In: Accounting
| 
 Budgeted Machine Hours  | 
 Flexible Machine Hours  | 
| 
 A. 64,400  | 
 72,800  | 
| 
 B. 72,800  | 
 64,400  | 
| 
 C. 68,000  | 
 75,000  | 
| 
 D. 75,000  | 
 68,000  | 
Solution 1:
The materials Quantity (usage) variance should be computed when materials are used in production.
Hence option "B" is correct.
Solution 2:
"The standard hours per unit for direct labor should allow for normal machine downtime, lean-up, and employee rest periods".
This Statement is correct.
Hence option "C" is correct.
Solution 3:
"In a flexible budget, both variables costs and fixed costs will vary across different levels of activity".
This statement is false about the flexible budget.
Hence option "B" is correct.
Solution 4:
Fixed overhead budget variance would be LEAST useful in calling attention to a possible control problem in the manufacturing costs due to its ambiguity.
Hence option "C" is correct.
Solution 5:
Budgeted machine hours at the original budget = Original Budget units* standard machine hours per unit = 23000* 2.8 = 64,400
Budgeted machine hours at the flexible budget = Units Produced* standard machine hours per unit = 26000*2.8 = 72,800
Hence option "A" is correct.