Question

In: Accounting

XYZ Company has bagged a fixed cost contract for the supply, installation, testing and commissioning of...

XYZ Company has bagged a fixed cost contract for the supply, installation, testing and commissioning of 200 computers of same specification at a cost of INR 600 lakhs. The company had estimated that it could supply, install, test and commission 10 computers per day so that the entire work would be completed in 20 days time. The project status was reviewed after the completion of 16 days. It was needed at the time of review that only 120 computers have been installed and the cost incurred was INR 380 lakhs. It was estimated at the time of the review that a sum of INR 260 lakhs would be required for completing the pending works of the remaining 80 computers. Make a performance analysis by arriving at the various connected parameters.

Solutions

Expert Solution

Total no of computer to be supplied under contract= 200

Conputer estimated to be supply per day = 10

Accordingly estimated supply of computer in 16 days= 16*10= 160

Actually Supplied in 16 days = 120

Now,

Total cost to be incurred in supplying 200 computers = INR 600 lakhs

Cost per computer would be = 600/200 = INR 3 Lakhs

Estimated cost of 120 computers installed till 16 day= 120*3lakhs= INR 360 Lakhs

Actaul Cost incurred in installing 120 computers = INR 380 Lakhs(Given)

Loss incurred till installation of 120 computers= 20 lakhs( 380-360)

Estimated cost of remaining 80 computers = 260 Lakhs(Given)

Total Estimated cost= 380+260= INR 640 Lakhs

Total Estimated Loss at the end of installation of 200 computers = 640 lakhs- 500 lakhs= INR 140 lakhs

Result:- As seen from the above working that the company has already incurred a loss of INR 20 Lakhs & expected to incurred a total estimated loss of INR 140 lakhs by the end of installation of 200 computers. So company should book a loss of INR 20 lakhs immediately & should make a provision for the remaining amount of estimate loss of INR 120 lakhs


Related Solutions

You and your team are awarded a 1 year contract to supply/deliver, construct, test and commissioning...
You and your team are awarded a 1 year contract to supply/deliver, construct, test and commissioning of a 20 units 2-storey shophouse near your hometown. Construct a financial plan to illustrate your preparation of material and manpower delivery plan comprehensively. Assuming the total budget will be $20,000,000
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has...
There are 2 basic types of contracts: the fixed-price contract and the cost-plus contract. Each has several common variations. It is not unusual for any specific contract to have special terms and agreements, so the basic contract is just the starting point. The project manager is most interested in the terms that define and help to control costs, schedule, and quality. Among the different types of contracts, which contracts do you think would be easiest for ADC to manage, and...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
A large wood products company is negotiating a contract to sell plywood overseas. The fixed cost...
A large wood products company is negotiating a contract to sell plywood overseas. The fixed cost that can be allocated to the production of plywood is $900,000 per month. The variable cost per thousand board feet is $131.50. The price charged will be determined by p = $600 – (0.05)D per 1,000 board feet. For this situation, (a) determine the optimal monthly sales volume for this product and calculate the profit (or loss) at the optimal volume. (b) What is...
1) ABC Company has mostly fixed costs and XYZ Company has mostly variable costs. Which company...
1) ABC Company has mostly fixed costs and XYZ Company has mostly variable costs. Which company has the greatest risk of a net loss? Why? 2) Briefly explain the concept of sensitivity analysis.
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ...
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ will pay $50 million when the contract is signed, another $360 million at the end of the first year, and the $50 million balance at the end of second year. The expected cash outflows required to produce the product are estimated to be $150 million now, $95 million the first year, and $218 million the second year. The firm’s MARR is 27% for this...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity for both contracts but is uncertain whether they will be profitable. Data as follows: Customer                                  AAA                BBB Component Type                         A999                B999 Contract Value($)                       $27,000            $100,000 Contract Quantity                      1,000 unit          2,000 units Material cost/unit                        $15                  $20 Molding time/batch                     5 hours            7.5 hours          Batch Size                                 100 units          50 units Annual Budgeted overheads as follows: Activity                                    Cost Driver                 Cost driver       Cost                       volume/year   pool Molding                                    Molding hours                2,000                $150,000 Inspection                                 Batches                        150                  $75,000 Production Mgmt                       Contracts                      20                    $125,000    Calculate the activity-based costs and profits for each contract. Company XYZ has two fixed price contracts...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity for both contracts but is uncertain whether they will be profitable. Data as follows: Customer                                  AAA                BBB Component Type                         A999                B999 Contract Value($)                       $27,000            $100,000 Contract Quantity                      1,000 unit          2,000 units Material cost/unit                        $15                  $20 Molding time/batch                     5 hours            7.5 hours          Batch Size                                 100 units          50 units Annual Budgeted overheads as follows: Activity                                    Cost Driver                 Cost driver       Cost                       volume/year   pool Molding                                    Molding hours                2,000                $150,000 Inspection                                 Batches                        150                  $75,000 Production Mgmt                       Contracts                      20                    $125,000    Calculate the activity-based costs and profits for each contract.
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity for both contracts but is uncertain whether they will be profitable. Data as follows: Customer AAA BBB Component Type A999 B999 Contract Value($) $27,000 $100,000 Contract Quantity 1,000 unit 2,000 units Material cost/unit $15 $20 Molding time/batch 5 hours 7.5 hours    Batch Size 100 units 50 units Annual Budgeted overheads as follows: Activity Cost Driver Cost driver Cost volume/year pool Molding Molding hours...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity...
Company XYZ has two fixed price contracts for two different clients. The company has enough capacity for both contracts but is uncertain whether they will be profitable. Data as follows: Customer                                  AAA                BBB Component Type                         A999                B999 Contract Value($)                       $27,000            $100,000 Contract Quantity                      1,000 unit          2,000 units Material cost/unit                        $15                  $20 Molding time/batch                     5 hours            7.5 hours          Batch Size                                 100 units          50 units Annual Budgeted overheads as follows: Activity                                    Cost Driver                 Cost driver       Cost                       volume/year   pool Molding                                    Molding hours                2,000                $150,000 Inspection                                 Batches                        150                  $75,000 Production Mgmt                       Contracts                      20                    $125,000    Calculate the activity-based costs and profits for each contract.   
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT