Question

In: Accounting

XYZ Company manufactures tables. A standard cost card for the manufacture of one table shows the...

XYZ Company manufactures tables. A standard cost card for the manufacture of one table shows the following:

Standard Cost per Table:

Direct material: 4 sq. ft. @ $3/sq. ft.

$12

Direct labor: 2 hours @ $8/hr

16

Total prime costs

$28

In November, the company produced 1,000 tables. Actual production costs and quantities were:

Direct material: 3,900 sq. ft. @ $3.10/sq. ft.

$12

Direct labor: 2,300 hours @ $7.80/hr

16

Required:

Calculate the price and quantity variances for direct material and direct labor.

Solutions

Expert Solution

  • Working

Actual DATA for

1000

units

Quantity (AQ)

Rate (AR)

Actual Cost

Direct Material

3900

$              3.10

$           12,090.00

Direct labor

2300

$                7.80

$           17,940.00

Standard DATA for

1000

units

Quantity (SQ)

Rate (SR)

Standard Cost

[A]

[B]

[A x B]

Direct Material

( 4 sq ft x 1000 units)=4000 sq ft

$                   3.00

$       12,000.00

Direct labor

( 2 hours x 1000 units)=2000 hours

$                   8.00

$       16,000.00

  • Answers

Material Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Quantity

(

$                        3.00

-

$                       3.10

)

x

3900

-390

Variance

$                  390.00

Unfavourable-U

Material Quantity Variance

(

Standard Quantity

-

Actual Quantity

)

x

Standard Rate

(

4000

-

3900

)

x

$                           3.00

300

Variance

$                  300.00

Favourable-F

Labor Price Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                        8.00

-

$                       7.80

)

x

2300

460

Variance

$                  460.00

Favourable-F

Labour Efficiency Variance or Labor Quantity Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

2000

-

2300

)

x

$                           8.00

-2400

Variance

$              2,400.00

Unfavourable-U


Related Solutions

3. Dow Company manufactures tables in U.S. The standard (budgeted) cost of one unit is shown...
3. Dow Company manufactures tables in U.S. The standard (budgeted) cost of one unit is shown below: Direct materials 9 pounds at $4 per pound $36 Direct labour 2 hours at $45 per hour 90 Variable manufacturing overhead* 2 hours at $15 per hour 30 Total standard variable cost per unit $156 *The variable manufacturing overhead rate is based on direct labour hour. During March, 8,000 units were produced. The company purchased 80,000 pounds of direct materials at a cost...
Table Rock Tables, manufactures two popular tables, a country style table and a contemporary style table....
Table Rock Tables, manufactures two popular tables, a country style table and a contemporary style table. The manufacturing process for both tables requires the use of three types of machines. The time to produce the tables on each machine given in the following table: Machine   Country Table Contemporary Table Total Time Available Router 1.5 2 1000 Sander 3.0 4.5 2000 Polisher 2.5 1.5 1500 The earns a profit of $350 on the Country table, and $450 on the Contemporary table....
Speed, Inc’s Standard Cost Card for jogging suits. The standard cost for one jogging suit would...
Speed, Inc’s Standard Cost Card for jogging suits. The standard cost for one jogging suit would be: Standard Cost Card for Jogging Suits (1 ) Standard Quantity or Hours (2) Standard Price or Rate (1) × (2) Standard Cost Direct materials..................................... 3.5 yards $6 per yard $21 Direct labor........................................... 2.0 hours $18 per hour 36 Variable manufacturing overhead........... 2.0 hours $4 per hour    8 Total standard cost per suit.................... $65 Direct Labor Information The following data are for last month’s...
Q1 The standard cost card shows the following details relating to material needed to produce product...
Q1 The standard cost card shows the following details relating to material needed to produce product QPz Quantity of raw material required 20 Kg. Rate of raw material OMR 3per Kg Actual production of QPz: Production during the month 200 Kg. Quantity of material used 3,800 Kg. Raw material purchased 5000 kg @ 4 per kg. Calculate: Material Cost Variance Material Price Variance    Material Usage Variance. Also verify your answer If there is 10% increase in standard material price...
Cardinal Company has determined the following standard cost data necessary to manufacture one unit of its...
Cardinal Company has determined the following standard cost data necessary to manufacture one unit of its primary product: Direct Materials….. (6 pounds @ $20) Direct Labor…………. .(8 hours @ $15) During 20X1, Cardinal produced only 1 unit of product. This unit required 7 pounds of direct material (a total of 8 pounds were purchased at a cost of $18 per pound). In addition, total payroll costs for direct labor during 20X1 were $130 (10 hours @ $13 per hour). Required:...
The table shows the cost data for one of several identical firms in a constant cost...
The table shows the cost data for one of several identical firms in a constant cost perfectly competitive industry for product X. Fill in the table given the fixed cost is $50. Quantity of X TVC TFC TC AFC AVC ATC MC 0 0 1 70 2 120 3 155 4 193 5 242 6 302 7 370 8 462 9 571 1. In the short run, calculate the output and profit or loss for this typical firm for each...
Company X manufactures a single product for which the standard cost of one unit is as...
Company X manufactures a single product for which the standard cost of one unit is as follows: € Direct material (3.0 kg at €2 per kg)   6.00 Direct labour (1.2 hours at €10 per hour)   12.00 Manufacturing overheads 7.00 25.00 During January, the company produced 9,000 units and the actual costs were as follows: Costs:          € 24,000 kg of material    56,500 10,950 hours of labour        110,700 Overheads 61,700 228,900 Material price variance is                        ...
Owen limited uses a standard costing system. The standard cost card for one product is shown...
Owen limited uses a standard costing system. The standard cost card for one product is shown below. Direct material                  4kg @$5 per kg                                 20 Direct labour                      2 hour @ $8 per hour                     16 Variable overhead           2 hours @ $3.5 per hour               7 Total variable cost                                                                            43 Fixed overhead                 2 hours @ $7 per hour                   14 Total production cost                                                                     57 Standard selling price                                                                     70 Standard profit margin                                                                   13 The budgeted output and sales was 1000 units. Actual production and...
HalimSdnBhd uses a standard costing system. The standard cost card for one product is shown below:...
HalimSdnBhd uses a standard costing system. The standard cost card for one product is shown below: Direct Material 4 kg at RM5 per kg                      RM 20 Direct Labor 2 hours at RM8 per hour 16 Variable Overhead 2 hours at RM 7.5 per hour15 Total Product Cost 51 The budgeted output and sales was 1,000 units. Actual output for the period was 1,300 units . Actual cost was as follows: Direct Material:                       5,000 kg, costing 22,750 Direct Labor:                      2,860 hours,...
XYZ Corporation manufactures rafts for use in swimming pools. The standard cost for material and labor...
XYZ Corporation manufactures rafts for use in swimming pools. The standard cost for material and labor is $89.20 per raft. This includes 8 kilograms of direct material at a standard cost of $5.00 per kilogram, and 6 hours of direct labor at $8.20 per hour. The following data pertain to November: • Work-in-process inventory on November 1: none.             • RM inventory on November 1: 2,000 kilograms for $10,040 • Work-in-process inventory on November 30: 800 units (75 percent complete...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT