Question

In: Accounting

Basics of Variance Analysis, Variable Inputs Basuras Waste Disposal Company has a long-term contract with several...

  1. Basics of Variance Analysis, Variable Inputs

    Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage and trash from residential customers. To facilitate the collection, Basuras places a large plastic container with each household. Because of wear and tear, growth, and other factors, Basuras places about 250,000 new containers each year (about 20% of the total households). Several years ago, Basuras decided to manufacture its own containers as a cost-saving measure. A strategically located plant involved in this type of manufacturing was acquired. To help ensure cost efficiency, a standard cost system was installed in the plant. The following standards have been established for the product's variable inputs:

    Standard
    Quantity
    Standard Price
    (rate in $)    
    Standard
    Cost    
    Direct materials 14 lbs. $ 3.5 $49
    Direct labor 1.7 hrs. 14 23.8
    Variable overhead 1.7 hrs. 6 10.2
    Total $72.8

    During the first week in January, Basuras had the following actual results:

    Units produced 9,000
    Actual labor costs $222,600
    Actual labor hours 15,900
    Materials purchased and used 124,000 lbs. @ $3.55
    Actual variable overhead costs $ 119,340

    The purchasing agent located a new source of slightly higher-quality plastic, and this material was used during the first week in January. Also, a new manufacturing process was implemented on a trial basis. The new process required a slightly higher level of skilled labor. The higher-quality material has no effect on labor utilization. However, the new manufacturing process was expected to reduce materials usage by 0.25 pound per container.

    Required:

    1. Conceptual Connection: Compute the materials price and usage variances. Assume that the 0.25 pound per container reduction of materials occurred as expected and that the remaining effects are all attributable to the higher-quality material. Would you recommend that the purchasing agent continue to buy this quality, or should the usual quality be purchased? Assume that the quality of the end product is not affected significantly.

    Price $  
    Usage $  
    Select the effect.
    Enter the net amount of the effect. $
    Select the correct decision.

    2. Conceptual Connection: Compute the labor rate and efficiency variances. Assuming that the labor variances are attributable to the new manufacturing process, should it be continued or discontinued? In answering, consider the new process's materials reduction effect as well. If an amount is zero, enter "0".

    Rate $  
    Efficiency $
    Select the effect.
    Enter the overall net amount of the effect. $
    Select the correct decision.

    3. Conceptual Connection: Refer to Requirement 2. Suppose that the industrial engineer argued that the new process should not be evaluated after only one week. His reasoning was that it would take at least a week for the workers to become efficient with the new approach. Suppose that the production is the same the second week and that the actual labor hours were 12,000 and the labor cost was $168,000. Should the new process be adopted? Assume the variances are attributable to the new process. Assuming production of 9,000 units per week, what would be the projected annual savings? (Include the materials reduction effect.) If an amount is zero, enter "0".

    Rate $
    Efficiency $
    Select the effect.
    Enter the annual amount of the effect. $
    Select the correct decision.

Solutions

Expert Solution

1.

Price $ 6,200 U
Usage 875 U
Effect Unfavorable
Net amount of effect $ 7,075 U
Decision Discontinue buying the new quality

Materials price variance = $ ( 3.50 - 3.55) x 124,000 lb. = $ 6,200 U

Materials usage variance = ( 9,000 x 13.75 - 124,000) x $ 3.50 = $ 875 U

Net amount of the effect = $ 7, 075 U

The purchasing agent should discontinue buying the new quality.

2.

Rate $ 0
Efficiency $ 8,400 U
Effect Unfavorable
Net amount of effect $ 8,400
Decision Discontinue new manufacturing process

Labor rate variance = $ ( 14 - 14) x 15,900 hours = $ 0

Labor efficiency variance = ( 9,000 x 1.70 - 15,900 ) x $ 14 =   $ 8,400 U

Net amount of effect = 8,400 U

The new manufacturing process should be discontinued.

3.

Rate $ 0
Efficiency $ 46,200 F
Effect Favorable
Annual amount of effect $ 2,402,400
Decision New manufacturing process should be continued

Labor rate variance = $ ( 14 - 14 ) x 12,000 = $ 0

Labor efficiency variance = ( 9,000 x 1.70 - 12,000 ) x $ 14 = $ 46,200 F

Net amount of effect = $ 46,200 F

Annual amount of the effect = $ 46,200 x 52 weeks = $ 2,402,400

The new manufacturing process should be continued.


Related Solutions

Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage and...
Basuras Waste Disposal Company has a long-term contract with several large cities to collect garbage and trash from residential customers. To facilitate the collection, Basuras places a large plastic container with each household. Because of wear and tear, growth, and other factors, Basuras places about 210,000 new containers each year (about 20% of the total households). Several years ago, Basuras decided to manufacture its own containers as a cost-saving measure. A strategically located plant involved in this type of manufacturing...
what are the true long-term disposal options for nuclear waste? does the substrate/polymer lend itself to...
what are the true long-term disposal options for nuclear waste? does the substrate/polymer lend itself to be hard directly in the final processing of the waste for longterm disposal?
CASHFLOWS A waste management company is considering powering a temporary waste disposal site in a remotr...
CASHFLOWS A waste management company is considering powering a temporary waste disposal site in a remotr area by either solar panels or constructing an abovr ground electric line to the fwcility and using conventional power Solar panels will cost $20,000 to install and will have a useful life of 6yrs with no salvage value. Annual cost for inspection, cleaning, etc. is expected to be $5,000 for first 3 years and $7,000 for last 3 years. Solar panels are tax free....
Coal, Inc. has paid $10 million to a waste disposal company to clean a site originally...
Coal, Inc. has paid $10 million to a waste disposal company to clean a site originally contaminated by Coal, Inc. through its operations and to assume its environmental liability (currently recorded as an $10 million liability on Coal's financial statements). State regulators have signed off on the liability transfer and now look to the waste disposal company as the responsible party for the cleanup. Question 1 What is an appropriate way for Coal, Inc. to remove the environmental liability from...
wa waste disposal company is considering getting into bio-disposal business. the incinerators cost $5000 per unit....
wa waste disposal company is considering getting into bio-disposal business. the incinerators cost $5000 per unit. each unit can safely burn 1.25 tons of waste per burn and can be used for 6 burns per 8-hour day. each unit requires 1 worker to operate the unit. assume a labor rate of $11.05 per hour. in addition, each burn requires $62 of fuel to operate. the overhead is estimated to run $70.00 per day. the company estimates it has sufficient demand...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract...
Problem 1: Long-Term Contract At the beginning of 2018, the Harding Construction Company received a contract to build an office for $5 million. Harding will construct the building according to the specifications provided by the buyer, and the project is estimated to take three years to complete. According to the contract, Harding will be the buyer in installments over the construction period according to a prearranged schedule. Information related to the contract is as follows: 2018                    2019                2020...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
case study: A leading maintenance management company has been awarded the contract for sole long- term...
case study: A leading maintenance management company has been awarded the contract for sole long- term maintenance of an airport including its hangars, control tower, parking and hotel facilities. Being a maintenance manager working for the company, suggest the most suitable ideas for the following situations. questions: 1. List five resources in this project which can have an MTBF or MTTF associated with them. Explain one benefit for each resource. 2. Explain any six benefits this project will experience by...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT