Question

In: Finance

Country Farmlands, Inc. is considering the following potential projects for this coming year, but has only $200,000 for these projects:

Constraints on borrowing.  

Country Farmlands, Inc. is considering the following potential projects for this coming year, but has only $200,000 for these projects: Project A: Cost $60,000, NPV $4,000, and IRR 11% Project B: Cost $78,000, NPV $6,000, and IRR 12% Project C: Cost $38,000, NPV $3,000, and IRR 10% Project D: Cost $41,000, NPV $4,000, and IRR 9% Project E: Cost $56,000, NPV $6,000, and IRR 13% Project F: Cost $29,000, NPV $2,000, and IRR 7% What projects should Farmlands pick?

Solutions

Expert Solution

W X Y Z=X/W
Cost NPV IRR NPV/Cost
PROJECT A $60,000 $4,000 11% 0.066667
PROJECT B $78,000 $6,000 12% 0.076923
PROJECT C $38,000 $3,000 10% 0.078947
PROJECT D $41,000 $4,000 9% 0.097561
PROJECT E $56,000 $6,000 13% 0.107143
PROJECT F $29,000 $2,000 7% 0.068966
The Objective should be to maximize NPV
Select projects with maximum NPV/Cost
Arranging Projects in decending order of( NPV/Cost)
Cost NPV IRR NPV/Cost Cumulative Cost
PROJECT E $56,000 $6,000 13% 0.107143 $56,000
PROJECT D $41,000 $4,000 9% 0.097561 $97,000
PROJECT C $38,000 $3,000 10% 0.078947 $135,000
PROJECT B $78,000 $6,000 12% 0.076923 $213,000
PROJECT F $29,000 $2,000 7% 0.068966 $242,000
PROJECT A $60,000 $4,000 11% 0.066667 $302,000
Cost Cumulative Cost NPV Cumulative NPV IRR
PROJECT E $56,000 $56,000 $6,000 $6,000 13%
PROJECT D $41,000 $97,000 $4,000 $10,000 9%
PROJECT C $38,000 $135,000 $3,000 $13,000 10%
Funds available $200,000
Balanceavailable after allocating for Project E,D and C $65,000 (200000-135000)
Out of left out projects of B, F and A,the balance $65000 cannot be sufficient for Project B
NPV of Project F $2,000
NPV of Project A $4,000
Project A should be selected tomaximize NPV
List of Selected Projects are given below
Selected Projects Cost NPV IRR
PROJECT A $60,000 $4,000 11%
PROJECT C $38,000 $3,000 10%
PROJECT D $41,000 $4,000 9%
PROJECT E $56,000 $6,000 13%
TOTAL $195,000 $17,000

Related Solutions

Dentaltech Inc. projects the following data for the coming year. If the firm follows the residual...
Dentaltech Inc. projects the following data for the coming year. If the firm follows the residual dividend model and also maintains its target capital structure, what will its dividend payout ratio be? EBIT $2,600,000 Capital budget $1,325,000 Interest rate 10% % Debt 40% Debt outstanding $4,900,000 % Equity 60% Shares outstanding 5,000,000 Tax rate 25%
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 10.75% High B 5 million 13.25 High C 3 million 8.75 Low D 2 million 7.75 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 5.75 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 13.25% High B 5 million 10.75 High C 3 million 8.75 Low D 2 million 8.00 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 6.00 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.50 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.50 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.50% High B 5 million 15.00 High C 3 million 10.50 Low D 2 million 9.50 Average E 6 million 13.50 High F 5 million 13.50 Average G 6 million 7.50 Low H 3 million 12.00 Low Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.25% High B 5 million 13.75 High C 3 million 9.25 Low D 2 million 9 Average E 6 million 12.25 High F 5 million 12.25 Average G 6 million 7 Low H 3 million 11 Low Ziege's WACC is 9.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.50% High B 5 million 14.00 High C 3 million 9.50 Low D 2 million 9.25 Average E 6 million 12.50 High F 5 million 12.50 Average G 6 million 7.25 Low H 3 million 11.50 Low Ziege's WACC is 10.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.25% High B 5 million 14.75 High C 3 million 10.25 Low D 2 million 9.75 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.75 Low H 3 million 12.00 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 9.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 7.75 Low H 3 million 11.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 8.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 6.75 Low H 3 million 12.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT