Below is the estimated time it should take (in hours) for each of the different types of buildings they work on.
Building |
Excavating |
Framing |
Electrical |
Plumbing |
Finishing |
Office Space |
45 |
100 |
88 |
132 |
312 |
School |
56 |
250 |
147 |
28 |
290 |
Apartments |
84 |
480 |
75 |
125 |
244 |
Grocery Store |
95 |
160 |
26 |
78 |
236 |
Below are the hourly rates for some different construction companies in the area.
Company |
Bouma |
Pinnacle |
Rockford |
McGraw |
Excavating |
$350 |
$300 |
$285 |
$245 |
Framing |
$225 |
$275 |
$280 |
$280 |
Electrical |
$405 |
$375 |
$295 |
$350 |
Plumbing |
$150 |
$240 |
$225 |
$200 |
Finishing |
$250 |
$190 |
$230 |
$215 |
Answer 1
By using the matrix multiplication, we get that
After the calculations we get the values as mentioned below:
Now, we get that
COST | BOUMA | PINNACLE | ROCKFORD | MCGRAW |
OFFICE SPACE | 171690 | 164960 | 168245 | 163305 |
SCHOOL | 212085 | 202495 | 202325 | 203120 |
APARTMENT | 247525 | 261685 | 264710 | 258690 |
GROCERY STORE | 150480 | 145810 | 151375 | 143515 |
TOTAL COST |
781,780 | 774,950 | 786,655 | 768,630 |
MCGRAW is the company can complete each project at the lowest cost.(768,630)
Answer 2
Lets Highlight the cells that give the lowest cost for each building project:
COST $ | BOUMA | PINNACLE | ROCKFORD | MCGRAW |
OFFICE SPACE | 171690 | 164960 | 168245 | 163305 |
SCHOOL | 212085 | 202495 | 202325 | 203120 |
APARTMENT | 247525 | 261685 | 264710 | 258690 |
GROCERY STORE | 150480 | 145810 | 151375 | 143515 |
Answer 3
The below table shows which company should be hired for each project.
HIRED FOR PROJECT | COMPANY NAME | COST IN $ |
OFFICE SPACE | MCGRAW | 163305 |
SCHOOL | ROCKFORD | 202325 |
APARTMENT | BOUMA | 247525 |
GROCERY STORE | MCGRAW | 143515 |