In: Finance
A project has the following cash flows: |
Year | Cash Flow | |||
0 | $ | 59,000 | ||
1 | – | 34,000 | ||
2 | – | 39,000 | ||
a. | What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) |
b. | What is the NPV of this project if the required return is 12 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
c. | What is the NPV of the project if the required return is 0 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
d. | What is the NPV of the project if the required return is 24 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) |
a.Internal rate of return is calculated using a financial calculator by inputting the below:
The IRR of project is 15.07%.
b. Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is -$2,447.70.
c. Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is -$14,000.
d. Net present value is calculated using a financial calculator by inputting the below:
The net present value of cash flows is $6,216.44.
In case of any query, kindly comment on the solution