just been installed to cut and rough-shape large slugs. The slugs are then transferred to a precision grinder. One of the critical measurements is the outside diameter. The quality control inspector randomly selected five slugs each half-hour, measured the outside diameter, and recorded the results. The measurements (in millimeters) for the period 8:00 a.m. to 10:30 a.m. follow. Outside Diameter (millimeters) Time 1 2 3 4 5 8:00 87.1 87.4 87.9 87.1 87.0 8:30 86.9 88.5...
Exercise 19-22 (LO19-4, LO19-6) A new machine has just been installed to cut and rough-shape large...
Exercise 19-22 (LO19-4, LO19-6) A new machine has just been installed to cut and rough-shape large slugs. The slugs are then transferred to a precision grinder. One of the critical measurements is the outside diameter. The quality control inspector randomly selected five slugs each half-hour, measured the outside diameter, and recorded the results. The measurements (in millimeters) for the period 8:00 a.m. to 10:30 a.m. follow. Outside Diameter (millimeters) Time 1 2 3 4 5 8:00 87.3 87.3 88.1 87.0...
Exercise 19-22 (LO19-4, LO19-6) A new machine has just been installed to cut and rough-shape large...
Exercise 19-22 (LO19-4, LO19-6) A new machine has just been installed to cut and rough-shape large slugs. The slugs are then transferred to a precision grinder. One of the critical measurements is the outside diameter. The quality control inspector randomly selected five slugs each half-hour, measured the outside diameter, and recorded the results. The measurements (in millimeters) for the period 8:00 a.m. to 10:30 a.m. follow. Outside Diameter (millimeters) Time 1 2 3 4 5 8:00 87.3 87.5 88.0 87.1...
A new paint process has been installed in a manufacturing facility. With this process, the facility...
A new paint process has been installed in a manufacturing facility. With this process, the facility has to wait only 58 minutes for drying before the next coat can be applied. That is, with the new process, the average dry time was 58 minutes and the standard deviation was 15.9 minutes for a sample of 30 automobiles. Compare this to the process that was replaced. This process (old process) was studied for 50 automobiles and the average dry time was...
Assume that a simulation model of an industrial process has just been completed. A sample of...
Assume that a simulation model of an industrial process has just been completed. A sample of output from the process and the simulation model appears below: Observation History Simulation 1 111 109 2 113 106 3 76 126 4 83 98 5 104 96                         Is there evidence to believe that the simulation adequately represents the real system with relation to this particular metric? Why or why not? State any assumptions you make. Later, the simulation is run under three...
Assume that a simulation model of an industrial process has just been completed. A sample of...
Assume that a simulation model of an industrial process has just been completed. A sample of output from the process and the simulation model appears below: Observation History Simulation 1 111 109 2 113 106 3 76 126 4 83 98 5 104 96 Is there evidence to believe that the simulation adequately represents the real system with relation to this particular metric? Why or why not? State any assumptions you make.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT