In: Accounting
Assume a company produces and sells only two products—14,000
units of Product A and 6,000 units of Product B. The selling prices
are $65 per unit for Product A and $96 per unit for Product B.
Product A’s direct materials and direct labor costs per unit are
$30 and $12, respectively. Product B’s direct materials and direct
labor costs per unit are $34 and $15, respectively. The company
uses a plantwide overhead rate based on direct labor dollars. It is
considering implementing an activity-based costing (ABC) system
that allocates all of its manufacturing overhead to three cost
pools. The following additional information is available for the
company as a whole and for Products A and B:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | |||
Machining | Machine-hours | $ | 300,000 | 15,000 | MH | |
Machine setups | Number of setups | $ | 150,000 | 200 | Setups | |
Product design | Number of products | $ | 80,000 | 2 | Products | |
Activity Measure | Product A | Product B |
Machine-hours | 9,000 | 6,000 |
Number of setups | 50 | 150 |
Number of products | 1 | 1 |
When comparing Product B’s total overhead costs using the
traditional approach with its total overhead costs using the
activity-based approach, which of the following statements is
true?
Multiple Choice
The traditional plantwide approach overcosts Product B by between $50,000 and $100,000 when compared to the activity-based approach.
The traditional plantwide approach undercosts Product B by between $50,00 and $100,000 when compared to the activity-based approach.
The traditional plantwide approach undercosts Product B by between $0 and $49,999 when compared to the activity-based approach.
The traditional plantwide approach overcosts Product B by between $0 and $49,999 when compared to the activity-based approach.
The traditional plantwide approach undercosts Product B by between $50,000 and $100,000 when compared to the activity-based approach. |
Option B is correct |
Workings: | ||
Traditional plantwide: | ||
Direct labor costs: | ||
Product A | 168000 | =14000*12 |
Product B | 90000 | =6000*15 |
Direct labor costs | 258000 | |
Estimated Overhead Cost | 530000 | =300000+150000+80000 |
/ Direct labor costs | 258000 | |
Plantwide overhead rate | 205.43% | |
Overhead allocated: | ||
Product B | 184887 | =90000*205.43% |
Activity-based approach: | ||
Activity rates: | ||
Machining | 20 | =300000/15000 |
Machine setups | 750 | =150000/200 |
Product design | 40000 | =80000/2 |
Overhead allocated: | ||
Product B | ||
Machining | 120000 | =6000*20 |
Machine setups | 112500 | =150*750 |
Product design | 40000 | |
Overhead allocated product B | 272500 | |
Traditional plantwide approach undercosts | 87613 | =272500-184887 |