Question

In: Accounting

NashFurniture Company started construction of a combination office and warehouse building for its own use at...

NashFurniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,500,000 on January 1, 2020. Nash expected to complete the building by December 31, 2020. Nash has the following debt obligations outstanding during the construction period.

Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,800,000
Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,260,000
Long-term loan-11% interest, payable on January 1 of each year. Principal payable on January 1, 2024 900,000

(a)

Assume that Nash completed the office and warehouse building on December 31, 2020, as planned at a total cost of $4,680,000, and the weighted-average amount of accumulated expenditures was $3,240,000. Compute the avoidable interest on this project.

*Answer 366,000 is incorrect.

(b)

Compute the depreciation expense for the year ended December 31, 2021. Nash elected to depreciate the building on a straight-line basis and determined that the asset has a useful life of 30 years and a salvage value of $270,000.

Solutions

Expert Solution

Answer
Explanation :
a) The weighted average interest rate of all other debt (Other than the specific loan)
Debt Amount Interest rate Interest amount
10% Loan 12,60,000 10% 1,26,000
11% Loan 9,00,000 11% 99,000
21,60,000 2,25,000
Weighted avg rate = 225,000/21,60,000 x 100 = 10.4167%
Computation of Avoidable interest
Particulars Average Interest rate Avoidable interest
Avg accumulated expenditure 32,40,000
From:
Specific Loan interest 18,00,000 12% 2,16,000
Other debt interest 14,40,000 10.4167% 1,50,000
Total avoidable interest 3,66,000
b) Depreciation expense $135,200
Workings:
Straight Line method:-
Cost of building Total cost + Avoidable Interest
$3,960,000 + $366,000
$    43,26,000
Depreciation expense (Cost - Residual value) / useful Value
= ($43,26,000 - $270,000) / 30 years
= = 135,200 per year

Related Solutions

The Furniture Company started construction of a combination office and warehouse building for its own use...
The Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $14,500,000 on January 1, 2020. The Furniture Company expected to complete the building by December 31, 2020. The Furniture Company has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $5,800,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 4,060,000 Long-term loan-11% interest, payable...
Nash Furniture Company started construction of a combination office and warehouse building for its own use...
Nash Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $ 4,953,300 on January 1, 2017. Nash expected to complete the building by December 31, 2017. Nash has the following debt obligations outstanding during the construction period. Construction loan- 12% interest, payable semiannually, issued December 31, 2016 $2,015,500 Short-term loan- 10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,609,200 Long-term loan- 11% interest, payable...
Grouper Furniture Company started construction of a combination office and warehouse building for its own use...
Grouper Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $5,024,000 on January 1, 2017. Grouper expected to complete the building by December 31, 2017. Grouper has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $1,990,600 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,603,500 Long-term loan-11% interest, payable on January 1 of...
Riverbed Furniture Company started construction of a combination office and warehouse building for its own use...
Riverbed Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $3,000,000 on January 1, 2020. Riverbed expected to complete the building by December 31, 2020. Riverbed has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 840,000 Long-term loan-11% interest, payable on January 1 of...
Bramble Furniture Company started construction of a combination office and warehouse building for its own use...
Bramble Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $2,500,000 on January 1, 2020. Bramble expected to complete the building by December 31, 2020. Bramble has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,000,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 700,000 Long-term loan-11% interest, payable on January 1 of...
Nash Furniture Company started construction of a combination office and warehouse building for its own use...
Nash Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,600,000 on January 1, 2021. Nash expected to complete the building by December 31, 2021. Nash has the following debt obligations outstanding during the construction period. Construction loan—10% interest, payable semi-annually, issued December 31, 2020, maturity on December 31, 2030 $2,096,000 Short-term loan—8% interest, payable monthly, and principal payable at maturity on May 30, 2022 1,422,000 Long-term loan—9% interest,...
Skysong Furniture Company started construction of a combination office and warehouse building for its own use...
Skysong Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,981,900 on January 1, 2017. Skysong expected to complete the building by December 31, 2017. Skysong has the following debt obligations outstanding during the construction period. Construction loan-10% interest, payable semiannually, issued December 31, 2016 $2,000,100 Short-term loan-8% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,595,800 Long-term loan-9% interest, payable on January 1 of...
Flounder Furniture Company started construction of a combination office and warehouse building for its own use...
Flounder Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $3,000,000 on January 1, 2020. Flounder expected to complete the building by December 31, 2020. Flounder has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2019 $1,200,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2021 840,000 Long-term loan-11% interest, payable on January 1 of...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use...
Pronghorn Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $4,978,200 on January 1, 2017. Pronghorn expected to complete the building by December 31, 2017. Pronghorn has the following debt obligations outstanding during the construction period. Construction loan-12% interest, payable semiannually, issued December 31, 2016 $2,012,000 Short-term loan-10% interest, payable monthly, and principal payable at maturity on May 30, 2018 1,615,200 Long-term loan-11% interest, payable on January 1 of...
Culver Furniture Company started construction of a combination office and warehouse building for its own use...
Culver Furniture Company started construction of a combination office and warehouse building for its own use at an estimated cost of $6,000,000 on January 1, 2020. Culver expected to complete the building by December 31, 2020. Culver has the following debt obligations outstanding during the construction period. Construction loan-14% interest, payable semiannually, issued December 31, 2019 $2,400,000 Short-term loan-12% interest, payable monthly, and principal payable at maturity on May 30, 2021 1,680,000 Long-term loan-13% interest, payable on January 1 of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT