In: Finance
Constraints on borrowing.
Country Farmlands, Inc. is considering the following potential projects for this coming year, but has only $200,000 for these projects: Project A: Cost $60,000, NPV $4,000, and IRR 11% Project B: Cost $78,000, NPV $6,000, and IRR 12% Project C: Cost $38,000, NPV $3,000, and IRR 10% Project D: Cost $41,000, NPV $4,000, and IRR 9% Project E: Cost $56,000, NPV $6,000, and IRR 13% Project F: Cost $29,000, NPV $2,000, and IRR 7% What projects should Farmlands pick?
W | X | Y | Z=X/W | |||||
Cost | NPV | IRR | NPV/Cost | |||||
PROJECT A | $60,000 | $4,000 | 11% | 0.066667 | ||||
PROJECT B | $78,000 | $6,000 | 12% | 0.076923 | ||||
PROJECT C | $38,000 | $3,000 | 10% | 0.078947 | ||||
PROJECT D | $41,000 | $4,000 | 9% | 0.097561 | ||||
PROJECT E | $56,000 | $6,000 | 13% | 0.107143 | ||||
PROJECT F | $29,000 | $2,000 | 7% | 0.068966 | ||||
The Objective should be to maximize NPV | ||||||||
Select projects with maximum NPV/Cost | ||||||||
Arranging Projects in decending order of( NPV/Cost) | ||||||||
Cost | NPV | IRR | NPV/Cost | Cumulative Cost | ||||
PROJECT E | $56,000 | $6,000 | 13% | 0.107143 | $56,000 | |||
PROJECT D | $41,000 | $4,000 | 9% | 0.097561 | $97,000 | |||
PROJECT C | $38,000 | $3,000 | 10% | 0.078947 | $135,000 | |||
PROJECT B | $78,000 | $6,000 | 12% | 0.076923 | $213,000 | |||
PROJECT F | $29,000 | $2,000 | 7% | 0.068966 | $242,000 | |||
PROJECT A | $60,000 | $4,000 | 11% | 0.066667 | $302,000 | |||
Cost | Cumulative Cost | NPV | Cumulative NPV | IRR | ||||
PROJECT E | $56,000 | $56,000 | $6,000 | $6,000 | 13% | |||
PROJECT D | $41,000 | $97,000 | $4,000 | $10,000 | 9% | |||
PROJECT C | $38,000 | $135,000 | $3,000 | $13,000 | 10% | |||
Funds available | $200,000 | |||||||
Balanceavailable after allocating for Project E,D and C | $65,000 | (200000-135000) | ||||||
Out of left out projects of B, F and A,the balance $65000 cannot be sufficient for Project B | ||||||||
NPV of Project F | $2,000 | |||||||
NPV of Project A | $4,000 | |||||||
Project A should be selected tomaximize NPV | ||||||||
List of Selected Projects are given below | ||||||||
Selected Projects | Cost | NPV | IRR | |||||
PROJECT A | $60,000 | $4,000 | 11% | |||||
PROJECT C | $38,000 | $3,000 | 10% | |||||
PROJECT D | $41,000 | $4,000 | 9% | |||||
PROJECT E | $56,000 | $6,000 | 13% | |||||
TOTAL | $195,000 | $17,000 | ||||||