Xie Company identified the following activities, costs, and
activity drivers for this year. The company manufactures two types
of go-karts: Deluxe and Basic.
Activity | Expected Costs | Expected Activity | ||||
Handling materials | $ | 675,000 | 100,000 | parts | ||
Inspecting product | 950,000 | 1,500 | batches | |||
Processing purchase orders | 155,000 | 700 | orders | |||
Paying suppliers | 225,000 | 500 | invoices | |||
Insuring the factory | 350,000 | 40,000 | square feet | |||
Designing packaging | 125,000 | 2 | models | |||
Required:
1. Compute a single plantwide overhead rate for
the year, assuming that the company assigns overhead based on
125,000 budgeted direct labor hours.
2. In January of this year, the Deluxe model
required 2,500 direct labor hours and the basic model required
6,000 direct labor hours. Assign overhead costs to each model using
the single plantwide overhead rate.
Complete this question by entering your answers in the tabs below.
Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead based on 125,000 budgeted direct labor hours.
In January of this year, the Deluxe model required 2,500 direct labor hours and the basic model required 6,000 direct labor hours. Assign overhead costs to each model using the single plantwide overhead rate. (Round "OH cost" answers to 2 decimal places.)
|
Req 1) | Calculation of Plantwide overhead rate | |||
Overhead rate = Total estimated overhead cost / Total Budgeted direct labour hours | ||||
=2480000/125000 | ||||
19.84 | per direct labour hours | |||
Activity | Expected Costs | |||
Handling materials | 675,000 | |||
Inspecting product | 950,000 | |||
Processing purchase orders | 155,000 | |||
Paying suppliers | 225,000 | |||
Insuring the factory | 350,000 | |||
Designing packaging | 125,000 | |||
Total | 2,480,000 | |||
Req 2 | Deluxe Model | Basic Model | ||
Direct labour hour | 2500 | 6000 | ||
Plantwide overhead rate | 19.84 | 19.84 | ||
Total Overhead allocated | 49600 | 119040 | ||