Question

In: Accounting

Problem 2: Given the net cash flows for Project X (over 3-years) for Aberdeen Company Year...

Problem 2: Given the net cash flows for Project X (over 3-years) for Aberdeen Company Year CF 0-$300,000 1 $120,000 2 $128,000 3 $155,000 The company's capital structure is distributed equally between debt, preferred stock, common stock and new common stock. It has also the following information: 1- After tax cost of debt: 5.4%. Tax rate: 40% 2- Preferred stocks are selling at $80 per share and pay a dividend of $8 per share 3- Common stocks are selling at $50 per share, pay a year-end dividend of $3 per share and grow at a constant rate of 6%. When issuing new common stock, a 10% flotation cost would be incurred. The company is also considering another two projects "Y" & "Z" with the following information: Projects Y Z NPV $20,100.3 $37,320.2 MIRR 9.2% 14.5% IRR 7.77% 15.04% Payback period in years 4.1 1.64 Noted. 5. Assuming that the three projects X, Y & Z are independent, which project (s) should the company accept? * A. Project X B. Project Y C. Only Projects X & Z D. All E. Reject all projects 6. Assuming that the three projects X Y & Z are mutual exclusive, and which project (s) should the company accept? A. Project X B. Project Y C. Project Z D. All E. Reject all projects 7. Assuming that the three projects X, Y & Z are independent, based on MIRR criteria which project(s) should the company accept? A Project X B. Project Z C. Projects X, Y & Z D. Only Projects X & Z E Reject all projects

Solutions

Expert Solution

Answer:-

Year Cash Flow
0 $300,000
1 $120,000
2 $128,000
3 $155,000
After-Tax Cost of debt 5.40%
Tax Rate 40.00%
Preferred Dividend 8
Preferred Stock price 80
Current Selling Price 50
Dividend per share 3
Growth Rate 6%
Flotation cost 10%
Capital Structure Weights
A 33.33%
B 33.33%
C 33.33%
1. Calculation of Cost of preferred stock 10%
2. Calculation of Cost of Equity 12.67%
3. Calculation of WACC 9.36%
Year Cash Flow Discount Rate PV Factor PV of Item
0 -300000 9.36% 1 -300000
PV of cash outflows 300000
Year Cash Flow Discount Rate PV Factor PV of Item
1 120000 9.36% 1.196 143515.32
2 128000 9.36% 1.093 139980.8
3 155000 9.36% 1 155000
FV of Cash outflows 438496.12
Year Cash Flow Cumulative Cash Flows PVF PV of cash flow Cumulative PV of Cashflow
0 -300000 -300000 1 -300000 -300000
1 120000 -180000 0.914 109729.33 -190270.6
2 128000 -52000 0.836 107026.9 -83243.76
3 155000 103000 0.765 118510.33 35266.57
NPV 35266.57
MIRR 13.49%
Payback period 2.34
Discounted Payback period 2.7
Parameters X Y Z
NPV 35266.57 20100.3 37320.2
MIRR 13.49% 9.20% 14.50%
Payback period 2.34 4.1 1.64
IRR 15.59% 7.77% 15.04%

Part:5 - The Correct option is D - ALL ( All Projects have Positive NPV, Accept all)

Part 6:- The correct Option is C - Project Z (Highest NPV)

Part 7:- The correct Option is D - Only Project X&Z (MIRR>WACC)


Related Solutions

The cash flows and Net salvage value of Project X is given the following table: Year...
The cash flows and Net salvage value of Project X is given the following table: Year Cash flows Salvage Value 0 -5,800 4,800 1 2,100 3,000 2 3,400 2,200 3 3,600 1,800 4 1,800 0 Based on the Economic Life of this project and the cost of capital is 12%, in what year should you abandoning this Project X? A. Year 3, since NPV in year 3 = $8,429 B. Year 3, since NPV in year 3 = $2,629 C....
CASH FLOWS OVER PROJECT #2's LIFE Target Rate of Return 9.229% Net Cash Flows At End...
CASH FLOWS OVER PROJECT #2's LIFE Target Rate of Return 9.229% Net Cash Flows At End of Year Year Number 0 1 2 3 4 YEAR 2019 2020 2021 2022 2023 CAPITAL PRODUCT #2 -$1,581,500 $486,300 $486,700 $431,100 $1,123,100 Cumulative cash flows -$1,581,500 -$1,095,200 -$608,500 -$177,400 $945,700 Discounted cash flows -$1,581,500 $445,211 $407,930 $330,799 $788,981 Cumulative discounted cash flows -$1,581,500 -$1,136,289 -$728,359 -$397,560 $391,421 Calculate using above information: 1) Net Present Value (NPV) 2) Internal Rate of Return (IRR) 3)...
Cash Flow Over Project #3 Lifecycle Target Rate of Return 9.229% Net Cash Flows At End...
Cash Flow Over Project #3 Lifecycle Target Rate of Return 9.229% Net Cash Flows At End of Year Year Number 0 1 2 3 4 YEAR 2019 2020 2021 2022 2023 CAPITAL PRODUCT #3 -$1,593,800 $406,900 $445,500 $691,100 $1,106,400 Cumulative cash flows -$1,593,800 -$1,186,900 -$741,400 -$50,300 $1,056,100 Discounted cash flows -$1,593,800 $372,520 $373,398 $530,307 $777,249 Cumulative discounted cash flows -$1,593,800 -$1,221,280 -$847,882 -$317,575 $459,674 Calculate using the above information: 1) Net Present Value (NPV) 2) Internal Rate of Return (IRR)...
Consider a project generating the following cash flows over six years: Year Cash Flow (R in...
Consider a project generating the following cash flows over six years: Year Cash Flow (R in millions) 0 -59.00 1 4.00 2 5.00 3 6.00 4 7.33 5 8.00 6 8.25 Required: 1. Calculate the NPV over six years. The discount rate is 11%. 2. This project does not end after the sixth year but instead will generate cash flows far into the future. Estimate the terminal value, assume that cash flows after year 6 will continue at R8.25 million...
Here are the net cash flows for a project your company is considering: Year 0 =...
Here are the net cash flows for a project your company is considering: Year 0 = -1000 Year 1 = 250 Year 2 = 449 Year 3 = 800 Year 4 = 500 Year 5 = 500 If the payback period with interest is 3 years, for what range of interest rates is this project worth doing (start your analysis with an interest rate of 0%)? ** Kindly just don’t directly draw the table with values in it, it’ll be...
Here are the net cash flows for a project your company is considering: Year 0 =...
Here are the net cash flows for a project your company is considering: Year 0 = -1000 Year 1 = 250 Year 2 = 449 Year 3 = 800 Year 4 = 500 Year 5 = 500 If the payback period with interest is 3 years, for what range of interest rates is this project worth doing (start your analysis with an interest rate of 0%)? ** Kindly just don’t directly draw the table with values in it, it’ll be...
A project is expected to create operating cash flows of $37,600 a year for 3 years....
A project is expected to create operating cash flows of $37,600 a year for 3 years. The initial cost of the fixed assets is $98,000. These assets will be worthless at the end of the project. Also, $3,200 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of retum is 14 percent?
A project is expected to create operating cash flows of $37,600 a year for 3 years....
A project is expected to create operating cash flows of $37,600 a year for 3 years. The initial cost of the fixed assets is $98,000. These assets will be worthless at the end of the project. Also, $3,200 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 14 percent?
Project X is expected to generate cash flows of $5,000 per year for 5 years and...
Project X is expected to generate cash flows of $5,000 per year for 5 years and its initial cost is $17,000. Project Y is mutually exclusive to Project S. Project Y costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, what is the IRR of the better project? a)12.00% b)14.85% c)13.65% d)14.05% e)14.40%
Projects X has the following expected net cash flows: Year Project X 0 $-160,000 1 90,000...
Projects X has the following expected net cash flows: Year Project X 0 $-160,000 1 90,000 2 60,000 3 35,000 4 30,000 If the required rate of return is 12 percent, what is the net present value for the Project X? a.$ 18,578 b$ 16,533 c$ 10,250 d$ 12,167 e$ 20,968
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT