Question

In: Accounting

Grass Inc. identified the following overhead activities, their respective costs, and their cost drivers to produce...

Grass Inc. identified the following overhead activities, their respective costs, and their cost drivers to produce the three types of lawn mowerss

Type of Mowers

  Activity (Cost)

Cost Driver

Deluxe

Moderate

Economy

  Machine maintenance ($545,600)

  Number of machine hours

220

780

1,200

  Setups ($416,000)

  Number of setups

29

13

6

  Quality control ($203,322)

  Number of inspections

15

34

45

  Rent ($408,100)

  Number of square feet

420

180

110

The company produced the following number of lawn mowers during the prior year.

Deluxe

Moderate

Economy

500

1,440

1,970

1. Grass Inc. currently allocates all overhead costs based on machine hours. Determine the overhead cost per mower for the deluxe type. (choose the closest number).

2. Determine the overhead cost for one unit of economy mower, assuming that Grass Inc. uses an activity-based costing system. (choose the closest number)

Solutions

Expert Solution

Type of Mowers
  Activity (Cost) Activity Costs Cost Driver Deluxe Moderate Economy Total Cost Driver
  Machine maintenance ($545,600) 545600   Number of machine hours 220 780 1,200 2200
  Setups ($416,000) 416000   Number of setups 29 13 6 48
  Quality control ($203,322) 203322   Number of inspections 15 34 45 94
  Rent ($408,100) 408100   Number of square feet 420 180 110 710
1573022
1 Total Overheads 1573022 A
Total Machine Hours 2200 B
Overhead Per MH 715.01 A/B
Allocation of Overhead to Deluxe:
Machine Hours 220 A
Overhead Per MH 715 B
Total Allocation 157302 A*B
Total Units of Deluxe 500
Overhead Per Unit 315
2 Activity Based System:
A B A/B
  Activity (Cost) Activity Costs Cost Driver Deluxe Moderate Economy Total Cost Driver Cost Per Driver
  Machine maintenance ($545,600) 545600   Number of machine hours 220 780 1,200 2200 248
  Setups ($416,000) 416000   Number of setups 29 13 6 48 8,667
  Quality control ($203,322) 203322   Number of inspections 15 34 45 94 2,163
  Rent ($408,100) 408100   Number of square feet 420 180 110 710 575
1573022
Economy Economy
Allocation of Overhead to Deluxe: Cost Drivers Cost Per Driver Overhead Costs
  Machine maintenane 1,200 248 297600
  Setups 6 8,667 52000
  Quality control 45 2,163 97335
  Rent 110 575 63227
Total 510162
Total Units of Economy 1970
Overhead Per Unit 258.97

Related Solutions

Sheridan Publishing identified the following overhead activities, their respective costs, and their cost drivers to produce...
Sheridan Publishing identified the following overhead activities, their respective costs, and their cost drivers to produce the three types of textbooks the company publishes. Type of Textbook Activity (Cost) Cost Driver Deluxe Moderate Economy Machine maintenance ($360,000) Number of machine hours 300 900 1,200 Setups ($640,000) Number of setups 30 15 5 Packing ($168,000) Number of cartons 15 35 55 Photo development ($680,000) Number of pictures 4,500 2,500 1,500 Deluxe textbooks are made with the finest-quality paper, six-color printing, and...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year:...
Orange, Inc. has identified the following cost drivers for its expected overhead costs for the year: Total overhead budgeted = $200,000 Total direct labor hours budgeted = 2,000 hours Actual direct labor hours worked on Job 21 = 100 Actual direct materials = $5,000 total Actual direct labor = $3,000 total Actual units completed = 100 The totoal cost of Job 21 is: a. $ 22,500 b. $ 16,000 c. $ 18,000 d. $ 19,900 The Total Cost of Job...
DAB Company has identified the following overhead activities, costs, and activity drivers for the coming year:...
DAB Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity                                Expected Cost          Activity Driver               Activity Capacity Material-handling costs.. £45,000             Number of moves.........        450 Machine costs................ £80,000             Machine hours.............. 20,000 Order costs.................... £15,000             Number of orders.........        750 Receiving costs.............. £30,000             Number of parts........... 50,000 Setup costs.................... £50,000             Number of setups.........        250 Assume that each activity corresponds to a process. DAB’s normal activity is 5,000 direct labor hours. The following two jobs...
5) A company has identified the following overhead costs and cost drivers for the coming year:...
5) A company has identified the following overhead costs and cost drivers for the coming year: Overhead Item Cost Driver Budgeted Cost Budgeted Activity Level Machine setup Number of setups $ 20,000 200 Inspection Number of inspections 130,000 6,500 Material handling Number of material moves 80,000 8,000 Engineering Engineering hours 50,000 1,000 Total $280,000 The following information was collected on three jobs that were completed during the year: Job 101 Job 102 Job 103 Direct materials $5,000 $12,000 $8,000 Direct...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go-karts: Deluxe and Basic. Activity Expected Costs Expected Activity Handling materials $ 710,000 100,000 parts Inspecting product 985,000 1,500 batches Processing purchase orders 190,000 700 orders Paying suppliers 260,000 500 invoices Insuring the factory 385,000 40,000 square feet Designing packaging 160,000 2 models Assume that the following information is available for the company’s two products for the first quarter of this...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures...
Xie Company identified the following activities, costs, and activity drivers for this year. The company manufactures two types of go-karts: Deluxe and Basic. Activity Expected Costs Expected Activity Handling materials $ 675,000 100,000 parts Inspecting product 950,000 1,500 batches Processing purchase orders 155,000 700 orders Paying suppliers 225,000 500 invoices Insuring the factory 350,000 40,000 square feet Designing packaging 125,000 2 models     Required: 1. Compute a single plantwide overhead rate for the year, assuming that the company assigns overhead...
Xie Company identified the following activities, costs, and activity drivers for 2015. The company manufactures two...
Xie Company identified the following activities, costs, and activity drivers for 2015. The company manufactures two types of go-karts: Deluxe and Basic.        Activity Expected Costs Expected Activity   Handling materials $ 625,000      100,000 parts   Inspecting product 900,000      1,500 batches   Processing purchase orders 105,000      700 orders   Paying suppliers 175,000      500 invoices   Insuring the factory 300,000      40,000 square feet   Designing packaging   75,000    2 models Assume that the following information is available for the company’s two products...
Xie Company identified the following activities, costs, and activity drivers for 2017. The company manufactures two...
Xie Company identified the following activities, costs, and activity drivers for 2017. The company manufactures two types of go-karts: Deluxe and Basic. Activity Expected Costs Expected Activity Handling materials $ 625,000 100,000 parts Inspecting product 900,000 1,500 batches Processing purchase orders 105,000 700 orders Paying suppliers 175,000 500 invoices Insuring the factory 300,000 40,000 square feet Designing packaging 75,000 2 models Assume that the following information is available for the company’s two products for the first quarter of 2017. Deluxe...
Fischer Company identified the following activities, costs, and activity drivers: Activity Expected Costs Expected Activity Handling...
Fischer Company identified the following activities, costs, and activity drivers: Activity Expected Costs Expected Activity Handling Parts 425,000 25,00 parts in stock Inspecting Parts 390,000 940 batches Processing Purchase Orders 220,000 440 orders Designing Packaging 230,000 5 models a. Compute a plantwide overhead rate assuming the company assigns overhead based on 70,000 budgeted direct labor hours (Round to two decimals). b. Compute separate rates for each of the four activities using the activity-based costing.
Equally Accurate Reduced ABC System Silven Company has identified the following overhead activities, costs, and activity...
Equally Accurate Reduced ABC System Silven Company has identified the following overhead activities, costs, and activity drivers for the coming year: Activity Expected Cost Activity Driver Activity Capacity Setting up equipment $126,000 Number of setups 150 Ordering materials 18,000 Number of orders 900 Machining 126,000 Machine hours 10,500 Receiving 30,000 Receiving hours 1,250 Silven produces two models of cell phones with the following expected activity demands: Model X Model Y Units completed 5,000 10,000 Number of setups 100 50 Number...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT