Question

In: Economics

Find the present worth of the following project, using i = 10%/year. Cash Flows Initial cost...

Find the present worth of the following project, using i = 10%/year.

Cash Flows

Initial cost $20000

Annual benefit for years 1 ~ 10 $6000

Annual benefit for years 11 ~ 20 $8000

Solutions

Expert Solution

Hey Here is the answer feel free to ask anything-

Calculation of present value:

-Initial Cost * Present Value Factor (10%, 0 year) + Annual Benefit * Present Value Annuity

Factor(10%,10 years) + Annual Benefit * Present Value Annuity Factor(10%,20-11years)

($200,000) * 1 + $6000 * 6.145 + $8,000 * (8.514-6.145)

($200,000) + 36,870 + 18,952

($144,178) is the present worth of the project.

Difference of Annuity factor for 11 and 20 years at 10% is used.


Related Solutions

Find the present worth of the following infinite cash flows, using i = 8%/year: $0 for...
Find the present worth of the following infinite cash flows, using i = 8%/year: $0 for years 1 ~ 3, $500 for even years 4, 6, 8, ..., and $900 for odd years 5, 7, 9, ....
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost: ​$210,000 Cash flow year​ one: ​$25,000 Cash flow year​ two: ​$72,000 Cash flow year​ three: ​$146,000 Cash flow year​ four: ​$146,000 a. Using a discount rate of 11​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 13​%? c. Should the company accept...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Quark Industries has a project with the following projected cash​ flows: Initial​ cost: ​$270,000 Cash flow year​ one: ​$24,000 Cash flow year​ two: ​$79,000 Cash flow year​ three: ​$155,000 Cash flow year​ four: ​$155,000 a. Using a discount rate of 10​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 13​%? c. Should the company accept...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial​ cost:...
Net present value. Lepton Industries has a project with the following projected cash​ flows: Initial​ cost: ​$460,000 Cash flow year​ one: ​$132,000 Cash flow year​ two: ​$200,000 Cash flow year​ three: ​$191,000 Cash flow year​ four: ​$132,000 a. Using a discount rate of 11​% for this project and the NPV​ model, determine whether the company should accept or reject this project. b. Should the company accept or reject it using a discount rate of 13​%? c. Should the company accept...
A project requires an initial cost of $225,000; has a present value of operating cash flows...
A project requires an initial cost of $225,000; has a present value of operating cash flows over its ten-year life of $310,000; and has a book value at the end of 10 years of $120,000. Current assets of $20,000, and current liabilities of $4,000 will be needed for the project to begin. Calculate the terminal value and NPV using its book value after 10 years, assuming a 15 percent discount rate.
Determine the breakeven (based on net present worth) initial cost for a project with an interest...
Determine the breakeven (based on net present worth) initial cost for a project with an interest rate of 6% and a useful life of 14 years with the following data: Annual Cost (O&M): $7,500/ year with an annual increase of $800/ year Annual Revenue = $9,000/ year with an annual increase of $1,000/ year Salvage Value: $50,000
Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0: $468,000...
Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0: $468,000 Cash flow year one: $135,000 Cash flow year two: $240,000 Cash flow year three: $185,000 Cash flow year four: $135,000 Plot the NPV profile of this project in Excel. Start with discount rate equal to zero and increase the discount rate by 2% increments until discount rate equal to 30%. For what discount rates would Lepton accept this project? For what discount rates would...
Project Q has an initial cost of $257,412 and projected cash flows of $123,300 in Year...
Project Q has an initial cost of $257,412 and projected cash flows of $123,300 in Year 1 and $180,300 in Year 2. Project R has an initial cost of $349,000 and projected cash flows of $184,500 in Year 1 and $230,600 in Year 2. The discount rate is 12.2 percent and the projects are mutually exclusive. Which project(s), if any, should be accepted based on the net present value rule? A. Accept both Projects. B. Accept Project R and reject...
Hendrix Guitar is considering the following Project. The Projected cash flows are below: Initial Cost is...
Hendrix Guitar is considering the following Project. The Projected cash flows are below: Initial Cost is $ 2.1 million; annual net cash flows are $750, 000 per year for 5 years. what is the discounted Payback Period if the appropriate discount rate is 7.5%?
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year...
A project has an initial cost of $40,000, expected net cash flows of $9,000 per year for 7 years, and a cost of capital of 11% Calculate in excel NPV, IRR, PB, DPB?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT