Question

In: Accounting

The accountant of ABC Company has the following maintenance costs and working hours for the past...

The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components:

Month

Cost

Working hours

March

$100,000

5,000

April

60,000

1,000

May

68,600

2,000

June

83,450

3,420

July

88,000

5,250

The equation to predict the maintenance cost is

[[selectone]]

a. Y=38,000+16X

b. Y=40,000+10X

c. Y=50,000+10X

d. Y=40,000+12X

Solutions

Expert Solution

Answer is Option C i.e. Y=50,000 + 10X

Here X is the working hours. Here if we analyse the given options for predicting the maintenance cost, the Option C is giving the consistent answer for the month of March and April. Further for the month of May, une and July it is giving answer with less variance than that of other options upon comparison of the given data.

Kindly consider the following for better understanding;

Option a : 38000 + 16X

38000+16X Total Cost Variance
38000      80,000    118,000 (18,000)
38000      16,000       54,000       6,000
38000      32,000       70,000     (1,400)
38000      54,720       92,720     (9,270)
38000      84,000    122,000 (34,000)

Option b : 40000+10X  

40000+10X Total Cost Variance
       40,000        50,000        90,000        10,000
       40,000        10,000        50,000        10,000
       40,000        20,000        60,000           8,600
       40,000        34,200        74,200           9,250
       40,000        52,500        92,500         (4,500)

Option c : 50000+10X

50000+10X Total Cost Variance
       50,000        50,000        100,000                  -  
       50,000        10,000           60,000                  -  
       50,000        20,000           70,000          (1,400)
       50,000        34,200           84,200              (750)
       50,000        52,500        102,500        (14,500)

Option d : 40000+12X

40000+12X Total Cost Variance
       40,000        60,000        100,000                  -  
       40,000        12,000           52,000            8,000
       40,000        24,000           64,000            4,600
       40,000        41,040           81,040            2,410
       40,000        63,000        103,000        (15,000)

Variance = Total Cost - Actual Cost given in the question.


Related Solutions

SHOW ALL WORK!!                 Machine hours and electricity costs for ABC Industries for the past eleven...
SHOW ALL WORK!!                 Machine hours and electricity costs for ABC Industries for the past eleven months were as follows: Month Electricity Costs Machine Hours January $12,600                 2,000 February              14,000 2,400 March   9,310   1,400 April       15,200 2,600 May       19,000 2,300 June      15,500 3,300 July        17,000 3,600 August 15,500 3,000 September         10,700 1,500 October               17,700 3,300 November          21,000 4,200 Required: a.            Using the high-low method, develop an estimate of variable electricity costs per machine hour. (Round to the nearest penny) b.           ...
Markowis Corp. has collected the following data concerning its maintenance costs for the past 6 months....
Markowis Corp. has collected the following data concerning its maintenance costs for the past 6 months. Units Produced Total Cost July 18,054 $36,108 August 32,096 48,144 September 36,108 55,165 October 22,066 38,114 November 40,120 74,724 December 38,114 62,186 Collapse question part (a1) Incorrect answer. Your answer is incorrect. Try again. Compute the variable cost per unit using the high-low method. (Round variable cost per mile to 2 decimal places e.g. 1.25.) Variable cost per unit $Entry field with incorrect answer...
For the past 5 years, Shirin Nadia has been working as a Management Accountant at Meridian...
For the past 5 years, Shirin Nadia has been working as a Management Accountant at Meridian Energy – a leading power company based in New Zealand. However, she has recently seen a job advertisement for a Senior Management Accountant at Auckland Museum. Shirin applied for the position and subsequently progressed towards the final interview stage. While she was going through the final interview process, an interview panel member asked her how the performance report of Auckland Museum would be different...
Prior to installing a JIT system, Clarendon Company used machine hours to assign maintenance costs to...
Prior to installing a JIT system, Clarendon Company used machine hours to assign maintenance costs to its three products of 6-inch, 8-inch, and 11-inch insulation. The maintenance costs totaled $400,000 per year. The machine hours used by each product and the quantity produced of each product are as follows: Machine Hours Quantity Produced 6-inch 12,000 31,250 rolls 8-inch 20,000 25,000 rolls 11-inch 18,000 12,000 rolls After installing JIT, three manufacturing cells were created and the cell workers were trained to...
ABC company incurred the following maintainance costs during the past 6 months Table 1 Months Machine...
ABC company incurred the following maintainance costs during the past 6 months Table 1 Months Machine hours Cost $ 1 20 4560 2 40 9780 3 50 10920 4 60 11280 5 30 6320 6 90 18920 7 25 5140 8 43 10500 9 70 12400 REQUIRED Part 1 A. Use the data on Table 1 , estimate the variable and fixed cost of the company using the high and low method B. Develop a cost function for the company....
The maintenance department's costs are allocated to other departments based on the number of hours of...
The maintenance department's costs are allocated to other departments based on the number of hours of maintenance use by each department. The maintenance department has fixed costs of $500,000 and variable costs of $30 per hour of maintenance provided. The variable costs include the salaries of the maintenance workers. More maintenance workers can be added if greater maintenance is demanded by the other departments without affecting the fixed costs of the maintenance department. The maintenance department expects to provide 10,000...
The Grey Manufacturing Company has two service departments: Maintenance and Accounting. The Maintenance Department's costs of...
The Grey Manufacturing Company has two service departments: Maintenance and Accounting. The Maintenance Department's costs of $300,000 are allocated on the basis of machine hours. The Accounting Department's costs of $120,000 are allocated on the basis of the number of employees within a specific department. The direct departmental costs for A and B are $300,000 and $500,000, respectively. Maintenance Accounting A B Machine hours 480 20 2,300 200 Number of employees 2 2 8 4 What are the total service...
A. The Grey Manufacturing Company has two service departments: Maintenance and Accounting. The Maintenance Department's costs...
A. The Grey Manufacturing Company has two service departments: Maintenance and Accounting. The Maintenance Department's costs of $300,000 are allocated on the basis of machine hours. The Accounting Department's costs of $120,000 are allocated on the basis of the number of employees within a specific department. The direct departmental costs for A and B are $300,000 and $500,000, respectively. Maintenance Accounting A B Machine hours 480 20 2,300 200 Number of employees 2 2 8 4 What are the total...
Deidoro Company has provided the following data for maintenance cost: Prior Year Current Year Machine hours...
Deidoro Company has provided the following data for maintenance cost: Prior Year Current Year Machine hours 22,000 24,500 Maintenance cost $ 31,400 $ 34,900 Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to: Multiple Choice $34,300 per year; $.714 per machine hour $600 per year; $.714 per machine hour $600 per year; $1.400 per machine hour $31,400 per year; $1.400 per machine hour . Derst Inc. sells...
For the past 8 months: Machine-Hours Maintenance Cost This is all the given info!! March 4,440...
For the past 8 months: Machine-Hours Maintenance Cost This is all the given info!! March 4,440 $50,950 April 4,431 $50,877 May 4,412 $50,696 June 4,460 $51,113 July 4,414 $50,711 August 4,433 $50,900 September 4,443 $50,976 October 4,415 $50,730 November 4,391 $50,530 Management believes that maintenance cost is a mixed cost that depends on machine-hours Using the high-low method, calculate (a) Variable cost per machine-hour (b) Fixed cost per month (c) What would total costs be for a month with 4,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT