In: Accounting
1) Department G had 1,800 units 25% completed at the beginning of the period, 12,800 units were completed during the period; 1,500 units were 20% completed at the end of the period, and the following manufacturing costs debited to the departmental work in process account during the period:
Work in process, beginning of period | $26,500 |
Costs added during period: | |
Direct materials (12,500 units at $9) | 112,500 |
Direct labor | 88,200 |
Factory overhead | 29,400 |
All direct materials are placed in process at the beginning of production and the first-in, first-out method of inventory costing is used. What is the total cost of the units started and completed during the period (round unit cost calculations to four decimal places and round your final answer to the nearest dollar)?
a.$99,000
b.$221,713
c.$180,809
d.$201,261
2) Department A had 4,700 units in Work in Process that were 79% completed at the beginning of the period at a cost of $7,600. During the period, 39,200 units of direct materials were added at a cost of $94,080, and 41,800 units were completed. At the end of the period, 2,100 units were 35% completed. All materials are added at the beginning of the process. Direct labor was $26,100 and factory overhead was $6,000. The cost of the 2,100 units in process at the end of the period if the first-in, first-out method is used to cost inventories was
a.$5,648
b.$6,256
c.$5,344
d.$5,040
3) The Thomlin Company forecasts that total overhead for the current year will be $11,333,000 with 168,000 total machine hours. Year to date, the actual overhead is $7,810,000 and the actual machine hours are 95,000 hours. If the Thomlin Company uses a predetermined overhead rate based on machine hours for applying overhead, as of this point in time (year to date), the overhead is
Round the factory overhead rate to the nearest dollar before multiplying by the number of hours.
a.$1,878,500 overapplied
b.$1,445,000 underapplied
c.$1,878,500 underapplied
d.$1,445,000 overapplied
4) . Reynolds Manufacturers Inc. has estimated total factory overhead costs of $123,600 and expected direct labor hours of 10,300 for the current fiscal year. If job number 117 incurs 1,310 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for
a.$1,310
b.$61,800
c.$15,720
d.$123,600
1 | |||||
Materials | Conversion costs | ||||
Work in process, beginning of period | 0 | 1350 | |||
Units started and complete | 11000 | 11000 | |||
Work in process, ending of period | 1500 | 300 | |||
Equivalent units of production | 12500 | 12650 | |||
Materials | Conversion costs | ||||
Costs added during period | 112500 | 117600 | |||
Divided by Equivalent units of production | 12500 | 12650 | |||
Cost per Equivalent unit of production | 9 | 9.2964 | |||
Total cost of the units started and completed = 11000*(9+9.2964)= $201261 | |||||
2 | |||||
Materials | Conversion costs | ||||
Work in process, beginning of period | 0 | 987 | |||
Units started and complete | 37100 | 37100 | |||
Work in process, ending of period | 2100 | 735 | |||
Equivalent units of production | 39200 | 38822 | |||
Materials | Conversion costs | ||||
Costs added during period | 94080 | 32100 | |||
Divided by Equivalent units of production | 39200 | 38822 | |||
Cost per Equivalent unit of production | 2.4 | 0.8269 | |||
Cost of the 2,100 units in process at the end of the period=(2100*2.4)+(735*0.8269)= $5648 | |||||
3 | |||||
Predetermined overhead rate = 11333000/168000= $67 | |||||
Overhead applied = 95000*67 = $6365000 | |||||
Overhead underapplied = 7810000-6365000 = $1445000 underapplied | |||||
4 | |||||
Work in Process will be debited and Factory Overhead will be credited for = 123600/10300*1310= $15720 | |||||