Projects X has the following expected net cash flows:

Year Project X

0 $-160,000

1 90,000

2 60,000

3 35,000

4 30,000

If the required rate of return is 12 percent, what is the net present value for the Project X?

a.$ 18,578

b$ 16,533

c$ 10,250

d$ 12,167

e$ 20,968

Solutions

Expert Solution

Ans d$ 12,167

Year Project Cash Flows (i) DF@ 12% DF@ 12% (ii) PV of Project ( (i) * (ii) )
0 -160000 1 1                             (1,60,000)
1 90000 1/((1+12%)^1) 0.892857                                   80,357
2 60000 1/((1+12%)^2) 0.797194                                   47,832
3 35000 1/((1+12%)^3) 0.711780                                   24,912
4 30000 1/((1+12%)^4) 0.635518                                   19,066
NPV                                   12,167

Related Solutions

You are evaluating two projects with the following cash flows: Year Project X Project Y 0...
You are evaluating two projects with the following cash flows: Year Project X Project Y 0 −$552,600 −$521,000 1 217,700 207,400 2 227,600 217,200 3 234,800 225,100 4 194,500 185,900 What is the crossover rate for these two projects?
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
A hospital’s project has the following expected cash flows Year Cash flow 0 ($5,000) 1 $1,000...
A hospital’s project has the following expected cash flows Year Cash flow 0 ($5,000) 1 $1,000 2 $2,000 3 $3,000 If the cost of capital is 12%, should the project be undertaken? Show your calculations
The following are the cash flows of two projects: Year Project A Project B 0 $(340)...
The following are the cash flows of two projects: Year Project A Project B 0 $(340) $(340) 1 170 240 2 170 240 3 170 240 4 170 A.) Calculate the NPV for both projects if the opportunity costs of capital is 15%. *(2 decimal places, do not round intermediate calculations) B.) Suppose you can choose one one of these projects, which would you choose?
The following are the cash flows of two projects: Year Project A Project B 0 −$330...
The following are the cash flows of two projects: Year Project A Project B 0 −$330        −$330        1 160        230        2 160        230        3 160        230        4 160        a. Calculate the NPV for both projects if the opportunity cost of capital is 17%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV         A $    B    b. Suppose that you can choose only one of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT