Question

In: Accounting

I need this question answered assuming that Westgate Construction's contract with Santa Clara County does NOT...

I need this question answered assuming that Westgate Construction's contract with Santa Clara County does NOT qualify for revenue recongnition over time... In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:

2016 2017 2018
Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000
Estimated costs to complete as of year-end 5,600,000 2,000,000 0
Billings during the year 2,000,000 4,000,000 4,000,000
Cash collections during the year 1,800,000 3,600,000 4,600,000
****IMPORTANT - Complete the requirements assuming that Westgate Construction's contract with Santa Clara County does NOT qualify for revenue recongnition over time.****
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2016 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2017 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
3. Complete the information required below to prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

Solutions

Expert Solution

·         Note: Question states that Contract DOES NOT QUALIFY for revenue recognition over time. This means that revenue will be recorded when the contract gets completed.

Requirement 1

2016

2017

2018

Revenue

$0

$0

$10,000,000

Gross Profits (Loss)

$0

$0

$1,800,000

Requirement 2A

Date

Accounts title

Debit

Credit

2016

Construction in Progress

$2,400,000

   Various accounts

$2,400,000

(construction cost incurred)

2016

Accounts receivables

$2,000,000

Billing on Construction contracts

$2,000,000

(amount billed during the year)

2016

Cash

$1,800,000

Accounts receivables

$1,800,000

(cash received)

Requirement 2B

Date

Accounts title

Debit

Credit

2017

Construction in Progress

$3,600,000

   Various accounts

$3,600,000

(construction cost incurred)

2017

Accounts receivables

$4,000,000

Billing on Construction contracts

$4,000,000

(amount billed during the year)

2017

Cash

$3,600,000

Accounts receivables

$3,600,000

(cash received)

Requirement 2C

Date

Accounts title

Debit

Credit

2018

Construction in Progress

$2,200,000

   Various accounts

$2,200,000

(construction cost incurred)

2018

Accounts receivables

$4,000,000

Billing on Construction contracts

$4,000,000

(amount billed during the year)

2018

Cash

$4,600,000

Accounts receivables

$4,600,000

(cash received)

2018

Construction in Progress

$1,800,000

Cost of construction

$8,200,000

Revenue from Long Term contract

$10,000,000

(revenue recognised)

Requirement 3

Balance Sheet [Partial]

2016

2017

Current Assets:

Accounts receivables

$200,000

$600,000

Construction in progress

$2,400,000

$6,000,000

Less: Billings

($2,000,000)

($6,000,000)

Costs and profits in excess of billings

$400,000

$0

Current Liabilities:

Accounts Payable

$0

$0

  • Requirement 4 [Data not provided]
    However,
    Gross Profits and Revenue for 2016 and 2017 would be $ 0
    For 2018:
    revenue = $ 10,000,000
    Gross Profit (loss) = $ 10,000,000 – total cost incurred in all 3 years.


Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000.
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:   2021 2022 2023 Cost incurred during the year $ 2,610,000   $ 3,162,000   $ 2,230,800   Estimated costs to complete as of year-end   6,390,000     2,028,000     0   Billings during the year   2,100,000     3,672,000     4,228,000...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000.
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:  Westgate recognizes revenue over time according to percentage of completion.    Required:  1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.  2. Prepare all necessary journal entries for each of the years (credit “Cash, Materials, etc.” for...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000.
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows:   2021 2022 2023 Cost incurred during the year $ 2,100,000   $ 2,450,000   $ 2,695,000   Estimated costs to complete as of year-end   4,900,000     2,450,000     0   Billings during the year   2,200,000     2,350,000     5,450,000...
Suppose a random sample of 500 adults from Santa Clara County answered this question: “in general,...
Suppose a random sample of 500 adults from Santa Clara County answered this question: “in general, do you believe in ghosts?” 225 responded that they believe in ghosts. Test whether it is plausible that, if you could ask all adults in the Santa Clara County this question, less than half would say they believe in ghosts. Use the significance level of 0.01 for this test. Do not forget to follow those five steps. Suppose you believe that your long-time supplier...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT