In: Finance
Data Mining is considering an expansion project. The company’s
management has decided that the initial cost of the project is
$300,000 with an additional installment cost of $80,000. The
project life is four years, during it’s life the project will
depreciate based on the following rates:
• 1st year 33%
• 2nd year 45%
• 3rd year 15%
• 4th year 7%
Management has also decided that an additional of $45,000 in
inventories and $12,000 in accounts payable needed if the project
taken today. During the next four years, the expected quantity of
merchandise to be sold each year is 15,000 units at a price of $50
per unit. The project’s fixed cost and total variable costs
estimated to be $350,000. The project has been assigned a salvage
value of $45,000 at it’s end life after four years and the weighted
average cost of capital of 10%.
*tax rate is 40%.
Based on the company’s information, the fixed capital investment(Depreciable Basis) is *
$300,000
$380,000
$220,000
$400,000
2) The change in net working capital is : *
$33,000
$45,000
$57,000
$47,000
3) Then, initial investment (I0) can be calculated as : *
$410,000
$412,000
$413,000
$415,000
4) The depreciation of the 1st year is *
$120,300
$125,400
$130,300
$116,000
5) The depreciation of the 2nd year is
$150,000
$171,000
$154,000
$183,000
6) The depreciation of the 3rd year is *
$57,000
$49,000
$40,000
$41,000
7) The depreciation of the 4th year is *
$26,200
$26,300
$26,500
$26,600
8) The the net operating cash flow after tax for the first year is *
$290,160
$285,700
$290,700
$285,900
9) The the net operating cash flow after tax for the second year is *
$255,000
$308,400
$450,600
$460,000
10) The net operating cash flow after tax for the third year is *
$250,000
$352,100
$262,800
$360,000
11) The the net operating cash flow after tax for the 4th year is *
$200,440
$300,360
$400,000
$250,640
12) The Book Value of the fixed asset at the termination after four years is *
$49,200
$0
$45,000
$45,200
13) The termination value at the end life of the project is calculated as *
$45,000
$77,760
$78,000
$$60,000
14) The NPV of the project is equal to *
$458,157.4
$645,998.5
$515,274.7
-$252,998.2
15) In conclusion, what is your decision regarding the project *
Reject the project
Accept the project
Can't determine
either accept or reject based on economic conditions
Based On Information Given, Answer should be :
1) the fixed capital investment(Depreciable Basis) is
the initial cost of the project with an additional installment
cost
= $300,000 + $80,000. =$380,000 (Option B is Right)
2) The change in net working capital is
an additional of inventories by Management, If Project taken
today,
= $45,000 (Option B is Right)
3) Then, initial investment (I0) can be calculated as
= Fixed capital Investment + Changes In Net Working capital
= $ 380,000 + $ 45,000 = $425,000 ( I think Option D Should Be
425,000 instead of 415,000)
4) The depreciation of the 1st year is
= Fixed capital Investment * Depr. rate For First year
= $ 380,000 * 33%
= $ 125,400 (Option B is Right)
5) The depreciation of the 2nd year is
= Fixed capital Investment * Depr. rate For Second year
= $380,000 * 45%
= $171,000 (Option B is Right)
6) The depreciation of the 3rd year is
Fixed capital Investment * Depr. rate For Third year
= $380,000 * 15%
= $57,000 (Option A is Right)
7) The depreciation of the 4th year is
Fixed capital Investment * Depr. rate For fourth year
= $380,000 * 7%
= $26,600 (Option D is Right)
8) The the net operating cash flow after tax for the first year
is (Based on image table)
=
9) The the net operating cash flow after tax for the second year is
(Based on image table)
=
10) The the net operating cash flow after tax for the third year is
(Based on image table)
=
11) The the net operating cash flow after tax for the fourth year
is (Based on image table)
=
12) The Book Value of the fixed asset at the termination after four
years is
= Zero (Due to 100% Depriciation of assets into Four Years)
*(Assumtion
Is Depriciation Based SLM, Not WDV)
13) The termination value at the end life of the project is
calculated as
= $ 45,000 Which is salvage value itself (Option A)
14) The NPV of the project is equal to
= $537,980.96
15) In conclusion, what is your decision regarding the
project
= Accept the project in view of positive NPV...