Question

In: Accounting

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019.

Expenditures on the project were as follows:

January 1, 2018 $ 1,420,000
March 1, 2018 1,140,000
June 30, 2018 1,340,000
October 1, 2018 1,140,000
January 31, 2019 351,000
April 30, 2019 684,000
August 31, 2019 981,000

On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $6,000,000 and $9,000,000 with interest rates of 8% and 10%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:
1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the specific interest method.
2. What is the total cost of the building?
3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

Solutions

Expert Solution

Summary of Answer
Answer 1 Interest capitalized in 2018 $             399,000
Answer 1 Interest capitalized in 2019 $             512,460
Answer 2 Total cost of the building $         7,967,460
Answer 3 Interest expense in 2018 $         1,449,000
Answer 3 Interest expense in 2019 $         1,335,540

Calculation Parts

Specific interest method
Expenditure for 2018
Expenditure for 2018 Amount Time factor
01-Jan-18          1,420,000 12/12              1,420,000
01-Mar-18          1,140,000 10/12                 950,000
30-Jun-18          1,340,000 6/12                 670,000
01-Oct-18          1,140,000 3/12                 285,000
Accumulated capital Expenditure before interest capitalized          5,040,000
Average Accumulated capital Expenditure              3,325,000
Interest capitalized in 2018
Average Accumulated capital Expenditure Multiplied by: interest rate Interest capitalized in 2018
                                             3,325,000 12.00%              399,000
Total capitalized value in 2018          5,040,000              399,000              5,439,000
Expenditure for 2019
Expenditure for 2019 Amount Time factor
01-Jan-19          5,439,000 9/9              5,439,000
31-Jan-19              351,000 8/9                 312,000
30-Apr-19              684,000 5/9                 380,000
31-Aug-19              981,000 1/9                 109,000
Accumulated capital Expenditure before interest capitalized          7,455,000
Average accumulated capital Expenditure              6,240,000
Weighted average rate for other debt
                                             6,000,000 8.00%              480,000
                                             9,000,000 10.00%              900,000
15,000,000          1,380,000
Weighted average rate for other debt (Total interest/Total loan )          1,380,000 15,000,000 9.20%
Interest capitalized in 2019
For construction loan 3,900,000 12.00%                 468,000
Other debt (6240000-3900000) 2,340,000 9.20%                 215,280
Interest for annual                 683,280
Interest capitalized in 2019 (683280*9/12)                 512,460
Interest expense charged to income statement
Construction loan          3,900,000 12.00%                 468,000
Other debt 1          6,000,000 8.00%                 480,000
Other debt 2          9,000,000 10.00%                 900,000
Total interest paid              1,848,000
Interest expense charged to income statement
Year 2018 2019
Total interest paid          1,848,000              1,848,000
Less: interest capitalized              399,000                 512,460
Interest expense charged to income statement          1,449,000              1,335,540
Total cost of the building
Expenditure in 2018              5,040,000
Interest capitalized in 2018                 399,000
Expenditure in 2019              2,016,000
Interest capitalized in 2019                 512,460
Total cost of the building              7,967,460

Related Solutions

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,940,000 March 1, 2018 1,680,000 June 30, 2018 1,880,000 October 1, 2018 1,680,000 January 31, 2019 432,000 April 30, 2019 765,000 August 31, 2019 1,062,000 On January 1, 2018, the company obtained a $4,800,000 construction loan with a 14% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,850,000 March 1, 2018 1,500,000 June 30, 2018 1,700,000 October 1, 2018 1,500,000 January 31, 2019 405,000 April 30, 2019 738,000 August 31, 2019 1,035,000 On January 1, 2018, the company obtained a $4,500,000 construction loan with a 12% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT