Question

In: Economics

You have analyzed a 10-year project and determined that it's net present worth (calculated at MARR=8%)...

You have analyzed a 10-year project and determined that it's net present worth (calculated at MARR=8%) is -$1,455,340.00. Which of the following statements must be true?

Question options:

The project's IRR is 8%.

The project's IRR is greater than 8%.

The project's IRR is less than 8%.

You cannot make any of the above judgments about this project's IRR from this information.

Solutions

Expert Solution

Answer - Project's IRR is less than 8%.

In the question, MARR is 8%.

At MARR of 8%, the NPW is -1,455,340. It means the NPW is negative. A negative net present value implies that at 8%, the present value of outflows is more than the present value of inflows.
For the calculation of IRR we use the trial and error method. At this given condition, we need to reduce the rate of interest to get a positive NPV. After getting the positive NPV we can use the interpolation formula to calculate IRR. In the interpolation formula we have to start with that rate of interest where the NPV is positive and that interest rate definitely will less than the MARR. In the question at 8%, the NPV is negative. To calculate positive NPV we have to decrease the rate of interest. It means we need to calculate NPV at a rate that is less than 8%.

Therefore, if the NPV at MARR is negative, the IRR will be definitely less than MARR.


Related Solutions

A breakeven analysis for net present worth is performed with a MARR of 15% and a...
A breakeven analysis for net present worth is performed with a MARR of 15% and a useful life of 20 years with the following data: Initial Cost: $750,000 Annual Cost (O&M): $60,000/ year with an annual increase of $5,000 each year Annual Revenue: $80,000/ year with an annual increase of $1,000 each year Salvage Value: $475,000 Determine the following: a. If the project is viable (i.e. if the profit is larger than the cost using net present worth). b. The...
How is the net present value (NPV) calculated for a project with a conventional cash flow...
How is the net present value (NPV) calculated for a project with a conventional cash flow pattern, and what are the acceptance criteria for NPV, how are they related to the firm’s market value with explanation of the similarities and differences between NPV, PI, and EVA. PLEASE MINIMUM 350 WORDS.
Have you ever calculated your own net worth? Why or why not..... What are client goals?...
Have you ever calculated your own net worth? Why or why not..... What are client goals? Why are they important? What are some of your financial goals?
Determine the breakeven (based on net present worth) initial cost for a project with an interest...
Determine the breakeven (based on net present worth) initial cost for a project with an interest rate of 6% and a useful life of 14 years with the following data: Annual Cost (O&M): $7,500/ year with an annual increase of $800/ year Annual Revenue = $9,000/ year with an annual increase of $1,000/ year Salvage Value: $50,000
Find the present worth of the following project, using i = 10%/year. Cash Flows Initial cost...
Find the present worth of the following project, using i = 10%/year. Cash Flows Initial cost $20000 Annual benefit for years 1 ~ 10 $6000 Annual benefit for years 11 ~ 20 $8000
Net present worth (NPW) of a project is sensitive to 4 input parameters, namely: A, B,...
Net present worth (NPW) of a project is sensitive to 4 input parameters, namely: A, B, C and D. Assume that NPW= 4000-90000Pa, is the relation that gives the NPW of the project as a function of Pa, which is the percentage deviation in the factor A. Similarly, assume that NPW= 4000-40000Pb, NPW= 4000+60000Pc and NPW= 4000+70,000Pd are the functions that give the NPW of the project as function of the percentage deviations in the factors B, C and D...
You have determined the profitability of a planned project by finding the present value of all the cash flows fro...
You have determined the profitability of a planned project by finding the present value of all the cash flows from that project. Which of the following would cause the project to look more appealing in terms of the present value of those cash flows? The discount rate decreases. The cash flows are extended over a longer period of time, but the total amount of the cash flows remains the same. The discount rate increases. Answers band c above. Answers a and b above. The future value...
What is the net present value of the stadium project, which is a 3-year project where...
What is the net present value of the stadium project, which is a 3-year project where Fairfax Pizza would sell pizza in the baseball stadium? The project would involve an initial investment in equipment of 160,000 dollars today. To finance the project, Fairfax Pizza would borrow 160,000 dollars. The firm would receive 160,000 dollars from the bank today and would pay the bank 206,400 dollars in 3 years (consisting of an interest payment of 46,400 dollars and a principal payment...
Find the present worth of the following infinite cash flows, using i = 8%/year: $0 for...
Find the present worth of the following infinite cash flows, using i = 8%/year: $0 for years 1 ~ 3, $500 for even years 4, 6, 8, ..., and $900 for odd years 5, 7, 9, ....
To recover your investment and earn a MARR of 10% per year, how long will you...
To recover your investment and earn a MARR of 10% per year, how long will you have to own a business that costs $230,000 to setup, generates $50,000 per year in income and has $15,000 per year in expenses ?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT