In: Accounting
Assume a company produces and sells only two products—14,000
units of Product A and 6,000 units of Product B. The selling prices
are $65 per unit for Product A and $96 per unit for Product B.
Product A’s direct materials and direct labor costs per unit are
$30 and $12, respectively. Product B’s direct materials and direct
labor costs per unit are $34 and $15, respectively. The company
uses a plantwide overhead rate based on direct labor dollars. It is
considering implementing an activity-based costing (ABC) system
that allocates all of its manufacturing overhead to three cost
pools. The following additional information is available for the
company as a whole and for Products A and B:
Activity Cost Pool | Activity Measure | Estimated Overhead Cost | Expected Activity | |||
Machining | Machine-hours | $ | 300,000 | 15,000 | MH | |
Machine setups | Number of setups | $ | 150,000 | 200 | Setups | |
Product design | Number of products | $ | 80,000 | 2 | Products | |
Activity Measure | Product A | Product B |
Machine-hours | 9,000 | 6,000 |
Number of setups | 50 | 150 |
Number of products | 1 | 1 |
When comparing Product A’s total overhead costs using the traditional approach with its total overhead costs using the activity-based approach, which of the following statements is true?
Multiple Choice
The traditional plantwide approach undercosts Product A by between $0 and $49,999 when compared to the activity-based approach.
The traditional plantwide approach undercosts Product A by between $50,000 and $100,000 when compared to the activity-based approach.
The traditional plantwide approach overcosts Product A by between $50,000 and $100,000 when compared to the activity-based approach.
The traditional plantwide approach overcosts Product A by between $0 and $49,999 when compared to the activity-based approach.
product | Total production | direct labour per unit | total direct labour cost |
A | 14,000 | $ 12 | 14,000 * 12=168,000 |
B | 6,000 | $ 15 | 6,000 * 15= 90,000 |
TOTAL= 258,000 |
in traditional approach overhead is allocated based on the direct labour dollars.
total overhead cost= machining cost + machine setup+ product design
=300,000+150,000+80,000=530,000
overhead allocation rate= total overhead / total direct labour dollars
=530,000/258,000 =2.05426
Total overhead cost of product A using tradtional approach = overhead allocation rate * total labour cost of product A
=168,000 * 2.05426 = 345,115.68
ACTIVITY BASED APPROACH
total overhead classified in to three, each will allocate in to products based on the cost driver.an allocation rate will find for all cost pools and it will allocate based on the activity used by the products
Cost pool | Cost | Activity | Allocation rate |
Machining | 300,000 | 15,000 MH | 300,000/ 15000= 20 per MH |
machine setup | 150,000 | 200 setup | 150,000/200= 750 per set up |
Product design | 80,000 | 2 products | 80,000/2= 40,000 per product |
Machining cost is allocate @ 20 per machine hour
total machine hours used by product A= 9,000
Machining cost allocated to Product A= 9,000 * 20 = 180,000
machine set up cost is 750 per set up
Total machine setup for Product A = 50
Machine set up cost allocated to product A= 750* 50= 37,500
product design cost is 40,000 per product
product design cost for product A =1 * 40,000= 40,000
TOTAL OVERHEAD COST OF PRODUCT A BY ACTIVITY BASED APPROACH= 180,000+37,500+40,000=257,500
Overhead cost Based on Traditional approach is 345,115.68. but in Activity based approach it is 257,500
345,115.68-257,500= 87,615.68
so option C is correct
The traditional plantwide approach overcosts Product A by between $50,000 and $100,000 when compared to the activity-based approach.