Question

In: Accounting

Prior to installing a JIT system, Clarendon Company used machine hours to assign maintenance costs to...

Prior to installing a JIT system, Clarendon Company used machine hours to assign maintenance costs to its three products of 6-inch, 8-inch, and 11-inch insulation. The maintenance costs totaled $400,000 per year. The machine hours used by each product and the quantity produced of each product are as follows:

Machine Hours Quantity Produced
6-inch 12,000 31,250 rolls
8-inch 20,000 25,000 rolls
11-inch 18,000 12,000 rolls


After installing JIT, three manufacturing cells were created and the cell workers were trained to perform maintenance. Maintenance costs for the three cells still totaled $400,000; however, these costs are now traceable to each cell.

Cell, 6-inch $100,000
Cell, 8-inch 120,000
Cell, 11-inch 180,000


The maintenance cost per roll of 8-inch insulation before JIT is installed would be

a.$20.00.

b.$16.00.

c.$9.33.

d.$6.40.

Blue Vibrance Company sells a product used in many manufacturing processes. The sales activity involves three activity areas:

Activity Area Cost Driver and Rate
Order taking $100 per purchase order
Sales visits $50 per visit
Delivery vehicles $1 per delivery mile


The following customer information is given:

AX BY DZ
Units sold 100,000 80,000 60,000
List price $50 $50 $50
Actual sales price $45 $48 $50
Number of purchase orders 30 20 10
Number of sales visits 6 5 3
Number of delivery miles 100 80 60


What is the profitability of customer BY?

a.$3,840,000

b.$4,000,000

c.$3,837,670

d.$2,330,000

Solutions

Expert Solution

  • All working forms part of the answer
  • Question 1

Working

Machine hours

A

6 inch

                    12,000

B

8 inch

                    20,000

C

11 inch

                    18,000

D= A+B+C

Total machine hours

                    50,000

A

Maintenance Costs

$        400,000.00

B

Total Machine hours

                    50,000

C= A/B

Maintenance cost per machine hour

$                     8.00

D

No. of machine hours for 8 inch

                    20,000

E =C x D

Total Cost allocated to 8 inch

$        160,000.00

F

Total Quantity of 8 inch

                    25,000

G = E/F

Maintenance cost per unit

$                     6.40 = Answer

Correct Answer = Option ‘D’ $ 6.40

  • Question 2

Customer BY

per unit cost

Amount

Sales Revenue

                    80,000

$                  48.00

$ 3,840,000.00

Costs:

Order taking

                          100

$                  20.00

$           2,000.00

Sales Visits

                            50

$                     5.00

$              250.00

Delivery Vehicles

                               1

$                  80.00

$                 80.00

Profitability

$ 3,837,670.00

Correct Answer = Option ‘C’ $ 3,837,670


Related Solutions

JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer...
JIT Features and Product Costing Accuracy Prior to installing a JIT system, Barker Company, a producer of automobile parts, used maintenance hours to assign maintenance costs to its three products (wheels, brake pads, and ball bearings). The maintenance costs totaled $5,414,640 per year. The maintenance hours used by each product and the quantity of each product produced are as follows: Maintenance Hours Quantity Produced Wheels 180,000 157,500 Pads 180,000 157,500 Bearings 226,000 197,750 After installing JIT, three manufacturing cells were...
Deidoro Company has provided the following data for maintenance cost: Prior Year Current Year Machine hours...
Deidoro Company has provided the following data for maintenance cost: Prior Year Current Year Machine hours 22,000 24,500 Maintenance cost $ 31,400 $ 34,900 Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to: Multiple Choice $34,300 per year; $.714 per machine hour $600 per year; $.714 per machine hour $600 per year; $1.400 per machine hour $31,400 per year; $1.400 per machine hour . Derst Inc. sells...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $300,000 for the year, and machine usage is estimated at 125,000 hours. For the year, $322,000 of overhead costs are incurred and 130,000 hours are used. Collapse question part (a) Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $ per machine hour
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikea Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $456,789 4 for the year, and machine usage is estimated at 126,000 hours For the year, $432450 of overhead costs are incurred and 125,500 hours are used. What is the predetermined overhead rate What is the amount of overhead applied Has it been over or underapplied? Prepare the adjusting entry to adjust the cost of goods sold
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs...
Ikerd Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are estimated to total $283,725 for the year, and machine usage is estimated at 126,100 hours. For the year, $303,850 of overhead costs are incurred and 130,200 hours are used. Compute the manufacturing overhead rate for the year. (Round answer to 2 decimal places, e.g. 1.25.) Manufacturing overhead rate $ per machine hour What is the amount of under- or overapplied overhead at December...
The accountant of ABC Company has the following maintenance costs and working hours for the past...
The accountant of ABC Company has the following maintenance costs and working hours for the past five months and trying to separate the cost to its components: Month Cost Working hours March $100,000 5,000 April 60,000 1,000 May 68,600 2,000 June 83,450 3,420 July 88,000 5,250 The equation to predict the maintenance cost is [[selectone]] a. Y=38,000+16X b. Y=40,000+10X c. Y=50,000+10X d. Y=40,000+12X
Mosaic Company applies overhead using machine hours and reports the following information. Actual machine hours used...
Mosaic Company applies overhead using machine hours and reports the following information. Actual machine hours used (AH) 4,900 hours Standard machine hours (for actual production) (SH) 5,400 hours Actual variable overhead rate per hour (AVR) $ 4.55 Standard variable overhead rate per hour (SVR) $ 4.40 QS 23-18A Total variable overhead cost variance LO P5 Compute the total variable overhead cost variance and classify it as favorable, unfavorable or no variance. Compute the variable overhead spending variance and the variable...
Machine X costs $248,751 and has annual operating and maintenance costs of $9,980. Machine Y costs...
Machine X costs $248,751 and has annual operating and maintenance costs of $9,980. Machine Y costs $264,500 and has annual operating and maintenance cost of $5,120. Both machines are Class 39, which specifies a CCA rate of 25%. The company needs the machines for 11 years, and at the end of year 11 machine X can be sold for $12,257 and machine Y can be sold for 13,033. The Company's MARR is 10%, and its marginal tax rate is 35%....
Month # Machine Hours (X) Maintenance Costs (Y) Jan 3,000 $440 Feb 4,500 $690 Mar 8,000...
Month # Machine Hours (X) Maintenance Costs (Y) Jan 3,000 $440 Feb 4,500 $690 Mar 8,000 $510 Apr 7,000 $600 May 6,000 $550 Jun 9,000 $980 Jul 3,500 $840 Aug 5,500 $600 What does the slope represent? the rate at which the X variable changes as a result of the Y variable the rate at which the Y variable changes as a result of the X variable the rate at which the dependent variable changes as a result of the...
Month Machine Hours (hrs.) Maintenance Costs ($) 1 1,330 102,694 2 1,400 103,694 3 1,500 108,694...
Month Machine Hours (hrs.) Maintenance Costs ($) 1 1,330 102,694 2 1,400 103,694 3 1,500 108,694 4 1,470 108,694 5 1,620 116,694 6 1,690 115,694 7 1,490 107,694 8 1,310 102,694 9 1,450 106,694 10 1,580 113,694 11 1,300 100,694 12 1,600 113,694 13 1,650 114,694 14 1,440 109,694 15 1,340 102,694 16 1,670 114,694 17 1,480 106,694 18 1,360 103,694 19 1,340 103,694 20 1,540 112,694 Assume that the following relationship holds: Maintenance Costs = (v * Machine Hours)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT