Question

In: Accounting

Anderson Ltd. manufacture gearboxes for use in cars. At the start of the year, the management...

Anderson Ltd. manufacture gearboxes for use in cars. At the start of the

year, the management of Anderson Ltd. estimated that its costs would be:

This was based on the following:

Direct labour

Direct material

Variable production overhead

Fixed production overhead

Administration overhead

8

50

8

12

5

80 employees

2000 hours worked by each employee

40 000 gearboxes manufactured in the year as budgeted production

£200 unit selling price.

You have recently been employed by the company to establish a standard

costing system. At the end of the year you were able to extract the

following information:

• labour costs £4.40/hour

• 32 000 units sold

• £210/unit selling price

• 160 000 hours were worked

• variable production overheads were £640 000

• fixed production overheads were £810 000

• administration costs were £350 000

• raw material prices were 10% higher than expected

• total expenditure on raw material was £3.696 M

• there were no opening or closing stocks of raw materials.

(a) You are required to prepare an operating statement for the year, using

a standard absorption costing system.

Calculations should proceed according to the following headings

suffixing ‘A’ for Adverse and ‘F’ for Favourable where appropriate.

Resulting quantities required for the statement are then entered in the

‘Operating Statement for the Year’ sheet shown on page 6.

(All working must be shown.)

(Budgeted) Costs

Unit cost

£

Direct labour

Direct materials

Variable overhead

Fixed overhead

Admin. overhead

Total

Selling price

Standard profit (per unit)

Budgeted profit

Sales price variance

Sales quantity variance

Cost Variances

Labour Variances

Standard hours =

Standard cost/hour =

Rate variance =

Standard time =

Actual time =

Time variance =

Efficiency variance =

Material Variances

Material price =

Material usage      – standard =

– actual =

Material usage variance =

Variable overheads

Standard cost =

Actual cost =

Expenditure variance =

Efficiency variance =

Fixed overheads

Expenditure variance =

Volume variance =

Admin overhead (treat as fixed)

Expenditure variance =

Volume variance =

Operating Statement for the Year

£’000 £’000

Budgeted Profit

Sales variance      – price

– quantity

Cost variances

Labour                  – rate

– efficiency

Material                – price

– usage

Variable                – expenditure

– efficiency

Fixed                    – expenditure

– volume

Admin                  – expenditure

– volume

Actual Profit

(b) Give reasons/explanations why the variances in (a) above have

occurred for the following:

(i) material price

(ii) labour efficiency

(iii) fixed overhead expenditure.

(c) The accountant suggests that a standard marginal costing system may

be more suitable. He asks you to outline the strengths and

weaknesses of both systems and recommend the most suitable.

(d) The Board of Anderson Ltd. want to adopt ‘ideal’ standards because

they feel it will encourage harder work. You are asked to produce a

brief report giving your views.

Solutions

Expert Solution

Solution: In the given above problem has multiple parts having multiple sub parts. so, I Have answered the parts relating to a) Labour Cost Variances

b) Material Cost Variances

a) Calculated as per Labour Cost Variances

Particulars Formula working Amount
Standard Hours 80X2,000 160,000
Standard Cost/Hour 200X8%X.25 4
Rate Varaince Actual HoursX(Actual rate - Standard Rate) 160,000X(4.40 - 4) 64,000 (U)
Standard Time assumed for actual production 128,000
Actual Time 160,000
Time Variance Actual Time - Standard Time 32,000 (U)
Efficiency Variance Standard Rate X (Actual Hours - Standard Hours for Actual Production) 4X(160,000 - 32,000X160,000/40,000) or 32,000X4 128,000 (U)

Note:In this Labour cost variance , F indicates favorable variance and U indicates unfavorable variance.

b) Calculated as per Material Cost Variances

Particulars Formula working Amount
Material Price Variance (MPV) Actual Material X (Actual Rate - Stadard Rate) 369,600,0/110X(110-100) 336,000 (U)
Material Usage Variance (MUV) Standard Rate X (Actual Material - Standard Material for Actual Production) 100X(33,600-32,000) 160,000 (U)

Note:# In this Material cost variance , F indicates favorable variance and U indicates unfavorable variance.

#Standard Material Rate = Selling Price*50% = 200*50% = 100

#Standard material is assumed to be 1 per unit. Therefore, standard material used for actual production would be 32,0000 (32,000*1).


Related Solutions

On 31 December year 0, Khan Ltd invested in some machinery and started to manufacture a...
On 31 December year 0, Khan Ltd invested in some machinery and started to manufacture a new product the ‘gadget’. The decision was based on the machinery being capable of producing gadgets until the end of Year 6 and sales continuing until that time. Actual sales of gadgets have not been as buoyant as projected when the investment was being appraised during year 0. As a result, the business’s management is considering abandoning the project at the end of year...
Cleaning Equipment Specialists Ltd (CES) manufacture cleaning equipment for household and industrial use. They have received...
Cleaning Equipment Specialists Ltd (CES) manufacture cleaning equipment for household and industrial use. They have received a bid from a supplier to provide motors for their household vacuum cleaner product line. The bid is to supply 10,000 motors at a price of $85 each. CES currently manufacture the motors in-house. The management accountant of CES has estimated the current costs of producing one motor as follows: Direct Materials        $42 Direct Labour            18 Variable Overhead   20 Fixed Overhead         66...
Suppose you are the CFO of Toyota and that you manufacture your cars in Japan and...
Suppose you are the CFO of Toyota and that you manufacture your cars in Japan and export the vehicles to the USA. Assuming your current profit per car is $1,000 and you sell 10,000 this year, please answer the following and show your computations:    - From a profitability point of view, do you generally favor a strong or weak US Dollar versus the Japanese YEN? Why?    - If the exchange rate is 1 US Dollar = 1.20 Japanese...
ABC Ltd. bought an asset at the start of an accounting year costing $100,000. Asset has...
ABC Ltd. bought an asset at the start of an accounting year costing $100,000. Asset has an expected life of 10years with a residual value of $4,000. Show the schedule of depreciation expense in each year using double declining balance method (200%)with switchover to straight line method.
ABC Ltd. bought an asset at the start of an accounting year costing $100,000. Asset has...
ABC Ltd. bought an asset at the start of an accounting year costing $100,000. Asset has an expected life of 10years with a residual value of $4,000. Show the schedule of depreciation expense in each year using double declining balance method (200%) with switchover to straight line method.
Financial start of Red river ltd at the end of financial year 2018-2019 has the following...
Financial start of Red river ltd at the end of financial year 2018-2019 has the following information. Sales of $855000, Cost of goods sold $542000, selling expenses of $12000, administration expenses of $6000, depreciation expenses of $35000, interest expenses of $12000 and corporate tax rate of 30%. The firm is planning a new investment project that requires a cost of $350000. The firms plans a capital structure of 40% equity and 60% debt to finance this project. Calculate the gross...
Customer Ltd enters into a 10-year contract with Supplier Ltd for the right to use two...
Customer Ltd enters into a 10-year contract with Supplier Ltd for the right to use two specified physically distinct dark fibres within a larger cable connecting Hong Kong to Tokyo. Customer Ltd makes the decisions about the use of the fibres by connecting each end of the fibres to its electronic equipment (i.e., Customer ‘light’ the fibres and decides what data and how much data to transfer). If the fibres are damaged, Supplier Ltd is responsible for the repairs and...
1. Two cars are moving on a road and both start at the same place at...
1. Two cars are moving on a road and both start at the same place at time ?=0. The velocity of car number 1 is given by ?1(?)=sin?+1 and the velocity of car number 2 is given by ?2(?)=cos?+1. a. Which car is ahead at ?=?2 ,?=?,?=3?? [3 marks] b. Write down a definite integral which gives the total distance traveled by car number 1 from ?=0 to ?=10. [3 marks] b. Write down a definite integral which gives the...
Japanese auto companies manufacture cars in the United States for each of the following reasons EXCEPT...
Japanese auto companies manufacture cars in the United States for each of the following reasons EXCEPT ________. Question 45 options: to combat the costs of being home to the world's highest paid workers to offset the risk of currency fluctuations to be closer to customers to defuse political concerns regarding the U.S. trade deficit with Japan
The managers of PonchoParts, Inc. plan to manufacture engine blocks for classic cars from the 1960s...
The managers of PonchoParts, Inc. plan to manufacture engine blocks for classic cars from the 1960s era. They expect to sell 250 blocks annually for the next 5 years. The necessary foundry and machining equipment will cost a total of $800,000 and will be depreciated on a straight-line basis to zero over the project’s life. The firm expects to be able to dispose of the manufacturing equipment for $150,000 at the end of the project. Labor and materials costs total...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT