Question

In: Finance

Mills Mining is considering an expansion project. The proposed project has the following features: • The...

Mills Mining is considering an expansion project. The proposed project has the following features: • The project has an initial cost of $500,000--this is also the amount which can be depreciated using the three year MACRS depreciation schedule. • If the project is undertaken, at t = 0 the company will need to increase its inventories by $50,000, and its accounts payable will rise by $10,000. This net operating working capital will be recovered at the end of the project’s life (t = 4).

• If the project is undertaken, the company will realize an additional $600,000 in sales over each of the next four years (t = 1, 2, 3, 4). The company’s operating cost (not including depreciation) will equal $400,000 a year.

• The company’s tax rate is 40 percent. • At t = 4, the project’s economic life is complete, but it will have a salvage value of $50,000.

• The project’s WACC = 12 percent.

Solutions

Expert Solution


Related Solutions

Mills Mining is considering the purchase of additional equipment. The proposed project has the following​ features:...
Mills Mining is considering the purchase of additional equipment. The proposed project has the following​ features: The equipment has an invoice price of​ $390,000 and will cost​ $40,000 to modify for company use. Shipping will cost​ $10,000. The company spent​ $10,000 last year analyzing 5 competing brands of equipment before deciding that this brand was the best for their purposes. The equipment will be depreciated as a​ 3-Year MACRS asset with the following​ rates: Year 1​ – 33%, Year 2​...
ABC Corporation is considering an expansion project. The proposed project has the following features: The project...
ABC Corporation is considering an expansion project. The proposed project has the following features: The project has an initial cost of $1,000,000 (machine: $800,000, insurance: $40,000, shipping $60,000, modification: $100,000) --this is also the amount which can be depreciated using the following 3 year MACRS depreciation schedule: Year Depreciation Rate 1 33% 2 45% 3 15% 4 7% The sales price and cost are both expected to increase by 4 percent per year due to inflation. If the project is...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost of the project is $300,000 with an additional installment cost of $80,000. The project life is four years, during it’s life the project will depreciate based on the following rates: • 1st year 33% • 2nd year 45% • 3rd year 15% • 4th year 7% Management has also decided that an additional of $45,000 in inventories and $12,000 in accounts payable needed if...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost of the project is $300,000 with an additional installment cost of $80,000 and a $30,000 cost for research purposes related to the project. The project’s life is four years with a salvage value of $60,000 and it will be depreciated over four years using the straight-line method. Management has also decided that $45,000 in inventories and $12,000 in accounts payable are needed if the...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost of the project is $300,000 with an additional installment cost of $80,000 and a $30,000 cost for research purposes related to the project. The project’s life is four years with a salvage value of $60,000 and it will be depreciated over four years using the straight-line method. Management has also decided that $45,000 in inventories and $12,000 in accounts payable are needed if the...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost...
Data Mining is considering an expansion project. The company’s management has decided that the initial cost of the project is $300,000 with an additional installment cost of $80,000 and a $30,000 cost for research purposes related to the project. The project’s life is four years with a salvage value of $60,000 and it will be depreciated over four years using the straight-line method. Management has also decided that $45,000 in inventories and $12,000 in accounts payable are needed if the...
Fool Proof Software is considering an expansion project having life for four years. The proposed project...
Fool Proof Software is considering an expansion project having life for four years. The proposed project has the following features: • Initial cost of the equipment is $200,000, with shipping cost $10,000 and installation cost of $30,000. • The equipment will depreciate over 4 years using MACRS at the following rates (33%, 45%, 15%, and 7%) respectively. • Inventories will increase by $25,000, and accounts payable will rise by $5,000 • The company will sell 100,000 units per year with...
Fool Proof Software is considering an expansion project having life for four years. The proposed project...
Fool Proof Software is considering an expansion project having life for four years. The proposed project has the following features: • Initial cost of the equipment is $200,000, with shipping cost $10,000 and installation cost of $30,000. • The equipment will depreciate over 4 years using MACRS at the following rates (33%, 45%, 15%, and 7%) respectively. • Inventories will increase by $25,000, and accounts payable will rise by $5,000 • The company will sell 100,000 units per year with...
Manigault Industries is considering an expansion project. The proposed project would have a 4-year life along...
Manigault Industries is considering an expansion project. The proposed project would have a 4-year life along with the following features: • The necessary equipment is priced at $90,000. • The engineers require a cost of $3,000 to install the equipment and $5,000 to train employees to use the equipment • The equipment will be depreciated using MACRS 3 year class over 4 years using the following depreciation rates: 33% (year 1), 45% (year 2), 15% (year 3) and 7% (year...
Sovrano Café is considering a major expansion of its business. The details of the proposed expansion...
Sovrano Café is considering a major expansion of its business. The details of the proposed expansion project are summarized below: o The company will have to purchase $900,000 equipment, that require installation cost and transportation cost equal $100,000. o The sources of fund will be 250,000 loan from bank at interest 8% and the remaining will be from equity. o The company will pay interest equal to $120,000 each year. o The project has an economic life of 4 years....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT