5- On a Design-Build contract, who is responsible for paying to remedy a mistake made by...

5- On a Design-Build contract, who is responsible for paying to remedy a mistake made by a designer who has provided services compliant with the standard of care:

a. Design-build entity

b. Designer

c. Owner

d. Insurance company providing an E&O insurance policy

Solutions

Expert Solution

On a Design-Build contract, who is responsible for paying to remedy a mistake made by a designer who has provided services compliant with the standard of care:

a.Design-build entity


Related Solutions

Engineer E and Owner O are engaged in contract negotiations for E to design and build...
Engineer E and Owner O are engaged in contract negotiations for E to design and build a building for O. The proposed contract is for $200,000. The estimated duration of the turnkey project is 15 months. After reaching an oral agreement of the above, O tells E that they should get together over the next few weeks to hammer out the contract language details for a formal written contract. E begins work without notifying O and completes approximately 30% of...
Insurance Who is responsible for obtaining and paying for the following insurance? 1. Tenant Pays 2....
Insurance Who is responsible for obtaining and paying for the following insurance? 1. Tenant Pays 2. Landlord pays Will the tenant be required to provide proof of insurance? I always suggest clients to say yes, if not any PI will go to you! But however gets this page or part of the assignment can decide, in my sample I stated that tenant needs to proof insurance (upon request) Landlord Improvements Will the landlord be required to make any improvements to...
Who is ultimately responsible for the fatal design flaw? Why? What is the responsibility of a...
Who is ultimately responsible for the fatal design flaw? Why? What is the responsibility of a licensed professional engineer who affixes his/her seal to fabrication drawings?
Problem 5 Sage Corp. enters into a contract with a customer to build an apartment building...
Problem 5 Sage Corp. enters into a contract with a customer to build an apartment building for $1,069,900. The customer hopes to rent apartments at the beginning of the school year and provides a performance bonus of $153,300 to be paid if the building is ready for rental beginning August 1, 2018. The bonus is reduced by $51,100 each week that completion is delayed. Sage commonly includes these completion bonuses in its contracts and, based on prior experience, estimates the...
Who should be responsible for decisions made about how to spend money within the public sector?
Who should be responsible for decisions made about how to spend money within the public sector?
A third party who is intended to directly benefit from a contract made by two contracting...
A third party who is intended to directly benefit from a contract made by two contracting parties, is called an incidental beneficiary T/F If a contract states I assign all my rights under the contract , in most cases the assignment will be considered as assignment of rights but not duties T/F In order for an assignment to be valid, you must use an assignment form T/F A material breach does not discharge the non-breaching party from his obligations under...
Michael received a professional baseball contract paying $7,000,000 per year for 5 years, Bert received a...
Michael received a professional baseball contract paying $7,000,000 per year for 5 years, Bert received a two -year contract for $16,000,000 per year. For purposes of calculations. treat these contracts as ordinary annuities. who's contract has a greater present value if we assume discount rate of 6%? a. bert= $29,334,283 b. Michael = $ 29, 486,547 c. bert= $39,459651 d. Michael = $39,743,196
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT