In: Accounting
I need this question answered assuming that Westgate Construction's contract with Santa Clara County does NOT qualify for revenue recongnition over time... In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows:
2016 | 2017 | 2018 | ||||||
Cost incurred during the year | $ | 2,400,000 | $ | 3,600,000 | $ | 2,200,000 | ||
Estimated costs to complete as of year-end | 5,600,000 | 2,000,000 | 0 | |||||
Billings during the year | 2,000,000 | 4,000,000 | 4,000,000 | |||||
Cash collections during the year | 1,800,000 | 3,600,000 | 4,600,000 |
****IMPORTANT - Complete the requirements assuming that Westgate Construction's contract with Santa Clara County does NOT qualify for revenue recongnition over time.**** |
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. |
2-a. In the journal below, complete the necessary journal entries for the year 2016 (credit "Various accounts" for construction costs incurred). |
2-b. In the journal below, complete the necessary journal entries for the year 2017 (credit "Various accounts" for construction costs incurred). |
2-c. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred). |
3. Complete the information required below to prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract. |
4. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. |
· Note: Question states that Contract DOES NOT QUALIFY for revenue recognition over time. This means that revenue will be recorded when the contract gets completed.
Requirement 1 |
|||
2016 |
2017 |
2018 |
|
Revenue |
$0 |
$0 |
$10,000,000 |
Gross Profits (Loss) |
$0 |
$0 |
$1,800,000 |
Requirement 2A |
||||
Date |
Accounts title |
Debit |
Credit |
|
2016 |
Construction in Progress |
$2,400,000 |
||
Various accounts |
$2,400,000 |
|||
(construction cost incurred) |
||||
2016 |
Accounts receivables |
$2,000,000 |
||
Billing on Construction contracts |
$2,000,000 |
|||
(amount billed during the year) |
||||
2016 |
Cash |
$1,800,000 |
||
Accounts receivables |
$1,800,000 |
|||
(cash received) |
||||
Requirement 2B |
||||
Date |
Accounts title |
Debit |
Credit |
|
2017 |
Construction in Progress |
$3,600,000 |
||
Various accounts |
$3,600,000 |
|||
(construction cost incurred) |
||||
2017 |
Accounts receivables |
$4,000,000 |
||
Billing on Construction contracts |
$4,000,000 |
|||
(amount billed during the year) |
||||
2017 |
Cash |
$3,600,000 |
||
Accounts receivables |
$3,600,000 |
|||
(cash received) |
||||
Requirement 2C |
||||
Date |
Accounts title |
Debit |
Credit |
|
2018 |
Construction in Progress |
$2,200,000 |
||
Various accounts |
$2,200,000 |
|||
(construction cost incurred) |
||||
2018 |
Accounts receivables |
$4,000,000 |
||
Billing on Construction contracts |
$4,000,000 |
|||
(amount billed during the year) |
||||
2018 |
Cash |
$4,600,000 |
||
Accounts receivables |
$4,600,000 |
|||
(cash received) |
||||
2018 |
Construction in Progress |
$1,800,000 |
||
Cost of construction |
$8,200,000 |
|||
Revenue from Long Term contract |
$10,000,000 |
|||
(revenue recognised) |
Requirement 3 |
||||
Balance Sheet [Partial] |
2016 |
2017 |
||
Current Assets: |
||||
Accounts receivables |
$200,000 |
$600,000 |
||
Construction in progress |
$2,400,000 |
$6,000,000 |
||
Less: Billings |
($2,000,000) |
($6,000,000) |
||
Costs and profits in excess of billings |
$400,000 |
$0 |
||
Current Liabilities: |
||||
Accounts Payable |
$0 |
$0 |
||