Question

In: Accounting

Barry Company budgeted the cost of materials for August to be $60,000 for 10,000 units produced....

Barry Company budgeted the cost of materials for August to be $60,000 for 10,000 units produced. Barry used the following standard cost per unit to prepare the August budget:

2 ounces of materials at $3.00 per ounce

In August, Barry produced 8,000 units at a total cost of $49,280. Each unit required 2.2 ounces of materials.  What is the materials usage variance for August?

A.

$4,800 U

B.

$7,200 U

C.

$1,280 U

D.

$3,520 U

E.

$10,720 U

Solutions

Expert Solution

Answer: A

Standard usage = Actual units of production × Standard materials per unit

                        = 8000 × 2

                        = 16000 ounces

Actual usage = Actual units of production × Actual materials per unit

                        = 8000 × 2.2

                        = 17600 ounces

Usage variance = (Standard usage – Actual usage) × Standard price

                        = (16000 – 17600) × $3

                        = 1600 × 3

                        = 4,800 unfavorable

Note: Since actual usage is higher than standard usage, there is unfavorable variance.


Related Solutions

Company budgeted sales in units for the next four months as follows: July 7,000 units August...
Company budgeted sales in units for the next four months as follows: July 7,000 units August 5,000 units September 6,500 units 1. Prepare the sales budget for the company knowing that each unit is sold for $50. (1 pt) 2. Past experience has shown that the ending inventory for each month should be equal to 20% of the next month's sales in units. The inventory in the beginning of July was only 1,000 units, & the inventory on September 30...
Variances Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg)...
Variances Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg) 400 700 ? Material cost ($) 8,000 See purchases ? Direct Labour (hours) 35,000 46,102 ? Direct Labour ($) 385,000 507,080 ? Variable Overhead ($) 350,000 419,161 ? Fixed Overhead ($) 160,000 161,000 ?             Other Information Overhead is Allocated on Direct Labour Hours During the year, 800 kg of materials were purchased for $5,000 Beginning Inventory: none Ending Inventory:     100kg Required: Calculate the...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg) 400...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg) 400 700 ? Material cost ($) 8,000 See purchases ? Direct Labour (hours) 35,000 46,102 ? Direct Labour ($) 385,000 507,080 ? Variable Overhead ($) 350,000 419,161 ? Fixed Overhead ($) 160,000 161,000 ?             Other Information Overhead is Allocated on Direct Labour Hours During the year, 800 kg of materials were purchased for $5,000 Beginning Inventory: none Ending Inventory:     100kg Required: Calculate the flexible...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg) 400...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 ? Materials used (kg) 400 700 ? Material cost ($) 8,000 See purchases ? Direct Labour (hours) 35,000 46,102 ? Direct Labour ($) 385,000 507,080 ? Variable Overhead ($) 350,000 419,161 ? Fixed Overhead ($) 160,000 161,000 ?             Other Information Overhead is Allocated on Direct Labour Hours During the year, 800 kg of materials were purchased for $5,000 Beginning Inventory: none Ending Inventory:     100kg Required: Calculate the flexible...
• Beginning cash balance for August is $500,000 • The company budgeted sales at 550,000 units...
• Beginning cash balance for August is $500,000 • The company budgeted sales at 550,000 units in August, September, and November and at 625,000 units per month in July and October. The selling price is $3.75 per unit. All sales are cash sales. That is, customers must pay ABC, Inc. before the tiles are shipped to the customer • The inventory of finished goods on July 1 was 125,000 units. The finished goods inventory at the end of each month...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 Materials used (kg) 400 700...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 Materials used (kg) 400 700 Material cost ($) 8,000 See purchases Direct Labour (hours) 35,000 46,102 Direct Labour ($) 385,000 507,080 Variable Overhead ($) 350,000 419,161 Fixed Overhead ($) 160,000 161,000             Other Information Overhead is Allocated on Direct Labour Hours During the year, 800 kg of materials were purchased for $5,000 Beginning Inventory: none Ending Inventory:     100kg Required: Calculate the flexible budget amounts for all items. Calculate the...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 Materials used (kg) 400 700...
Original Budget Actual Flexible Budget Units Produced (in units) 10,000 12,000 Materials used (kg) 400 700 Material cost ($) 8,000 See purchases Direct Labour (hours) 35,000 46,102 Direct Labour ($) 385,000 507,080 Variable Overhead ($) 350,000 419,161 Fixed Overhead ($) 160,000 161,000             Other Information Overhead is Allocated on Direct Labour Hours During the year, 800 kg of materials were purchased for $5,000 Beginning Inventory: none Ending Inventory:     100kg Required: Calculate the flexible budget amounts for all items. Calculate the...
Assume the following information for a company that produced 10,000 units and sold 8,000 units during...
Assume the following information for a company that produced 10,000 units and sold 8,000 units during its first year of operations and produced 8,000 units and sold 10,000 units during its second year of operations: Per Unit Per Year Selling price $ 200 Direct materials $ 82 Direct labor $ 50 Variable manufacturing overhead $ 10 Sales commission $ 8 Fixed manufacturing overhead $ 300,000 Using absorption costing, what is the cost of goods sold for the second year of...
Wyatt Company has budgeted the following units sales for 2011: January 10,000 units February 8,000 units...
Wyatt Company has budgeted the following units sales for 2011: January 10,000 units February 8,000 units March 9,000 units April 11,000 units May 15,000 units Data regarding Finished Goods and Raw Materials Inventory is as follows: FINISHED GOODS: The finished goods units on hand on December 31, 2010 was 2,000 units. Each unit required 2 pounds of raw materials that are estimated to cost an average of $4 per pound. It is the company's policy to maintain a finished goods...
Flagstaff Company has budgeted production units of 8,300 for July and 8,500 for August. The direct...
Flagstaff Company has budgeted production units of 8,300 for July and 8,500 for August. The direct labor requirement per unit is 0.50 hours. Labor is paid at the rate of $19 per hour. The total cost of direct labor budgeted for the month of August is: Multiple Choice $78,850. $4,250. $80,750. $4,150. $159,600. Flagstaff Company has budgeted production units of 8,100 for July and 8,300 for August. The direct materials requirement per unit is 2 ounces (oz.). The company requires...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT