Question

In: Finance

I will rate, thank you. Part 1: Consider projects Alpha and Beta: Cash Flows ($) Project...

I will rate, thank you.

Part 1:

Consider projects Alpha and Beta:

Cash Flows ($)
Project C0 C1 C2 IRR (%)
Alpha –389,000 242,000 288,999 23
Beta –199,000 131,500 167,000 30

The opportunity cost of capital is 8%. Suppose you can undertake Alpha or Beta, but not both. Use the IRR rule to make the choice.

Which project did you choose?

Alpha
Beta

Part 2:

Consider the following projects:

Cash Flows ($)
Project C0 C1 C2 C3 C4 C5
A −2,500 2,500 0 0 0 0
B −5,000 2,500 2,500 5,500 2,500 2,500
C −6,250 2,500 2,500 0 2,500 2,500

a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV?

Which are Positive NPV project(s)?

Project A
Project B
Project C
Projects A and B
Projects A and C
Projects B and C
Projects A, B, and C
No project

b. Calculate the payback period for each project: (Round your answers to 2 decimal places. If a project never pays back, enter "0".)

  Project A year(s)
  Project B year(s)
  Project C year(s)

c. Which project(s) would a firm using the payback rule accept if the cutoff period were three years?

Project(s) accepted                 

(Click to select)

Project A

Project B

Project C

Projects A and B

Projects A and C

Projects B and C

Projects A, B, and C

No project

d. Calculate the discounted payback for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places. If a project never pays back, enter "0".)

Project A year(s)
Project B year(s)
Project C year(s)

e. Which project(s) would a firm using the discounted payback rule accept if the cutoff period were three years?

Project(s) accepted            

    (Click to select)

Project A

Project B

Project C

Projects A and B

Projects A and C

Projects B and C

Projects A, B, and C

No project

Solutions

Expert Solution

Part 1: Ans: Beta

IRR represents the rate of return given by the Project. A project can be accepted only if the IRR is higher than the Oppurtunity Cost of Capital.

In the given case IRR of the projects are already given, As the IRR of both the projects are above Oppurtunity cost of capital both th projects can be accepted.

Howeve as the is a restriction that only one project can be accepted, as per IRR rule, it is advisable to accept the project with higher IRR.

As Beta is having higher IRR as compared to Alpha, it is advisable to accept Beta.

Part 2: Ans:

Oppurtunity Cost of Capital = 9%

Project - A - B - C -
Year PVF @ 9% Cashflows - A PV of Cashflow Cashflows - B PV of Cashflow Cashflows - C PV of Cashflow
a b c d = c * b e f = e * b g h = g * b
0 1 -2500 -2500 -5000 -5000 -6250 -6250
1 0.9174 2500 2293.5 2500 2293.5 2500 2293.5
2 0.8417 0 0 2500 2104.25 2500 2104.25
3 0.7722 0 0 5500 4247.1 0 0
4 0.7084 0 0 2500 1771 2500 1771
5 0.6499 0 0 2500 1624.75 2500 1624.75
- NPV A -206.5 B 7040.6 C 1543.5

a. Projects with Positive NPV = Projects B and C

Project A - B - C -
Year Cashflows - A Cummulative Cashfow Cashflows - B Cummulative Cashfow Cashflows - C Cummulative Cashfow
0 -2500 -2500 -5000 -5000 -6250 -6250
1 2500 0 2500 -2500 2500 -3750
2 0 0 2500 0 2500 -1250
3 0 0 5500 5500 0 -1250
4 0 0 2500 8000 2500 1250
5 0 0 2500 10500 2500 3750

(b)

Payback Period of Project A = 1 Year
Payback Period of Project B = 2 Years
Payback Period of Project C = 3 Years + (2500/1250) = 3.5 Years

(c) If Cut off is 3 years: Only those projects with Payback period lessthan 3 years can be accepted.

Hence, Projects A and B can be accepted.

(d)

Project - A - - B - - C - -
Year PVF @ 9% Cashflows - A PV of Cashflow Cummulative PV of Cashflow Cashflows - B PV of Cashflow Cummulative PV of Cashflow Cashflows - C PV of Cashflow Cummulative PV of Cashflow
a b c d = c * b - e f = e * b - g h = g * b -
0 1 -2500 -2500 -2500 -5000 -5000 -5000 -6250 -6250 -6250
1 0.9174 2500 2293.5 -206.5 2500 2293.5 -2706.5 2500 2293.5 -3956.5
2 0.8417 0 0 -206.5 2500 2104.25 -602.25 2500 2104.25 -1852.25
3 0.7722 0 0 -206.5 5500 4247.1 3644.85 0 0 -1852.25
4 0.7084 0 0 -206.5 2500 1771 5415.85 2500 1771 -81.25
5 0.6499 0 0 -206.5 2500 1624.75 7040.6 2500 1624.75 1543.5

(d)

As the net PV of Cashflow is negative for Project A, it is not completely paid back, Hence, there wil be no Discounted Paybeck period for Project A. = 0
Discounted Payback Period for Project B = 2 Years + (4,247.1 / 602.25) = 2.14 Years
Discounted Payback Period for Project C = 4 Years + (81.25 / 1624.75) = 4.05 Years

(e)

If Cut off is 3 years: Only those projects with Discouted Payback period lessthan 3 years can be accepted.

Hence, Projects B can be accepted


Related Solutions

Using the cash flows given in the table below for mutually exclusive projects Alpha and Beta,...
Using the cash flows given in the table below for mutually exclusive projects Alpha and Beta, assist the Chief Financial Officer in finding the breakeven rate (the crossover point or the rate of indifference). Which project do you recommend if using a cost of capital of 9% and Why? YEAR PROJECT ALPHA PROJECT BETA 0 -175 000 -82 500 1 40 000 30 000 2 60 000 10 500 3 85 000 40 000 4 92 000 75 000 5...
The following cash flows have been given for mutually exclusive Projects Alpha and Beta: Year ProjectAlpha  ...
The following cash flows have been given for mutually exclusive Projects Alpha and Beta: Year ProjectAlpha   ProjectBeta 0 -175000 -82500 1 40000 30000 2 60000 -10500 3 85000 40000 4 92000 75000 5 92000 92000 (a) Use the payback period month to identify which project is more attractive. The requirement is that projects have a payback period of 3 years or less. (b) At 10% cost of capital, use NPV approach to identify which project should be accepted and why?...
You need to consider two projects which have the following cash flows: Project A requires an...
You need to consider two projects which have the following cash flows: Project A requires an initial investment of $10,000 and will generate net cash flows of $5,000 at the end of year 1, $6,000 at the end of year 2, $7,000 at the end of year 3, and $8,000 at the end of year 4. At the end of year 2, maintenance costs of $8,000 will have to be disbursed. Project B requires an initial investment of $15,500 and...
You need to consider two projects which have the following cash flows: Project A requires an...
You need to consider two projects which have the following cash flows: Project A requires an initial investment of $10,000 and will generate net cash flows of $5,000 at the end of year 1, $6,000 at the end of year 2, $7,000 at the end of year 3, and $8,000 at the end of year 4. At the end of year 2, maintenance costs of $8,000 will have to be disbursed. Project B requires an initial investment of $15,500 and...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260...
Consider the following two projects: Cash flows Project A Project B C0 −$ 260 −$ 260 C1 110 138 C2 110 138 C3 110 138 C4 110 a. If the opportunity cost of capital is 10%, which of these two projects would you accept (A, B, or both)? b. Suppose that you can choose only one of these two projects. Which would you choose? The discount rate is still 10%. c. Which one would you choose if the cost of...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280...
Consider the following two projects: Cash flows Project A Project B C0 −$ 280 −$ 280 C1 120 148 C2 120 148 C3 120 148 C4 120 a.What are the internal rates of return on the two projects? b. If the opportunity cost of capital is 11%, what is the profitability index for each project?
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project...
Consider cash flows for projects A and B Year: 0, 1, 2, 3, 4, 5 Project A: -$1000, 375, 375, 375, 375,-100 Project B: -$1000, 900, 700, 500, -200, 200 The cost of capital for both projects is 10% 1. Find the NPV and MIRR of projects A and B. If project A and B are mutually exclusive. 2. Find the crossover rate for projects A and B. 3. What is the profitability index for projects A and B? How...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project....
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project....