In: Operations Management
Implementing projects without a strong priority system linked to strategy creates problems, the implementation gap refers to the lack of understanding and consensus of organization strategy among top and middle-level managers.
Select one:
True
False
======================================
Which of the following is not one of the technical dimensions of
project management?
Select one:
a. D) WBS
b. A) Teamwork
c. E) Scope of work
d. C) Resources allocation
e. ? Schedules
======================================
good statement of work gives bidders a better understanding of the
buyer’s expectations.
Select one:
True
False
======================================
Request for Quotes is a document prepared by a seller when there
are different approaches for meeting buyer needs.
Select one:
True
False
======================================
Question 01: True
Explanation: Implementing the projects without a strong priority system linked to strategy causes various problems like implementation Gap, organization politics, resource conflicts, etc., Implementation gap refers to the issues in executing the strategy that is planned because of the lack of understanding among top and middle-level managers.
Question 02: Teamwork
Explanation: Technical dimension exhibits the science of the project management which includes scope, WBS, schedules, baseline budgets, etc., Teamwork belongs to the sociocultural dimension which also includes leadership, problem solving, customer expectations, etc.,
Question 03: True
Explanation: The statement of work should be clear, concise and complete as much as possible in such a way that the services required, performance reporting requirements, etc., are easily understood.
Question 04: False