Question

In: Accounting

Department G had 1,800 units 25% completed at the beginning of the period, 12,300 units were...

Department G had 1,800 units 25% completed at the beginning of the period, 12,300 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period:

Work in process, beginning of period $25,000
Costs added during period:
  Direct materials (12,000 units at $8) 96,000
  Direct labor 75,000
  Factory overhead 25,000

All direct materials are placed in process at the beginning of production and the first-in, first-out method of inventory costing is used. The total cost of the units started and completed during the period is (do not round unit cost calculations)

$153,136

$84,000

$170,420

$187,704

Solutions

Expert Solution

The total cost of the units started and completed during the period is calculated below:

Total Equivalent units are calculated below:

A) Total Equivalent units of Material = (12,300 - 1,800) *100% + 1500 *100

= 10,500 units + 1,500 Units

= 12,000 units

B) Total Equivalent units of Conversion Cost = 1800*75% + (12,300 -1,800) *100% + 1500 *20%

= 1,350 + 10,500 + 300

= 12,150 Units

Cost Per Equivalent units is calculated below:

A)Cost Per Equivalent units of Material :

Cost Per Equivalent units of Material = $96,000 / 12,000 units

= $8

B)Cost Per Equivalent units of Conversion Cost :

Cost Per Equivalent units of Conversion Cost = ($75,000(Direct Labor) + $25,000 (Direct Labor))/ 12,150 Units

= $100,000/12,150

   = $8.2305

The total cost of the units started and completed during the period = 10,500 Units* ($8 + $8.2305)

   = 10,500 Units* $16.2305

= $170,420

So correct answer is option (3) or $170,420


Related Solutions

Department G had 2,160 units 25% completed at the beginning of the period, 12,300 units were...
Department G had 2,160 units 25% completed at the beginning of the period, 12,300 units were completed during the period, 1,800 units were 20% completed at the end of the period, and the following manufacturing costs were debited to the departmental work in process account during the period: Work in process, beginning of period $26,400 Costs added during period:    Direct materials (11,940 units at $9) 107,460    Direct labor 73,200    Factory overhead 24,400 All direct materials are placed in process at...
Department G had 2,040 units 25% completed at the beginning of the period, 12,300 units were...
Department G had 2,040 units 25% completed at the beginning of the period, 12,300 units were completed during the period; 1,700 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $33,300 Costs added during period:   Direct materials (11,960 units at $8) 95,680   Direct labor 85,800   Factory overhead 28,600 All direct materials are placed in process at the...
Department G had 2,280 units 25% completed at the beginning of the period, 12,300 units were...
Department G had 2,280 units 25% completed at the beginning of the period, 12,300 units were completed during the period, 1,900 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $28,500 Costs added during period: Direct materials (11,920 units at $9) 107,280 Direct labor 77,400 Factory overhead 25,800 All direct materials are placed in process at the...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were completed during the period, 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $31,500--- Costs added during period: Direct materials (12,900 units at $9) 116,100 --- Direct labor 75,600 --- Factory overhead 25,200. All direct materials are placed in process...
Department G had 1,800 units 25% completed at the beginning of the period, 12,700 units were...
Department G had 1,800 units 25% completed at the beginning of the period, 12,700 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $34,900 Costs added during period:    Direct materials (12,400 units at $9) 111,600    Direct labor 85,800    Factory overhead 28,600 All direct materials are placed in process at the...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were completed during the period, 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $31,000 Costs added during period:    Direct materials (12,900 units at $9) 116,100    Direct labor 85,800    Factory overhead 28,600 All direct materials are placed in process at the...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were...
Department G had 1,800 units 25% completed at the beginning of the period, 13,200 units were completed during the period, 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $33,700 Costs added during period:    Direct materials (12,900 units at $9) 116,100    Direct labor 80,400    Factory overhead 26,800 All direct materials are placed in process at the...
1) Department G had 1,800 units 25% completed at the beginning of the period, 12,800 units...
1) Department G had 1,800 units 25% completed at the beginning of the period, 12,800 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $26,500 Costs added during period:    Direct materials (12,500 units at $9) 112,500    Direct labor 88,200    Factory overhead 29,400 All direct materials are placed in process at...
Department G had 2,280 units 25% completed at the beginning of the period, 13,900 units were...
Department G had 2,280 units 25% completed at the beginning of the period, 13,900 units were completed during the period, 1,900 units were 20% completed at the end of the period, and the following manufacturing costs were debited to the departmental work in process account during the period: Work in process, beginning of period $30,900 Costs added during period:    Direct materials (13,520 units at $9) 121,680    Direct labor 137,100    Factory overhead 54,840 All direct materials are placed in process at...
Department G had 1,920 units 25% completed at the beginning of the period, 12,800 units were...
Department G had 1,920 units 25% completed at the beginning of the period, 12,800 units were completed during the period, 1,600 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period: Work in process, beginning of period $29,700 Costs added during period:   Direct materials (12,480 units at $8) 99,840   Direct labor 81,000   Factory overhead 27,000 All direct materials are placed in process at the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT