In: Accounting
The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components:
Month |
Cost |
Working hours |
March |
$100,000 |
5,000 |
April |
60,000 |
1,000 |
May |
68,600 |
2,000 |
June |
83,450 |
3,420 |
July |
88,000 |
5,250 |
The equation to predict the maintenance cost is
[[selectone]]
a. Y=38,000+16X
b. Y=40,000+10X
c. Y=50,000+10X
d. Y=40,000+12X
Answer is Option C i.e. Y=50,000 + 10X
Here X is the working hours. Here if we analyse the given options for predicting the maintenance cost, the Option C is giving the consistent answer for the month of March and April. Further for the month of May, une and July it is giving answer with less variance than that of other options upon comparison of the given data.
Kindly consider the following for better understanding;
Option a : 38000 + 16X
38000+16X | Total Cost | Variance | |
38000 | 80,000 | 118,000 | (18,000) |
38000 | 16,000 | 54,000 | 6,000 |
38000 | 32,000 | 70,000 | (1,400) |
38000 | 54,720 | 92,720 | (9,270) |
38000 | 84,000 | 122,000 | (34,000) |
Option b : 40000+10X
40000+10X | Total Cost | Variance | |
40,000 | 50,000 | 90,000 | 10,000 |
40,000 | 10,000 | 50,000 | 10,000 |
40,000 | 20,000 | 60,000 | 8,600 |
40,000 | 34,200 | 74,200 | 9,250 |
40,000 | 52,500 | 92,500 | (4,500) |
Option c : 50000+10X
50000+10X | Total Cost | Variance | |
50,000 | 50,000 | 100,000 | - |
50,000 | 10,000 | 60,000 | - |
50,000 | 20,000 | 70,000 | (1,400) |
50,000 | 34,200 | 84,200 | (750) |
50,000 | 52,500 | 102,500 | (14,500) |
Option d : 40000+12X
40000+12X | Total Cost | Variance | |
40,000 | 60,000 | 100,000 | - |
40,000 | 12,000 | 52,000 | 8,000 |
40,000 | 24,000 | 64,000 | 4,600 |
40,000 | 41,040 | 81,040 | 2,410 |
40,000 | 63,000 | 103,000 | (15,000) |
Variance = Total Cost - Actual Cost given in the question.