Question

In: Finance

The following data are given for two mutually exclusive project proposals: (PhP) Project A Project B...

The following data are given for two mutually exclusive project proposals:

(PhP)

Project A Project B
Initial Investment 50,000.00 60,000.00
Annual Net Cash Inflows:
Year 1 15,000.00 30,000.00
Year 2 14,000.00 14,000.00
Year 3 12,000.00 10,000.00
Year 4 12,000.00 10,000.00
Year 5 12,000.00 10,000.00

Assuming that the firm’s required rate of return is 20%, compute the following:

a) Net Present Value

b) Payback Period

Which project would you undertake? Justify

Solutions

Expert Solution

a) NPV of project = Present Values of Cash Inflows - Initial Investment where the discount rate is 20 % (Given)

Therefore

Project A
Year 1 Year 2 Year 3 Year 4 Year 5
Cash Flows (A) 15000 14000 12000 12000 12000
Discount Factors (B) =1/(1.20)^1 =1/(1.20)^2 =1/(1.20)^3 =1/(1.20)^4 =1/(1.20)^5
Discount Factors (B) 0.83333333 0.69444444 0.5787037 0.48225309 0.40187757
Present Values (A x B)    12,500.00       9,722.22       6,944.44       5,787.04       4,822.53
Total of All the present Values of Cash Inflows (D)    39,776.23
Initial Investment ('E) 50000
NPV (D-E) -10,223.77
Project B
Year 1 Year 2 Year 3 Year 4 Year 5
Cash Flows (A) 30000 14000 10000 10000 10000
Discount Factors (B) =1/(1.20)^1 =1/(1.20)^2 =1/(1.20)^3 =1/(1.20)^4 =1/(1.20)^5
Discount Factors (B) 0.83333333 0.69444444 0.5787037 0.48225309 0.40187757
Present Values (A x B)    25,000.00       9,722.22       5,787.04       4,822.53       4,018.78
Total of All the present Values of Cash Inflows (D)    49,350.57
Initial Investment ('E) 60000
NPV (D-E) -10,649.43

NPV of both the projects is negative. Based on NPV none of the projects is viable at the discount rate ofn 20%. Therefore both the projects needs to be not accepted.

b) Payback Period

We need to first compute the Cumalative Cash Flows of the project

Project A
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Cash Flows (A) -50000 15000 14000 12000 12000 12000
Cumalative Cash Flows -50000 -35,000.00 -21,000.00     -9,000.00       3,000.00    15,000.00
1) last period number with a negative cumulative cash flow is Year 3
2) value without negative sign of cumulative net cash flow at the end of the period with a cumalative negative Cash Flow is 9000
3) Total cash inflow during the period following period with the last negative cumlative Cash flow is 12000
Payback Period = (1)+[(2)/(3)]
Payback Period =3+9000/12000
Payback Period 3.75 years
Project A
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
Cash Flows (A) -60000 30000 14000 10000 10000 10000
Cumalative Cash Flows -60000 -30,000.00 -16,000.00     -6,000.00       4,000.00    14,000.00
1) last period number with a negative cumulative cash flow is Year 3
2) value without negative sign of cumulative net cash flow at the end of the period with a cumalative negative Cash Flow is 6000
3) Total cash inflow during the period following period with the last negative cumlative Cash flow is 10000
Payback Period = (1)+[(2)/(3)]
Payback Period =3+6000/10000
Payback Period 3.6 Years

Considering only payback period as the criteria for selection of projects Project B having lesser payback period would be accepted. This means that the initial amount invested of the project would be received back in 3.6 years for project B.


Related Solutions

Given the following two mutually exclusive project, calculate the equivalent annual annuity for Project B. Assume...
Given the following two mutually exclusive project, calculate the equivalent annual annuity for Project B. Assume a required rate of return of 12%. (Round to 2 decimals) Year Project A Project B 0 -500 -600 1 320 300 2 320 300 3 320 300 4 300
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available...
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available to Simonsbosch Farm. They are producers of Rooi Bos tea. The initial cash outlay and cash flows are shown below and Simonsbosch will use straight line depreciation over each of the assets 4 year life and there will be no residual value on either investment. Years Cash Flows (A) Cash Flows (B) 0 (Investment) -240 000 -90 000 1 28 000 40 000 2...
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the internal rate of return of PROJECT A?
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0&
You are considering the following two mutually exclusive projects. YEAR             PROJECT (A)         PROJECT (B)        0                  -$35,000                  -$35,000     1                     22,000                     13,000     2                     20,000                     21,000     3                     13,000                     22,000 What is the crossover point?
Universal PLC is considering two mutually exclusive project proposals for new investment. The initial outlay of...
Universal PLC is considering two mutually exclusive project proposals for new investment. The initial outlay of both projects is £300,000 but will yield different levels of cash flows over the life of the project. The projects are estimated to last for five years. They will have no residual value at the end of their lives. Depreciation is charged on a straight-line basis. The company uses a 6% discount rate for the cost of capital. The cash flows of both projects...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000...
You are considering the following two mutually exclusive projects. Project A Project B Year 0 -$10,000 -$20,000 Year 1 $ 3,000 $ 5,000 Year 2 $ 8,000 $ 7,000 Year 3 $ 4,000 $12,000 Year 4 $ 2,000 $10,000 The required return on each project is 12 percent. Which project should you accept and what is the best reason for that decision? a. Project B; because it has the higher net present value b. Project A; because it pays back...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0...
Mutually exclusive investments. The following are cash flows of two projects. Year  Project A Project B 0 $ (200) $ (200) 1 80 100 2 80 100 3 80 100 4 80 Calculate the NPV for both projects if the discount rate is 11%(Do not intermediate calculations.Round your answer to 2 decimal places) Suppose that you can only choose one of the these projects. Which would you choose ? project A Project B Neither
1. McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost...
1. McKnight Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $543,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $74,600. Project B will cost $319,000, has an expected useful life of 12 years, a salvage value of zero, and is expected to increase net annual cash flows by $45,600. A discount rate of 7% is appropriate for both projects....
Beacon Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $480,826,...
Beacon Company is considering two different, mutually exclusive capital expenditure proposals. Project A will cost $480,826, has an expected useful life of 13 years, a salvage value of zero, and is expected to increase net annual cash flows by $71,600. Project B will cost $317,605, has an expected useful life of 13 years, a salvage value of zero, and is expected to increase net annual cash flows by $49,100. A discount rate of 9% is appropriate for both projects. (Refer...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT