In: Accounting
Department G had 1,800 units 25% completed at the beginning of the period, 12,300 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period:
Work in process, beginning of period | $25,000 |
Costs added during period: | |
Direct materials (12,000 units at $8) | 96,000 |
Direct labor | 75,000 |
Factory overhead | 25,000 |
All direct materials are placed in process at the beginning of production and the first-in, first-out method of inventory costing is used. The total cost of the units started and completed during the period is (do not round unit cost calculations)
$153,136
$84,000
$170,420
$187,704
The total cost of the units started and completed during the period is calculated below:
Total Equivalent units are calculated below:
A) Total Equivalent units of Material = (12,300 - 1,800) *100% + 1500 *100
= 10,500 units + 1,500 Units
= 12,000 units
B) Total Equivalent units of Conversion Cost = 1800*75% + (12,300 -1,800) *100% + 1500 *20%
= 1,350 + 10,500 + 300
= 12,150 Units
Cost Per Equivalent units is calculated below:
A)Cost Per Equivalent units of Material :
Cost Per Equivalent units of Material = $96,000 / 12,000 units
= $8
B)Cost Per Equivalent units of Conversion Cost :
Cost Per Equivalent units of Conversion Cost = ($75,000(Direct Labor) + $25,000 (Direct Labor))/ 12,150 Units
= $100,000/12,150
= $8.2305
The total cost of the units started and completed during the period = 10,500 Units* ($8 + $8.2305)
= 10,500 Units* $16.2305
= $170,420
So correct answer is option (3) or $170,420