Question

In: Accounting

At the beginning of 2017, Swifty Construction Company changed from the completed-contract method to recognizing revenue...

At the beginning of 2017, Swifty Construction Company changed from the completed-contract method to recognizing revenue over time (percentage-of-completion) for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2017, pretax income under the two methods was as follows: percentage-of-completion $114,600, and completed-contract $84,000. The tax rate is 40%. Swifty has a profit-sharing plan, which pays all employees a bonus at year-end based on 2% of pretax income.

Compute the indirect effect of Swifty’s change in accounting principle that will be reported in the 2017 income statement, assuming that the profit-sharing contract explicitly requires adjustment for changes in income numbers.

ANSWER 612

Solutions

Expert Solution

Difference in profit-sharing expense—prior years

Pre-tax income—percentage-of-completion..................................... $114,600

Pre-tax income—completed-contract.................................................     84,000

                                                                                                                     $ 30,600

                                                                                                                     X       2%

Indirect effect........................................................................................... $       612

The indirect effect from prior years will be reported as a profit-sharing expense for year 2017.


Related Solutions

Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred...
Swifty Construction Company began work on a $416,400 construction contract in 2017. During 2017, Swifty incurred costs of $277,100, billed its customer for $215,200, and collected $173,900. At December 31, 2017, the estimated additional costs to complete the project total $161,000. Prepare Swifty’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
At the beginning of 2017, the Mini Construction Company received a contract to build an office...
At the beginning of 2017, the Mini Construction Company received a contract to build an office building for $1.2 million. Mini will construct the building according to specifications provided by the buyer, and the project is estimated to take four years to complete. The cost breakdown is as follows. Determine the amount of revenue and gross profit to be recognized each year. (do not include $ in your answer, round to 4 decimal places). 2017 2018 2019 2020 cost incurred...
The board of directors of Sheridan Construction Company is meeting to choose between the completed-contract method...
The board of directors of Sheridan Construction Company is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Sheridan's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Sheridan commenced doing business on January 1, 2021. 2. Construction activities for the year ended December 31, 2021, were as...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Kingbird Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $594,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $267,300 $463,320 $606,000 Estimated costs to complete 326,700 130,680 –0– Progress billings to date 268,000 547,000 896,000 Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Change in Accounting Principle - Retroactive Approach In 2017, The UC Construction Company changed from the...
Change in Accounting Principle - Retroactive Approach In 2017, The UC Construction Company changed from the completed-contract method to the percentage-of-completion method of accounting for long-term construction contracts. The company continued to use the completed-contract method for tax purposes. The tax rate is 30 percent. The comparative income statements issued previously (using the completed-contract method) showed the following: 2017 2016 2015 2014 Construction revenue $520,000 $480,000 $460,000 $350,000 Construction expenses 410,000 390,000 300,000 200,000 Income before taxes 110,000 90,000 160,000...
During 2019, ABC Construction company changed from the cost-recovery method to the percentage-of-completion method for accounting...
During 2019, ABC Construction company changed from the cost-recovery method to the percentage-of-completion method for accounting purposes but not for tax purposes. Gross profit figures under both methods for the past three years appear below:                            Cost-Recovery           Percentage-of-Completion 2017                      $   475,000                        $   900,000 2018                           625,000 1,050,000 2019                           700,000     1,050,000                               $1,800,000 $3,000,000 Assuming an income tax rate of 40% for all years. the effect of this accounting change on prior periods should be reported by a credit of........... Select one: a. $510,000...
Under the completed-contract method:
Under the completed-contract method:Select one:a. Revenue, cost, and gross profit are recognized during the production cycle.b. Costs are recognized during the production cycle, but gross profit recognition is deferred until the contract is completed.c. Revenue, cost, and gross profit are not recognized until the contract is completed.d. Gross Profit is recognized during the production cycle, but net losses are delayed until the contract is completed.
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred...
Waterway Construction Company began work on a $417,400 construction contract in 2017. During 2017, Waterway incurred costs of $280,300, billed its customer for $216,200, and collected $176,500. At December 31, 2017, the estimated additional costs to complete the project total $162,000. Prepare Waterway’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method.
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT