Question

In: Operations Management

The ________ is a document which describes how the project management team will implement the performing...

The ________ is a document which describes how the project management team will implement the performing organization's quality policy.

Group of answer choices

Quality management plan

Quality assurance plan

Quality audit

Quality commitment

Solutions

Expert Solution

Answer: Option A - Quality management plan

Explanation: The Quality management plan is the document which helps the project manager to execute the quality management activities for the project. It describes how the PM team will implement the quality policy of the organization.


Related Solutions

The CMMI-ACQ document stresses (page 77) the importance of the project management team being acutely aware...
The CMMI-ACQ document stresses (page 77) the importance of the project management team being acutely aware of the legal implications of actions taken. This pertains to the project managers (regardless of titles) of both parties, the buyer and the contractor. Yet it is common for the contractor to constantly have to say no to requests from stakeholders that go beyond the contract and the contractor’s legal obligations. This can result in the contractor getting a bad reputation among the stakeholders...
summarize the importance of project management team and how they impact a project. 1 page please.
summarize the importance of project management team and how they impact a project. 1 page please.
Which of the following describes a document sent to verify an organization’s identity to the CA?
Which of the following describes a document sent to verify an organization’s identity to the CA?Digital trust application formPKI escrow formTrusted Site Application formCertificate-signing request
If you were to implement a research project to answer your clinical or management question: How...
If you were to implement a research project to answer your clinical or management question: How will you ensure that ethical principles are fostered? What statistical analyses would you incorporate?
A document that describes policies to control how computer resources are used is an example of:
A document that describes policies to control how computer resources are used is an example of:
The project scope defines and describes what needs to be done during the course of the project. Identify and describe the contents and sections of a project scope document.
The project scope defines and describes what needs to be done during the course of the project. Identify and describe the contents and sections of a project scope document.  
This process is for Senior Management and shows how the Senior Management controls the project. Which...
This process is for Senior Management and shows how the Senior Management controls the project. Which process am I referring to? This is a very short pre-project process that gathers the necessary data to start the project. Which process am I referring to?
If you were the Human Resources manager and wanted to convince the CEO/management team to implement...
If you were the Human Resources manager and wanted to convince the CEO/management team to implement a flextime policy (e.g., can work any 8 hours between 6 am and 6 pm) to assist employees with children (elderly parents, others) to care for, what would you say/do? You should present your post from the viewpoint of your role as the HR manager, a senior and experienced leader, to the CEO and his/her management team. It should be a comprehensive discussion or...
The project management plan is the most important planning document produced with inputs from several project...
The project management plan is the most important planning document produced with inputs from several project team members. In which of the following processes will the project management plan NOT be updated? Monitor and Control Project Work Develop Project Charter Perform Integrated Change Control Direct and Manage Project Work There are three projects: Project A has a payback period of 3 years and NPV of $ 300,000. Project B has a payback period of 2 years and NPV of $...
Jamil Hassan heads a newly formed project management team for a major international corporation. The team...
Jamil Hassan heads a newly formed project management team for a major international corporation. The team is composed of 20 professionals who live and work in Oman, Saudi Arabia, United Kingdom, Australia, Kuwait & Africa. All members of the team report to Jamil. The team is a virtual team now since March of this year due to the COVID-19 pandemic and all are connected primarily via videoconference, group-decision support software, email and telephone. The team has met twice in a...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT